HomeMy WebLinkAbout6.h. Payment 3 & Final – Lift Station 1 Improvement, City Project 4404ROSEMOUNTEXECUTIVE SUMMARY
CITY COUNCIL
City Council Meeting: February 5, 2013
AGENDA ITEM: Payment #3 & Final — Lift Station #1
AGENDA SECTION:
Improvement, City Project 440
Consent
PREPARED BY: Andrew J. Brotzler, PE, Director of lic
AGENDA NO.
Works / City Engineer
ATTACHMENTS: Payment Voucher, Map
APPROVED BY:
RECOMMENDED ACTION: Motion to Approve Payment #3 and Final for the Lift Station
#1 Improvement, City Project 440, to Magney Construction, Inc. and Accepting it for
Perpetual Maintenance.
BACKGROUND:
This item is on the agenda to request Payment # 3 and Final to Magney Construction, Inc. for the Lift
Station # 1 Improvement, City Project 440.
The final construction amount of $95,806 is 3.8% below the contract amount of $99,555.
The project was funded by the City Sanitary Sewer Utility Fund.
SUMMARY:
Staff recommends that Council approve Payment # 3 and final for the project and accept the project for
perpetual maintenance subject to the following conditions.
1. Satisfactorily showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year maintenance bond.
G: \ENGPROJ\440 \20130205 CC Payment 3&Final.docx
A
WSB
AAssx Engineering ■ Planning a Environmental ■ Construction
December 7, 2012
Mr. Mark Magney
Magney Construction, Inc.
1401 Park Road
Chanhassen, MN 55317
Re: Construction Pay Voucher No. 3 (Final)
Lift Station No. 1 Improvements
City Project No. 440
City of Rosemount, MN
WSB Project No. 1916 -400
Dear Mr. Magney:
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763- 541 -4800
Fax: 763 - 541.1700
Please find enclosed Construction Pay Voucher No. 3 and final (in triplicate) for the above - referenced
project for your review and signature. Please sign all three originals and return to Phil Olson at the
City of Rosemount for processing. Please note that the original signed vouchers must be accompanied
by the following documents when submitting for Final payment.
i . Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax (IC 134 forms).
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured (lien waivers).
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year Maintenance Bond (warranty start date to coincide with the date Council approves final
payment).
If you have any questions or concerns, please contact me at 763 -287 -7193. Thank you for your prompt
attention to this matter.
Sincerely,
WSB & Associates, Inc.
Kevin B. Kawlewski, PE
Senior Project Engineer
Enclosures
cc: Phil Olson, City of Rosemount
Cindy Dorniden, City of Rosemount srb
Minneapolis . St. Cloud
Equal Opportunity Employer
I'.!'ur: tl- .4— I'e.y.—l—, hl" C'emrrx(Mtkxd KC01,,61>t' Ilut.IR W S FXI.[7R+u
Owner: City of Rosemount
2875 145th Street West
WSB Rosemount, MN 55068 -4941
For Period: 8/1/2012 to 11/30/2012
Contractor: Magney Construction, Inc.
1401 Park Road
& Assoeraies, Inc. Chanhassen, MN 55317
Pay Voucher
RSMT - Lift Station No. 1 Modifications
Client Contract No.:
Project No.: 01916 -40
Client Project No.: 440
Date: 12/5/2012
Request No.: 3 & FINAL
Project
Summary
1
Original Contract Amount
$99,555.00
2
Contract Changes - Addition
$0.00
3
Contract Changes - Deduction
$0.00
4
Revised Contract Amount
$99,555.00
5
Value Completed to Date
$95,806.00
6
Material on Hand
$0.00
7
Amount Earned
$95,806.00
8
Less Retainage
$0.00
9
Subtotal
$95,806.00
10
Less Amount Paid Previously
$81,106.25
11
Liquidated Damages
$0.00
12
AMOUNT DUE THIS PAY VOUCHER NO. 3 & FINAL
$14,699.75
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT
THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL
VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE
WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER.
Reco mended f App oval by:
W S B s I
Approved by Contractor:
Malin eyronstiuction, Inc.
Specified Contract Com
8/15/2012
Comment:
Date:
Construction Observer:
Nor, 4J. 0
Date:
Paae 1
Project Material Status
Item
No. I
Item
Description
Units
I I
Unit Price
I
Contract
Quantity I
Quantity to
Date
Current
Quantity I
Amount to
Date
SCHEDULE A - SITE WORK
1
2021.5011
MOBILIZATION (5 %)
LUMP SUM
$4,000.00
1
1
0.25
$4,000.00
2
2101.511
CLEARING AND GRUBBING
LUMP SUM
$500.00
1
1
0
$500.00
3
2104.505
REMOVE BITUMINOUS PAVEMENT
SO YD
$40.00
5
5
0
$200.00
4
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
$6.00
50
50
0
$300.00
5
2105.501
COMMON EXCAVATION (P)
CU YD
$25.00
30
30
0
$750.00
6
2112.601
SUBGRADE PREPARATION
LUMP SUM
$1,000.00
1
1
0
$1,000.00
7
2211.501
AGGREGATE BASE CLASS 5
TON
$30.00
40
40
0
$1,200.00
8
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (2,C)
TON
$100.00
30
28
0
$2,800.00
9
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
$50.00
6
6
0
$300.00
10
2575.505
SODDING, TYPE LAWN (INCL. TOPSOIL & FERT.)
SQ YD
$7.00
15
151
0
$105.00
Totals For Section SCHEDULE A - SITE WORK:
1 $11,155.00
SCHEDULE B - LIFT STATION MODIFICATIONS
11
2503.601
SANITARY SEWER BYPASS PUMPING
LUMP SUM
$11,000.00
1
1
0
$11,000.00
12
12506.6011
LIFT STATION MODIFICATIONS
I LUMP SUM
J$67,600.001
11
11
0.05
$67,600.00
Totals For Section SCHEDULE B - LIFT STATION MODIFICATIONS:
$78,600.00
ALTERNATE 7 - NEW SUBMERSIBLE PUMPS
13 12506.601 1 F &I NEW SUBMERSIBLE PUMPS ILUMPSUMI $9,600.001 11 0.6303131 0.630313
$6,051.00
Totals For ALTERNATE 1 - NEW SUBMERSIBLE PUMPS:
$6,051.00
Project Totals:
$95,806.00
Pave 7
Project Payment Status
Owner: City of Rosemount
Client Project No.: 440
Client Contract No.:
Project No.: 01916 -40
Contractor: Magney Construction, Inc.
Contract Chancies
No.
Type
I Date
IDescription
Amount
Change Order Totals:
1 $0.00
Payment Summary
No.
From
Date
To Date
Payment
Total
Payment
Retainage
Per
Payment
Total
Retainage
Total
Payment +
Retainage
Work
Certified Per
Payment
Total Work
Certified
1
6/11/2012
6/30/2012
$63,137.00
$63,137.00
$3,323.00
$3,323.00
$66,460.00
$66,460.00
$66,460.00
2
7/1/2012
7/31/2012
$17,969.25
$81,106.25
$945.75
$4,268.75
$85,375.00
$18,915.00
$85,375.00
3&
FINAL
8/1/2012
11/30/2012
$14,699.75
$95,806.00
($4,268.75)
$0.00
$95,806.00
$10,431.00
$95,806.00
Payment Totals:
$95,806.00
$0.00
$95,806.00
$95,806.00
Proiect Summary
Material On Hand:
Total Payment to Date:
Total Retainage:
Total Amount Earned:
$0.00
$95,806.00 Original Contract:
$0.00 Contract Changes:
$95,806.00 Revised Contract:
$99,555.00
$0.00
$99,555.00
PaoP 'Z
Central
Park
ROSEM
1 46TH �ST t
0 90 180 360 540 720
Feet
T: /GIS /City /Maps /Departmental Maps /Engineering /Chris /Location Map - 440
N
March 2012
WSB
& Associates, Inc.
Engineering a Planning ■ Environmental ■ Construction
December 7, 2012
Mr. Mark Magney
Magney Construction, Inc.
1401 Park Road
Chanhassen, MN 55317
Re: Construction Pay Voucher No. 3 (Final)
Lift Station No. 1 Improvements
City Project No. 440
City of Rosemount, MN
WSB Project No. 1916 -400
Dear Mr. Magney:
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 -541 -4600
Fax: 763 -541 -1700
Please find enclosed Construction Pay Voucher No. 3 and final (in triplicate) for the above - referenced
project for your review and signature. Please sign all three originals and return to Phil Olson at the
City of Rosemount for processing. Please note that the original signed vouchers must be accompanied
by the following documents when submitting for final payment.
1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax (IC 134 forms).
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured (lien waivers).
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year Maintenance Bond (warranty start date to coincide with the date Council approves final
payment).
If you have any questions or concerns, please contact me at 763 - 287 -7193. Thank you for your prompt
attention to this matter.
Sincerely,
WSB & Associates, Inc.
I�_ �-_1
Kevin B. Kawlewski, PE
Senior Project Engineer
Enclosures
cc: Phil Olson, City of Rosemount
Cindy Dorniden, City of Rosemount srb
Minneapolis ■ St. Cloud
Equal Opportunity Employer
C. r)en kkt 1At ApplA,#.1n,d,tTicw 011-- :, Trx1- -lxk— thle., 0.1, O.M.AA( *WAA1V440L1R 103 PAL CTR -xrn ng,.;rr:l /,