City Council Meeting: July 16, 2013
AGENDA ITEM: Receive Bids / Award Contract -
AGENDA SECTION:
Prestwick Place 7th Addition Street and
New Business
Utility Improvements, City Project 448
$1,406,391.30
PREPARED BY: Andrew J. Brotzler, PE, Director lic
AGENDA NO.
q. b
Works /City Engineer
$1,537,521.30
ATTACHMENTS: Resolution; Bid Tab Summary; Le er of
APPROVED BY:
Recommendation; Map; Park Exhibit
ow
RECOMMENDED ACTION: Motion to Adopt a Resolution Receiving Bids and Awarding
the Contract for the Prestwick 7th Addition Street and Utility Improvements, City Project 448.
ISSUE:
Receive bids and award contract for Prestwick 7`h Addition Street and Utility Improvements, City Project
448.
BACKGROUND:
On Friday, June 28, 2013, bids for this project were received and read aloud publicly. This project
included a Base Bid (Schedules A -E) and three Alternates as described below. After verification of bids
received, the low bidder of the Base Bid plus the three Alternates is LaTour Construction, Inc. in the
amount of $1,537,521.30.
Base Bid:
Alternate 1:
Parking Lot
Alternate 2:
Park Trail
Alternate 3:
Basketball Court
Base Bid + Alternates
$1,406,391.30
$95,122.50
$11,945.00
$24,062.50
$1,537,521.30
The Prestwick Place 7"' Addition is a development of 37 single - family homes located west of Akron
Avenue between 150`h Street West and Connemara Trail. The project will be funded through assessments
by the developers, U.S. Home Corporation and Arcon Pemtom, LLC. The remaining costs associated
with storm trunk over - sizing will be funded with City Storm Core funds totaling $441,404.
Alternates 1 -3 are park improvements as highlighted on the attached exhibit. These improvements were
included as alternates with the Prestwick Place 7`h Addition project due to the proximity of the park and
the opportunity to receive lower bids by joining with a larger project. Alternates 1 -3 will be funded with
City Park Improvement funds.
G: \ENGPROJ \448 \Counci1 Items \20130716 CC Receive Bids Award Contract.docx
The table below outlines the project costs and funding:
Fundin
Construction
Indirect 259/6
Total
Developer
$1,053,268.30
$263,317.08
$1,316,585.38
Storm Core Fund
$353,123.00
$88,280.75
$441,403.75
Park Improvement Fund
$131,130.00
$32,782.50
$163,912.50
Total
$1,537,521.30
$384,380.33
$1,921,901.63
It is anticipated that the utility and roadway improvements for the Prestwick 7" Addition will be
substantially complete by October 6, 2013.
SUMMARY:
Staff recommends that Council adopt the attached resolution receiving the bids and awarding the contract
for the Prestwick 7`" Street and Utility Improvements, City Project 448.
K
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2013 - 67
A RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT
FOR THE PRESTWICK PLACE 7T"
STREET AND UTILITY IMPROVEMENTS
CITY PROJECT 448
BE IT RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows:
All bids on construction of the Prestwick Place 7th Addition Street and Utility Improvements
are hereby received and tabulated.
2. Based on the Base Bid plus Alternates 1, 2, and 3, the bid of LaTour Construction, Inc. in the
amount of $1,537,521.30 for the construction of said improvements is in accordance with the
plans and specifications and advertisement for bids, and is the lowest responsible bid and shall
be and hereby is accepted contingent upon securing all necessary right -of -way.
3. Upon securing all necessary right -of -way, the Mayor and City Clerk are authorized and
directed to enter into a contract with said bidder for the construction of said improvements
for and on behalf of the City of Rosemount.
4. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits
made with their bids, except that the deposit of the successful bidder and the next two lowest
bidders shall be retained until a contract has been executed.
ADOPTED this 16`h day of July, 2013.
William H. Droste, Mayor
ATTEST:
Amy Domeier, City Clerk
BID TABULATION SUMMARY
PROJECT:
Prestwick Place 7th Addition
Street and Utility Construction
City Project No. 448
OWNER: City of Rosemount
WSB PROJECT NO.: 1916 -99
BIDS OPENED: Friday, June 28, 2013, at 10:00 a.m.
Engineer's Opinion of Probable Cost $1,589,893.00 $85,140.00 $15,150.00 $19,165.00 $1,709,348.00
1 hereby certify that this is a true and correct tabulation of the bids as received on June 28, 2013.
QX140,-��
Philip C. Olson, PE, Project Manager
* Denotes corrected figure
K:101916- 990L4dminlConstruction Admin11916 -990 Bid Tab Summary-062813- signed
Contractor
Bid Bond
(5 %)
Add. No. 1
Rec'd.
Total Base Bid
(A +B +C +D +E)
Total Alternate 1
Total Alternate 2
Total Alternate 3
Grand Total Bid
(Base + Alts. 1 -3)
1
LaTour Construction, Inc.
X
X
$1,406,391.30
$95,122.50
$11,945.00
$24,062.50
$1,537,521.30
2
Northwest Asphalt, Inc.
X
X
$1,416,066.44
$102,115.50
$12,110.00
$25,962.50
$1,556,254.44
3
Friedges Contracting Co., LLC
X
X
$1,483,073.80
$108,820.00
$15,220.00
$17,340.00
$1,624,453.80
4
Kuechle Underground, Inc.
X
X
$1,546,507.31
$97,924.50
$17,583.00
$25,965.00
$1,687,979.81
5
Northdale Construction Co., Inc.
X
X
$1,788,063.94
$123,521.42
$17,815.00
$20,037.00
$1,949,437.36
Engineer's Opinion of Probable Cost $1,589,893.00 $85,140.00 $15,150.00 $19,165.00 $1,709,348.00
1 hereby certify that this is a true and correct tabulation of the bids as received on June 28, 2013.
QX140,-��
Philip C. Olson, PE, Project Manager
* Denotes corrected figure
K:101916- 990L4dminlConstruction Admin11916 -990 Bid Tab Summary-062813- signed
WSB
& Associates, Inc.
engineering • planning • environmental • construction
July 10, 2013
Honorable Mayor and City Council
City of Rosemount
2875-145 1h Street West
Rosemount, MN 55068
Attn: Jean Harrington/Karin Kladar, Public Works
Re: Prestwick Place 7th Addition Street and Utility Construction
City of Rosemount Project No. 448
WSB Project No. 1916 -99
Dear Mayor and Council Members:
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 - 541 -4800
Fax: 763 -541 -1700
Bids were received for the above - referenced project on Friday, June 28, 2013, and were opened
and read aloud. Five bids were received. The bids were checked for mathematical accuracy and
tabulated. It should be noted that the project included a Base Bid (Schedules A -E) and three
Alternates as detailed below. Please find enclosed the bid tabulation indicating LaTour
Construction, Inc., Maple Lake, Minnesota, as the low bidder with the bid amounts listed below.
The Engineer's Estimate was $1,709,348.00.
St. Cloud • Minneapolis • St. Paul
Equal Opportunity Employer
wsbeng.com
C. Usersljmh�AppDaln�Loc 1-11,c softJf 'ind,,,lTentpornrvinternet FlleslCont ent0u tlookKCEOGZ6 (PLTRRECtLILDTN- h,,,-- 071013.d-
LaTour
Engineer's
Construction,
Estimate
Inc.
Base Bid (Schedules A -E)
......................... 7
$1,406,391.30
...........................................................
$1,589,893.00
Alternate 1: Park Grading and Parking Lot Construction
......................................................................................................................................................................................................................................................................................................................................................................................................................................
$95,122.50
$85,140.00
...............................
Alternate 2: Park Bituminous Trail Construction
$11,945.00
$15,150.00
Alternate 3: Basketball Court Construction
$24,062.50
$19,165.00
GRAND TOTAL
$1,537,521.30
$1,7099348.00
St. Cloud • Minneapolis • St. Paul
Equal Opportunity Employer
wsbeng.com
C. Usersljmh�AppDaln�Loc 1-11,c softJf 'ind,,,lTentpornrvinternet FlleslCont ent0u tlookKCEOGZ6 (PLTRRECtLILDTN- h,,,-- 071013.d-
Honorable Mayor and City Council
July 10, 2013
Page 2
We recommend that the City Council consider these bids and award a contract for the Base Bid
and the three Alternates in the amount of $1,537,521.30 to LaTour Construction, Inc. based on
the results of the bids received.
Sincerely,
WSB & Associates, Inc.
Phil Olson, PE
Project Manager
Enclosures
cc: Joe LaTour, LaTour Construction, Inc.
Andy Brotzler, City of Rosemount
srb
C. Userswih'AppDamlLocalhlf ems ftdVindawe Ternpora , Internet Files ,Conrenr.Ourlook�KCEOGZ6ULTR REOLVDT,V- hmec- 071013.doe
ROSEMOLINT
PUBLIC WORKS DEPARTMENT
ST E
GN 142ND
0
I" 041FIELD
4 TER WAY
9., s
�c;GP
5TH seer w SAH 42)
0 275 550 1,100 1,650 21200
Feet
April 2013
TJGIS /City /Maps /Departmental Maps /Engineering /Chris /Location Map - 448
u
t
C
0
\
CP # 448
PAVING /IMPROVEMENT PLAN \
X
(ALTERNATE BIDS)
a`
7
Eg
a \
`�♦
♦``\
\
al
FUTURE PARK
IMPROVEMENTS
\\
\ ````` \`tg
L/
}l
ECE
a
BY OTHERS)i
S '
\ON�
p
CUT DOWN
\
PEDESTRIAN RAMP
<SEE DETAIL>
\ ALTERNATE 1:
B"
CONSTRUCT PARKING LOT
_I
4 J � I ``\
T /4�
0
AND CONCRETE WALK
_
(SEE TYPICAL SECTIONS)
'' /
� �
W
PARKING STRIPE (TYP)
` I
`\ ,'
`v
n 0
an
I
.�-
ALTERNATE 3:
CONSTRUCT BASKETBALL COURT,
BASKETBALL FURNISHINGS. AND
w u
Q
BITUMINOUS ACCESS TRAIL
J
a P
Z
(SEE DETAILS)
Y j
Z
c=
Lu
n
o
♦
♦
ALTERNATE 2:
CONSTRUCT 2' BITUMINOUS
/
\\ TRAIL (SEE TYPICAL SECTION)
E
J
1 1
`\
HANDICAP PAVEME
AILESBURY
COURT
a '.2
18
PAVING,AMPROVEMENT P LAN
CITY PROJECT NO. 448
PARK IMPROVEMENTS
SHEET 24 OF 30 SHEETS