HomeMy WebLinkAbout5.a. Stormwater Management Plan Discussion - ENG 0089 �OJ�I�IOt.Il r 1 EXECUTIVE SUMMARY
UTILITY COMMISSION
Utility Commission Meeting: March 12, 2012
AGENDA ITEM: Stormwater Management Plan AGENDA SECTION:
Discussion — ENG 0089 Ole
ktc 11i t S5
PREPARED BY: Andrew J. Brotzler, PE, Director of Public AGENDA NO. ' /; A
Works /City Engineer "
ATTACHMENTS: Memorandum and Exhibits APPROVED BY: lq*
RECOMMENDED ACTION: Discussion
BACKGROUND
At the last Utility Commission meeting, a preliminary review of the City's storm water area charges and
utility rates was discussed. During this discussion, the City's current Comprehensive Surface Water
Management Plan (SWMP) and strategies were also discussed along with alternative methods for overall
management of storm water and flood protection within the city. Since this time, Mayor Droste, staff and
Pete Willenbring have met to discuss various options for storm water management then constructing an
overflow to the Mississippi River.
The attached memorandum highlights the existing components of the current SWMP and includes a
comparison of options and impacts for discussion and evaluation. Additionally, the two attached exhibits
highlight the impact of a critical event based on the current storm water system.
Pete Willenbring with WSB & Associates, Inc. will be in attendance at the meeting to review the options
that may be considered as a change to the City's current SWMP.
C:\ Users \ajd \AppData \Local \Microsoft \Windows \Temporary Internet Files \Content.Outlook \ONLP97EA \20120312 UC Stormwater Management Plan
Update.doc
WSB
&Assoc- Engineering • Planning • Environmental • Construction 701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 - 541 -4800
Fax: 763 - 541 -1700
Memorandum
To: Rosemount Utility Commission
From: Pete Willenbring, PE
Date: March 8, 2012
Re: Review of Options Available to Accommodate Stormwater Runoff Generated from
the City of Rosemount
WSB Project No. 1916 -24
INTRODUCTION/BACKGROUND
This memorandum has been prepared as a follow up to the request by the Utility Commission to
review the feasibility of converting to a stormwater plan that would develop storage and
infiltration systems within eastern Rosemount instead of using the currently proposed pipe and/or
open ditch overflow system to the Mississippi River.
The Cities stormwater plan currently anticipates the construction of a pipe or open ditch
overflow to the Mississippi River to accommodate runoff from rainfall exceeding a 100- year /24-
hour duration event (6 inches in 24- hours). The piped overflow system would accommodate the
additional runoff volume generated by longer duration events such as a 10 -day snowmelt event
which creates approximately two times the runoff volume from a 100 -year 24 -hour duration
event. It has been determined that the 100 - year /10 -day runoff event (snowmelt condition) is the
critical event for flooding within the City of Rosemount.
The Commission is also advised that should a 100 -year runoff event occur, because we have not
yet constructed a pump that would provide a positive outlet from Shannon Pond and the outlet
from the Bloomfield development is not yet complete, if no overflow is provided it is anticipated
that approximately 50 structures could be inundated in and around Shannon Pond, and up to 135
structures could be inundated in the Bloomfield development (Figure 1A and 1B).
Minneapolis • St. Cloud
Equal Opportunity Employer
CdUsers tajbVsppDato\LocalUticrosofl\Windows \Temporary Inland Files \ContatlOutlook\RTQJIJOI\MEMO utility commission 030612.doc
Rosemount Utility Commission
March 8, 2012
Page 2
Outlined below please find a listing of the various features associated with the two systems.
These systems will be discussed in more detail during the Utility Commission meeting on
Monday March 12, 2012.
Storage /Infiltration System capable of
Storm Sewer Overflow to Mississippi River handling 10 day runoff volume with no
discharge
• Pipe outlet from basin 1864 (Bloomfield • Pipe outlet from basin 1864 (Bloomfield
development) would be finished and outfall development) would be finished, outfall to
to the Flint Hills property and be the Flint Hills property and be operational
operational (Figure 2). (Figure 2).
• Pipe overflow conveyance system • A storage /infiltration system capable of
constructed to river with capacity of 800 handling a 10 -day runoff overflow volume
cfs at outfall into river. This system would with no discharge would need to be
be capable of overflowing 16,000 acre feet developed. It would need to create storage
to the river over a 10 day period. for approximately 8,000 acre feet of water
within the community.
• Approximately 30 acres of permanent • To accommodate the 10 -day runoff volume
easements would be required to facilitate overflow, if the average depth of
installation of the pipe outfall downstream stormwater storage was 5 feet, 1,600 acres
of Bloomfield to the river of land would need to be reserved for this
purpose. This could be provided as part of
development or redevelopment, through the
creation of regional ponding systems, or
both.
• If ponding was provided as redevelopment
takes places, for each 100 acre site
approximately 25 acre feet of additional
stormwater storage would be required
compared to the storm sewer overflow
alternative.
• Cost to construct trunk line estimated at • The cost to construct storage /infiltration
$30 million. system estimated as follows:
o Cost for excavation estimated to
range from $20 to 65 million
dollars
o Cost for land (1600 acres)
o Cost for regional improvements.
See attached for description of
regional improvements that were
identified to be feasible and cost
effective.
C AUserstajbWppDataLLocal\Microsoft Wmdows\Temporary Inland Film \Contan.Outlook\RIVJUORMEMO ufilitycommission O30612.doc
Rosemount Utility Commission
March 8, 2012
Page 3
• Limited loss of tax base anticipated over • Stormwater storage /infiltration areas could
easement area as pipe alignment would be not typically have structures placed within
typically placed in road right -of -areas or in their footprint and would likely reduce
areas as part of development in a way to developable area (See Figure 2).
reduce impact on buildable areas.
• System will have capability to overflow up
to 16,000 acre feet every 10 days.
• Construction of trunk system will reduce • Storage /infiltration areas will still require
size and need for lateral conveyance system lateral system to direct water to regional
in many areas. areas and/or serve as overflow routes. If
storage /infiltration systems are provided on
each site as they develop, the need for and
cost of lateral system could be reduced.
• Storm sewer outfall provides draw down • Storage /infiltration system must infiltrate
capability following event to provide for runoff at 30 day critical duration runoff
flood protection for longer duration events volumes to provide flood protection.
(30 days).
• Existing plan is approved by the • Updated plan will need to be approved by
Vermillion River Watershed Vermillion River Watershed, Empire
Township, Ninenger Township, and Flint
Hills Resources
• If approved by the above agencies, unlikely
the City will be given allocation from
MPCA for future pollutant or volume
discharge to the Mississippi River.
• Schedule: To provide flood protection for • Schedule: Regional improvements would
residents in and around Shannon Pond and need to be constructed to accommodate
Bloomfield developments, downstream overflow from upstream area tributary to
outlet improvements will need to pond in Bloomfield development.
completed. • Require agreement with UMore to impound
water on their property without future
discharge.
• Require agreement with Flint Hills to
impound water within their property
without future discharge.
C:\ Users\ajb\AppData\Local\Microsoft \Windows \Tanporary Intana Files \Contan.Outlaok\RTQJUOI\MEMO utility comnussion 030612.doc
t r c Y t
r
:� 150T��H STREET s _ �"
' e H Cis i 1 `r .4''..—.1411 ° 11 , ! FTT
. `� i � :4 4 I, i APPROX. CTUR 94 TO 1.02 ._ I �.
�' , y STRUCTURE [MPACTEDt. 1
"-I � ' AT EL EV• 9 38 ` EEE , 938
Ili .. F . t 2439 '�' `» ' `
r 6 00 STORAGE ELT
� , F Al 3. ELEV• 938 2 r * . 9< . r:. 24
Z > M rCb 4 "
g 1
liir 0_ . , � t A-, 7. r y Z 7 s ' e ft •• ;� �� ,s� , d . ,...i'.4 ...-4-4 y f
,GFRN ]] ZZ 'r x
►� WACHTER L�. ' 1
�,`` .�- "��� " "'' •. ' c REV 9 40 STRUCTURE I MPACT '
r .,�...�'' . °' N 'ELEV. — 92
4 + "�STRUCTURE l PACT
EL 950 0,
#' ° E LEV. - 927.0. , 1r ," . WL H E 906' E ,'
K
r ; PPROx 50 - 57 - , r , . T 3 FLOOD ii t�
y STRUCTURES I MPACTED _. _le, 9 . +' —
5
H
u�
ELEV. 9 18 920 ,
ii r AT ELEV• 930° r k n ELEy w 1 , ..
' fit 4-4.4„: ' ��'# w
1 ,, . � { .. +, Q r1,
a ■err 4, yit -r 0
' . ORA E � ELEV. '''� �:r.l�*''i w t //fiy
'�', - z ELEV• 930 U
.160TH STREET �.
T
fL
LEGEND
SHANNON POND
AREA INUNDATED TO EOF —ELEV 930 A
WACHTER LAKE
AREA INUNDATED TO ELEV 938
I.
m
Flood Protection Analysis MB Project Nc 1916.24 Date March 7 2012
,., 701 Xenra Avenue South. Suite 300
WSB
Minneapolis MN 55418 100 - fear 10-Day Runo F:rient
�»vw wsbeng corn I u re
hter ff Lake
Shannon Pond & War
9
•
1 ;45TRJ- F': , Erk;'kEEfio6 %pieeyf • :AV5TRUC1Cn Rosemount, Minnesota
• I i • \(
iAr: r r „... ,r. f
, TPA IL ,
r,,, . 4 r . �. r Cr r Z f f' t r r , ' f ' , s rt,
0.
.. AfflIrFF 1 M
r' f • t 1 F.
f i f r t t r • IN MINI
rrr r T ,V ; gyp , 737
j
rrrr
k , r / / ? 3
r 1 • ", ),4 - t r ' g : I 1783
4 5 r _ _
� STRUCTURE I PACTS
,_, ,F.,, ' e,. - ELEV. — 922.3
r .. r F _
t' 1 . ' „ ' . 1F, ,, #(_t �, 1816
030-135 STRUCTUF , ,T - /
, 1 , r ,14Ft nw r! EV. 938y_,, • • i EMERGE CY OVERFLO
r tr ■ :., E L E — 9 38
145TH STREET.__ . , µ„",
RO.D LOW PO1 T
"�,” ' ELEV. — 922 ,
16' DEEP I U DATIO
v . )
i
( : f t 1 c r };� -' .err, : _
r,
V ,. , -----1--
2019 i l i 1 t „
r
,vrr.rr rt +,Y -, ,T ,
* ,-, I ,,,
2097
2104
I
Flood Protection :Anal sis WSB Project No 1916.24 Date March 7 2612
- 701 Xenia a Avenue South. Suite 300
WSB Minneapolis. MN 55416
`"`”" "'g`°"' 100-1 car 10 -Dad Runoff 1:vcnt
Figure
Bloomfield Development
'3.5'� ��0nM' 'P Rosemount, Minnesota •
INF.3hSTRJCTURE . ENG IEEP op y: .10K5TRUC'T A