HomeMy WebLinkAbout8.a. City Projects Update City Projects Update
Council
City Council Public Receives Award Assessment Contract Payments %
Project Project Name Authorizes Hearing Plans/Specs. Open Bids Contract Start Date Hearing Contractor Amount To Date Complete Summary
Number Plans/Specs Authorize Ad
For Bid
This project will establish the master feasibility report for all future
433 Bella Vista N/A N/A N/A Bella Vista developments. The feasibility report is expected to be
received by council on November 19th.
145th Street Pedestrian Design and construction of the railroad crossing improvements will
447 Improvements at RR 01/02/13 N/A N/A occur in 2014. Sidewalk has been installed on the southwest
Crossing corner adjacent to the Park&Ride.
448 Prestwick Place 7th 04/16/13 N/A 06/18/13 06/28/13 07/16/13 07/29/13 N/A LaTour Construction, $1,537,521 $1,052,761 68% This project is on hold for the winter. Final paving and punch list
Inc. items will be completed in spring,2014.
449 Greystone 2nd 05/07/13 N/A 06/04/13 06/07/13 06/18/13 07/01/13 N/A Fr edges Contracting, $519,194 $424,867 82q, This project is on hold for the winter. Final paving and punch list
Inc. items will be completed in spring,2014.
A feasibility report is currently being prepared for this project. It will
Bacardi Avenue outline the necessary improvements to Bacardi Avenue north of
452 Improvements 11/19/13 01/21/14 02/18/14 03/07/14 04/24/14 05/01/14 N/A Bonaire Path,and estimated cost and funding.The report is
expected to be received by council on December 17th.
This development includes 28 single-family homes by developer
454 Bella Vista 2nd 11/19/13 N/A N/A U.S.Home Corporation(Lennar). Final plat approval is expected
at the November 19 council meeting. Construction is planned for
2014.
455 2014 Street Improvement 11/05/13 N/A This project includes mill and overlay improvements on Shannon
Project Parkway and Carrollton 2nd Addition.
G:\ENGPROJ\Project Tracking/Project Update.xls Updated: 11/13/2013