HomeMy WebLinkAbout6.j. Payment #4 & Final – Hawkins Sanitary Sewer Extension, City Project 438 4 ROSEN4OUPJT EXECUTIVE SUMMARY
CITY COUNCIL
City Council Meeting: August 6, 2012
AGENDA ITEM: Payment #4 & Final, Hawkins Sanitary AGENDA SECTION:
Sewer Extension, City Project 438 Consent
PREPARED BY: Andrew J. Brotzler, PE, Director of P AGENDA NO.
Works / City Engineer t i(j .
ATTACHMENTS: Payment Voucher; Map APPROVED BY:
04.1
RECOMMENDED ACTION: Motion to Approve Payment #4 and Final for the Hawkins
Sanitary Sewer Extension, City Project 438, to C. W. Houle, Inc. and Accepting it for
Perpetual Maintenance.
BACKGROUND:
This item is on the agenda to request Payment #4 and Final to C. W. Houle, Inc. for the Hawkins Sanitary
Sewer Extension, City Project 438. The final construction amount of $172,326.04 is 0.3% below the
contract amount of $172,812.00.
This project included the extension of trunk sanitary sewer service from the existing trunk sanitary sewer
main along Highway 52 to the Hawkins, Inc. and Feed Products North, Inc. sites. This project was
jointly- funded by Hawkins, Inc. and Feed Products North, Inc. Hawkins, Inc. has paid their portion in
cash, while Feed Products North, Inc. has executed a Petition and Waiver Agreement with the City to have
their portion of the cost assessed.
SUMMARY:
Staff recommends that Council approve Payment #4 and Final for the project and accept the project for
perpetual maintenance subject to the following conditions.
1. Satisfactorily showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year maintenance bond.
G: \ENGPROJ \438 \20120806 CC Pymt 41-Final Payment.docx
6- z 7
WSB
llal Engineering • Planning • Environmental • Construction 701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 -541 -4800
Fax: 763 - 541 -1700
June 13, 2012
Mr. Andy Brotzler, PE
City Engineer
City of Rosemount
2875 — 145 Street West
Rosemount, MN 55068
Attn: Cindy Dorniden, City of Rosemount
Re: Construction Pay Voucher No. 4 (Final)
Hawkins Sanitary Sewer Extension
City of Rosemount Project No. 438
WSB Project No. 1916 -46
Dear Mr. Brotzler:
Please find enclosed Construction Pay Voucher No. 4 and final for the above - referenced project in the
amount of $10,052.09.
Also enclosed are the following documents required for processing final payment for the above -
referenced project:
1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax (IC134 forms).
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured (lien waivers).
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year Maintenance Bond (warranty start date to coincide with the date Council approves final
payment).
We recommend that you make final payment in the amount of $10,052.09 to C. W. Houle, Inc. at your
earliest convenience. Please contact me at 651- 322 -2015 if you have any questions or comments
regarding the attached information. Thank you.
Sincerely,
WSB & Associates, Inc.
c20011640
Phil Olson, PE
Project Engineer
Enclosures
cc: Cindy Dorniden, City of Rosemount srb
Minneapolis • St. Cloud
Equal Opportunity Employer
C:I Leers end IppDato oral Microsoft IF - indows:Tempornry Internet Files lContenc Outlook JOD1XJ5J'438 LTR P0 4 I. C7T -n brotzler- 061112 .dor
WSB
& Asso Engineering • Planning • Environmental • Construction 701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 -541 -4800
Fax: 763 - 541 -1700
June 13, 2012
Mr. Bryan Houle
C. W. Houle, Inc.
1300 West County Road I
Shoreview, MN 55126
Re: Construction Pay Voucher No. 4 (Final)
Hawkins Sanitary Sewer Extension
City of Rosemount Project No. 438
WSB Project No. 1916 -46
Dear Mr. Houle:
Please find enclosed Construction Pay Voucher No. 4 and final (in triplicate) for the above - referenced
project for your review and signature. Please sign all three originals and return to the City of
Rosemount for processing.
Please note that the original signed vouchers must be accompanied by the following documents when
submitting for final payment.
1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax (IC 134 forms).
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured (lien waivers).
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year Maintenance Bond (warranty start date to coincide with the date Council approves final
payment).
If you have any questions or concerns, please contact me at 651- 322 -2015. Thank you for your prompt
attention to this matter.
Sincerely,
WSB & Associates, Inc.
Phil Olson, PE
Project Engineer
Enclosures
cc: Andy Brotzler, City of Rosemount
Cindy Dorniden, City of Rosemount srb
Minneapolis • St. Cloud
Equal Opportunity Employer
C 1 Leers'cadAppData LocaLlficros ft Windows Temporary Internet Files Content Outlook IQD6_V5JU38 LTR IV 4 FNL CTR -b horde - 061312 riot
AIL Owner: City of Rosemount Date: 6/7/2012
2875 145th Street West
W Rosemount, MN 55068 -4941
For Period: 5/1/2012 to 5/31/2012 Request No.: 4 & FINAL
Contractor: C. W. Houle, Inc.
AININI 1300 W County Road I
Associates, Inc, Shoreview, MN 55126
Pay Voucher
RSMT - Hawkins Sanitary Sewer Extension
Client Contract No.:
Project No.: 01916 -46
Client Project No.: 438
Project Summary
1 Original Contract Amount $172,812.00
2 Contract Changes - Addition $0.00
3 Contract Changes - Deduction $0.00
4 Revised Contract Amount $172,812.00
5 Value Completed to Date $172,326.04
6 Material on Hand $0.00
7 Amount Earned $172,326.04
8 Less Retainage $0.00
9 Subtotal $172,326.04
10 Less Amount Paid Previously $162,273.95
11 Liquidated Damages $0.00
12 AMOUNT DUE THIS PAY VOUCHER NO. 4 & FINAL $10,052.09
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT THE
CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL VOUCHER HAS
BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE WITH, AND PURSUANT
TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER.
Recommended for Approval by: Construction Observer:
WSB & Associates, Inc.
Approved by Contractor: Approved by Owner:
C. W. Houle, Inc. City of Rosemount
Specified Contract Completion Date: Date:
12/31/2011
Comment:
Page 1
Hawkins, Inc. Sanitary Sewer Extension rT ROSEMOUNT
a s s
i ; S S
•N
,i
Er
4 �a
L Y_
cep
/�sq{ ,
V \ y 0 t
#
,
5
� t
f
,E
fS tr.
2. s
t o
d
Z;
0 �
i--
1 E '' I _0
U 52
w
ii
z
' _...,.1401 _ST E,5, - r.._ . .,__ , ,e __ :55---- - _ .� , -55.— .__. 1 40341 .ST.
0
a
Hi
0
0
145TH ST SAN 42) 145TH ST E
0 875 1,750 3,500 5,250 7,000
iFeet
Septem ber 2011
T: /GIS /City /Maps/Departmental Maps /Engineering /Chris /Location Map - 438