HomeMy WebLinkAbout6.a. Authorize Development of Well 16ROSEMOLINTEXECUTIVE SUMMARY
UTILITY COMMISSION
Utility Commission Meeting: September 9, 2013
AGENDA ITEM: Authorize Development of Well 16
AGENDA SECTION:
New Business
PREPARED BY: Andrew J. Brotzler, PE, Director of Public
Works /City Engineer
AGENDA NO.
ATTACHMENTS: Map, Preliminary Plat
APPROVED BY: KI
RECOMMENDED ACTION: Motion to authorize the development of Well 16
ISSUE
With the increase in development over the past several years, the planning and development of Well 16 is
necessary to support continued development.
BACKGROUND
Following the completion of Well 15, an evaluation and summary of the available water supply capacity for
development was completed. Based on the development that has occurred and approved development
plans since the completion of Well 15, the city's water supply system can support an additional 400 to 600
units of development before additional capacity is required. Based on a lead time of at least 2 years to
develop a well and well house and bring it online, it is appropriate to consider the development of the next
well, Well 16 at this time.
Well 16 is planned to be located on property within the recently approved Bella Vista development as
shown on the attached map. This location is consistent with the city's water supply plan and well field
study.
The scope and schedule for the development of Well 16 is outlined below.
Development of Well 16 will include the following phases:
1. Design and construct a monitoring well near the center of the city in accordance with the DNR's
requirements identified in the city's appropriations permit.
2. Design and construct a test well at the well 16 site to confirm geology and water quality data that
will aid in the design phase.
3. Design and Construct Well 16
4. Design and Construct a pumping facility for Well 16
The DNR is requiring that the City install 3 monitoring wells in the Jordan formation. Two of the three
G: \ENGPROJ \416 \20130909 UC Authorize Development of Well 16.docx
monitoring wells in the Jordan formation requested by DNR in the appropriation permit have been
installed.
The City has been using MDH grants or combining the monitoring wells with other projects to fund the
DNR's request and has therefore spread the work out over time to lessen the impact on the City's
finances.
The monitoring wells are as follows:
1. Test Well 14 at Well House 14 has been converted to a monitoring well. A data logger was
installed and the city will be submitting data in the near future.
2. A monitoring well was installed at UMore Park along with the installation of an irrigation well
project. That project was completed in spring 2013. A data logger has been installed and the City
will be submitting data in the near future.
3. The 3rd monitoring well requested by the DNR will be installed this fall/winter near the center of
the City as requested by the DNR.
4. An additional monitoring well (shallow) was installed by the City near Well House 14 to study the
interaction between the shallow and deep aquifers.
The city has applied for a grant from the MDH to investigate the condition of abandoned wells 1 and 2. It
is known that they were capped, but it is unclear whether they were ever sealed. If former wells 1 or 2 have
not been sealed the possibility of using one of the wells as the 3rd monitoring well will be assessed.
Schedule
The preliminary schedule for all phases is as follows:
Phase 1 — Monitoring well
• Assess the condition of Wells 1 & 2
• Prepare quote documents for
converting well 1 or 2 or
constructing a separate monitoring well
• Submit design to DNR for approval
• Obtain quotes and award contract
• Construct monitoring well
• Install data logger
• Obtain data and submit to the DNR
Phase 2 — Test Well
• Design test well
• Obtain quotes and award contract
• Construct test well
• Obtain geological and water quality data
Phase 3 — Well 16
• Submit preliminary well application to the DNR
• Design well
• MDH /DNR review of plans & specs
• Advertise for bids and award contract
September/ October 2013
September- October 2013
October - November 2013
November - December 2013
January 2014
Spring 2014
Spring 2014
September- October 2013
October- November 2013
November- December 2013
December 2013
October 2013
November 2013 —January 2014
February - March 2014
March — April 2014
2
• Construct well
Phase 4 — Well House 16
• Preliminary Design well house
• Prepare plans and specifications
• MDH review of plans & specs
• Advertise for bids and award contract
• Construct well house
SUMMARY
May — September 2014
April 2014
May — June 2014
July — August 2014
September 2014
October 2014 — Spring 2015
Staff is recommending that the Utility Commission authorize the development of Well 16.
3
z
128TH CO
uj W
> ST W >
z
0 < 1
B3 co
130TH ST W
KEEGAN
LAKE
132ND CT W KEEGAN LAKE
SRONZt-
J.1 Cl BRASS
D >- 133RD ST
Al 7FZ
LU
Qdj 128TH
z ST W
LU
CO
..
T:/GIS/City/Maps/Departmental Maps /Engineering /Chris /Location Map - 433
W r" -4
N 134TH ST �N MARE
z
0 POND BONAIRE PA W
ft
BIRDSONG LU RE POND ATHE
CT >
Brockway BIRDSONG PATH
MARE
POND BONAIRE PA
RE POND ATHE
B
Park
>
136TH ST W 0
0-
> U�
Br BONZE 'P 3�
ockw -10
WY o ob
Park ay PKR 0) /k
E
m
CONNEMARA
0
TRL
cONN�TRLgi
L. 138TH ST W
14,
GN PX 138TH 0 A to
0A
> 138TH ST W c B1R (11 ST W 17
< Cu
U. 138TH ST W rn �,A
BELVIDERE >
139TH ST W <
< <) CT
> z 0
Z < < W 0
z
z L: 140TH ST W
< z C�
W < 0 11 ST
-H ST W r
Birch 71,
BELMONT
z Park
ui
0 CT BIRCH U-
> > Ga Z BELFA'--T 1310001le 0
Er' Park ckso P's ��o N P,4 0
5� 'V 0
Park )W 3:
Oof E L D S TA '--
v"P N% TRIL <
01 1Q r C, 142ND 0
00 6 ST 1,4j 0
MCME
PC
I — �o t--
-76 C'�0 0 010 3: u
FIELD
z
'al m "->ALEA PA�%"'
BEECH ST W BAYBERRY
"I'T ER 145TH S7
A A r-r U 10'r A A I
4ROSEMOUNT
MINNESOTA
Well 16
A
N
City Project 416, September 2013
F
02013 Westwood Professional Services, Inc.
I I
I I
I I
J I
I I
I I
> I I
I
I
I
_J
oulLor a
Call 48 Hours before digging:
GOPHER STATE ONE CALL
Twin City Area 651- 454 -0002
Mn. Toll Free 1- 800 - 252 -1166
DEVELOPMENT DATA
PHASE 1
Existing Zoning
AG
Existing Guide Plan
LDR; Low Density Residential
Proposed Zoning
R -1 (PUD)
Total Site Area:
142.61 Acres
County Rood 38 R.O.W dedication:
0.53 Acres
Autumn Path R.O.W.:
2.50 Acres
City /County Lands (Outlots E & F):
63.0 Acres
Net Residential Area.,
76.58 Acres
Net Major ROW & City /County Lands
35' min.
Proposed Single Family Lots.,
158 Lots
Density.
2.06 un /ac
158 Lots / Net Resid. Area 76.58 ac.
rear yard Wetland constraints.
LOT STANDARDS Single Family
PHASE 1
Lot Width (O Front Yard Setback)
75' Min.
Lot Depth
125' Min. (130'+ overage)
Minimum Lot Area:
9,499 s!.
Average Lot Area:
17,695 st.
Front Yard Setback
s25' Typ (20' Min.)
Side Yard Corner Lots
25'
Side Yard Setback
75%75' : 15' Total
Rear Yard Setback
30'
Setback to Autumn Path (fut. collector)
35' min.
Setback to County Road 38
70' as shown
Structure Setback to wetland buffers
5' min.
-Note. Lots marked with . (Blocks 2,3,4,& 10) have reduced front setback to 20' due to
rear yard Wetland constraints.
FINAL PLAT PHASING PLAN
PHASE 1
– 28 LOTS
PHASE 2
– 44 LOTS
PHASE 3
– 40 LOTS
PHASE 4
– 46 LOTS
TOTAL –
158 LOTS
PHASING NOTBS
1. GRADING CONSTRUCTION LIMITS OF EACH PHASE OF THE PLAT MAY EXCEED LIMITS OF
PLATTED LOTS IN ORDER TO BALANCE SITE.
2. ALL PROPOSED WETLAND IMPACTS AND MITIGATION AREAS WILL BE CONSTRUCTED WITHIN
PHASE 1 CONSTRUCTION.
3 CONSTRUCTION OF THE INFILTRAT70N BASIN WILL BE COMPLETED IN 3 PHASES
BEGINNING WITH PHASE 1 CONS7RUCTON AND COMPLETING IN PHASE 3 CONSTRUCTION.
EACH OF THE FIRST TWO PHASES ON THE INFILTRA77ON BASIN CONSTRUCTION WILL BE OF
ADEQUATE SIZE AS TO PROVIDE THE REQUIRED INFILTRATION AREA CALCULATED USING THE
NEW DEVELOPMENT AREA OF EACH OF PHASES 1 & 2.
Typical
75' Single Family Lot
30'
REAR YARD SETBACK
Bella Vista
Rosemount, M nnesota
10.0' Rear Easement
����=a,.�a�Na
SIDE YARD SETBACK
it
9 LOT NUMBER
Side Easement
it
II
10.0' Front Easement
25' Front Yard Setback
STREET
0' 200' 400' 600'
NOT FOR CONSTRUCTION
0000586dpp01.dwg
Date 04 /30/13 Sheet 3 OF 38
W mood ^O�d1� `' �"` ' °veby `°� `s" w. �° ° °"F°ad " e. a �-
1s99 an.9nn, mne a5.c .uye.wo..�a w.. 1 wn . awy aamaa LnNOSCwea
Eden F Ha MN 5534{ e� �-� d -
WO NE 952 - 9311150
FM 952-93) -5613
Tom — 1-185-931-5150 Cory L Meyer
04/30/13 26971
W65'tVY000I www.venwoodp..alm nee Ilmn Nn
A^d_
Dedoed cut
Prepared for.
Lennar Corporation
]6305 36th Avenue North Suite 600
Plymouth, M nnesota 55446
Bella Vista
Rosemount, M nnesota
Development
Plan & overall
Preliminary Plat
����=a,.�a�Na
CherlmR CI.M_
�� aM
s.®a on .e a e ra.ea