HomeMy WebLinkAbout8a. City Projects UpdateCity Projects Update
G:\ENGPROJ \Project Tracking \Project Update Updated: 07/03/2013
Council
city
Project
Project Name
Council
Authorizes
Public
Receives
Plans/Specs.
Open Bids
Award
Start Date
Assessment
Contractor
Contract
Amount
Payments
To Date
Complete
Summary
Number
Plans/Specs
Hearing
Authorize Ad
Contract
Hearing
For Bid
433
Bella Vista
N/A
N/A
Construction is planned for 2014.
(Marshes of Bloomfield)
439
Greystone 1 st
05/15/12
N/A
06/05/12
06/22/12
07/03112
07/16/12
N/A
Kuechle Underground,
Inc.
$828,569
$818,630
99%
Project is substantially compete.
The project includes construction of a 10 -fool high x 14 -foot wide
pedestrian underpass under TH 3, approximately 360 feet north of
443
Trunk Highway 3 Underpass
05/15/12
N/A
04/02/13
04/26/13
05/07/13
05/20/13
N/A
Minnesota Dirt Works,
$745,894
142nd Street, adjacent to the Rosemount High School athletic
Inc.
facilities. Construction has begun and is expected to be completed
before school begins in September.
444
Prestwick Place 4th
08/21/12
N/A
08/21/12
08124/12
09/04/12
09/17/12
N/A
Kuechle Underground,
Inc.
$977,099
$910,501
93%
Project is substantially compete.
Mill and overlay improvements to 155th Street West, the Carrollton
445
2013 Street Improvement
12/04/12
12/04112
02/05/13
02/22/13
04/02/12
05/06/13
04/02/13
Valley Paving, Inc.
$507,045
$436,982
86%
Addition, and Danville Avenue are substantially complete. Punch
Project
list items remain.
Ryan Contracting
Construction in progress. Substantial completion expected by the
446
149th Street Improvements
01/02/13
N/A
04/16/13
04/26/13
05/07/13
05/20/13
N/A
Company
$806,816
end of August, 2013.
Design and construction of the railroad crossing improvements will
145th Street Pedestrian
occur in 2013. Sidewalk will be installed on the southwest corner
447
Improvements at RR
01/02/13
N/A
N/A
by mid -July, 2013. Other pedestrian improvements will be
Crossing
constructed in 2014.
This development includes 37 single - family homes by developer
U.S. Home Corporation n The contract i expected to be
448
Prestwick Place 7th
04/16/13
N/A
07/02/13
06/28/13
07/16/13
07/29/13
N/A
awarded at the July 16 Coouunccil il m meeting. The City will share in a
portion of the storm sewer cost for this project.
This development includes 31 single - family homes by The Ryland
Friedges Contracting,
Group, Inc. The contract was awarded at the June 18 Council
449
Gre Y stone 2nd
05/07/13
N/A
06/04/13
06/07/13
06/18/13
07/01113
N/A
Inc.
$519,194
meeting; construction began July 1. Substantial completion
expected by the end of September, 2013.
This development includes 33 single - family homes by D.R. Horton.
450
Prestwick Place 8th
04/16/13
N/A
N/A
THIS PROJECT IS ON HOLD BY THE DEVELOPER.
A feasibility report is currently being prepared for this project. The
Bacardi Avenue
N/A
N/A
report will outline the necessary improvements to Bacardi Avenue
452
Improvements
north of Bonaire Path, as well as the estimated cost and funding.
G:\ENGPROJ \Project Tracking \Project Update Updated: 07/03/2013