HomeMy WebLinkAbout6.k. SCBA Breathing Air Compressor 4ROSEtvLOUI\J'1T EXECUTIVE SUMMARY
CITY COUNCIL
City Council (regular meeting): December 17, 2013
AGENDA ITEM: SCBA Breathing Air Compressor A A ECTION:
PREPARED BY: Fire Chief Schroeder AGENDA NO. (TV.
ATTACHMENTS: Bid Proposal APPROVED BY:
RECOMMENDED ACTION: Purchase of a Bauer Vertecon Breathing Air Compressor for 0.)
Fire Station 2, to be purchased from Alex Air Apparatus in the amount of$43,660.00.
Additionally, the installation of the compressor by Collins Electrical in the amount of
$1,585.00.
ISSUE
Currently the Rosemount Fire Department only has one breathing air compressor which is
located at Station 1. With the addition of the Station 2, we have added fire personnel and will
continue to add more in the coming years. This has caused additional strain on the breathing
air compressor at Station 1.
DISCUSSION
Currently after fires both stations have to reconvene at Station 1 to fill SCBA bottles. One
issue the department faces is when large numbers of bottles are needed to be filled, the air
compressor struggles to fill to capacity. An additional breathing air compressor would
significantly reduce time spent getting back in service as well as air bottles only getting
partially filled. It has also created a situation where Firefighters are transporting bottles back
and forth in fire vehicles after calls and training. This would alleviate time and fuel spent
between stations transporting air bottles to be filled. Also, an additional breathing air
compressor would significantly reduce the chance of not having the ability to fill air bottles in
the event the Station 1 compressor were to fail. Finally, an additional compressor installed at
Station 2 would put this department in a better position to take on additional firefighters in the
years to come.
RECOMMENDATION
As Fire Chief, I recommend that the additional Bauer air compressor be installed at Station 2.
Some benefits include a safer environment because firefighters will have the ability to
efficiently and successfully fill air bottles after a fire; therefore, creating a safer environment
for the citizens of Rosemount. We will implement a back-up plan to fill SCBA bottles and get
them back in service, should the breathing air compressor at Station 1 fail. Lastly, many of
the firefighters struggle to get to work after an overnight fire. This additional air compressor
would speed up the process of getting equipment back in service and FF's out the door and
to work in a timely manner.
Page 2 of 2
RECOMMENDED ACTION: Purchase and installation of a Bauer Vertecon Breathing
Air Compressor at Fire Station 2.
ADDITIONAL DISCUSSION
As part of this process to select a compressor for station two, a committee composed of
several members of the Rosemount Fire Department was put together to conduct the
research. This process included speaking with members from several fire departments in
Dakota County as well as conducting research on line. After the initial investigation, two front
runners emerged in the process, Bauer and Scott SCBA compressors.
Meetings were then set up with representatives from Scott and Bauer to discuss Rosemount
Fire needs and expectations in an SCBA compressor. After meeting with the
representatives, committee members then visited Flint Hills Resources to observe their Scott
SCBA compressor. A visit was also conducted at a Burnsville Fire Station to observe their
Bauer SCBA compressor.
After putting all of the leg work together, the committee decided on the Bauer compressor.
The main reason is for its proven compressor pump and reliability. It also was chosen due to
its track record for reliability as well as ease of service to maintain it.
Bids were obtained from two companies that included Alex Air Apparatus for the Bauer
compressor and Municipal Emergency Services for the Scott compressor. These quotes are
included along with this summary. Also as part of this process, a proposal was put together
by Collins Electric for the installation of the compressor in Fire Station #2.
As the City of Rosemount continues to grow, so must the equipment and resources within the
Rosemount Fire Department. We must learn from the past and prepare for the future.
Total project cost with the purchase and installation of the Bauer SCBA compressor totals:
$45,245.00. This item was on the 2013 Capital Improvement Budget (CIP) and this purchase
price and installation is within the budgeted amount.
2
Fire-Rescue Sales and Service
301 Eleanor St PROPOSAL
Mankato, MN 56001
'Y .ig ,__ 507-381-3207
aI@alexairapparatus.com
'CUSTOMER NAME DATE REF NUMBER
Rosemount Fire Dept 7/30/13
ADDRESS ATTENTION
Chris Dyson
CITY.'STATE.BP PHONE
Rosemount, MN
QTY DESCRIPTION EACH TOTAL
1 Bauer Vertecon 10 breathing air compressor, 208V/E3, 9.7 cfm, $19,900.00 $19,900.00
7.51-4P, Auto drain, Securus moisture monitor, gauges.
1 Electronic CO monitor, Auto-cal, includes reg and cal gas $3,175.00 $3,175.00
1 Remote compressor control panel $1,990.00 $1,990.00
1 Bauer CFS5.5-3S fill station,with reg and fill controls $7,450.00 $7,450.00
1 Auto cascade system, with controls at fill station $3,945.00 $3,945.00
4 UN6000 Y
storage cylinders, mounted $1,200.00 $4,800.00
1 Freight and installation $2,400.00 $2,400.00
•
TOTAL $43,660.00
Page 1 of 1 PRICES VALID FOR 30 DAYS Signed: Al Bobinga
CO/ft/1S
Proposal / Contract
UNLIMITED ELECTRICAL+TECHNOLOGY SOLUTIONS
LOGY o< S
Date: 07-16-2010
Proposal submitted to: Work to be performed at:
Joe Werden Fire Station'
Address: Phone/Fax:
2875 145th Street West 651-485-2291 /joe.werden @ci.rosemount.mn.us
City, State,Zip Code: Project Name:
Rosemount,MN 55068 Pre-wiring for New Compressor
We are pleased to submit the following proposal:
• Remove existing 240 Volt,3 phase,30 amp disconnect.
• Remove old#10 Copper feeder from panel to disconnect.
• Furnish and install(1)new 3 pole 40 amp breaker in panel.
• Furnish and install new 60 amp/250 volt non-fused disconnect in place of old 30 amp unit.
• Pull new#8 Copper wire from panel to new 60 amp/250 volt non-fused disconnect in existing conduit.
• Make final connections to new compressor when it arrives.
Fee for services—$1,585.00
All work shall conform to all Local and National Electrical Codes.
Any alteration or deviation from the services outlined in this proposal will be executed only upon written request and may
become an extra charge over and above the estimate.
All work described above to be done during standard working hours unless other wise specified.
This proposal may be withdrawn by us if not accepted within 30 days.
Payment-in-full is due within 30 days of project completion.
Additional costs due to abnormal fluctuations of commodity pricing are not included.
Respectfully submitted,
Collins Electrical Construction Co.
Joseph Hanley,Project Manger/Estimator
Direct#651-255-0169/Fax#651-292-0359
Joseph.hanley(acollinsolutions.com
Acceptance of Proposal
The prices, specifications,terms and conditions of this proposal are satisfactory and are hereby accepted. Collins
Electrical Construction Co.is authorized to perform the work as specified.
Signature: Date:
Collins Electrical Construction Co. 1 278 State Street I St.Paul,MN 55107 I Office:651-224-2833 I Fax:651-292-0359 I www.collinsolutions.com
4
MES - MIDAM Telephone • 402-727-5785
1880 East Military Ave Fax •402-727-5789
Fremont, NE 68025
MES
MUNICIPAL EMERGENCY SERVICES,INC.1,,,
Ship To: Quotation
ROSEMOUNT FIRE DEPARTMENT
2875 145 STREET WEST Number • QT_00226759-3
ROSEMOUNT, MN 55068 Date • 9/12/2013
Contact: CHRIS DYSON Page • 1 of 2
Sales order
•
Phone: 651-235-7538
Requisition
•
Your ref.
Our ref • BMcCabe
Bill To: Quotation deadline • 10/11/2013
ROSEMOUNT FIRE DEPARTMENT Payment • Net 30
2875 145 STREET WEST Sales Rep • BMcCabe
ROSEMOUNT, MN 55068 Terms of delivery • Customer Pays
Freight-Taxable
I
Item number Description Size Color Quantity Unit Unit price Amount
AC0403364110 SIMPLE AIR COMPRESSOR, 1.00 EA 20,679.44 20,679.44
208V/3PH/60HTZ, 6000PSI,
10HP, CONTROLLER
MOUNTED IN FILL STATION
W/CO AND DEW POINT
MONITORS&CAL KIT, OPEN
UNIT W/REMOTE AIR
INTAKE.
4
AR4204A4101 STORAGE SYSTEM, 4ea 1.00 EA 6,473.25 6,473.25
6000 PSI DOT CYLINDERS
W/4 CYL WALL MOUNT
RACK, 10' HOSES PLUMBED
FOR AUTO CASCADE
AF2110221A001 REVOLVAIR CHARGE 1.00 EA 11,845.58 11,845.58
STATION,W/BASE, FILL
PANEL, MOUNTING HOLE
FOR CONTROLLER,4 BANK
AUTO CASCADE ,AND CGA
ADAPTER.
AB110-1464-850 CONTROLLER CABEL 1.00 EA 335.48 335.48
EXTENSION, 50'
526-4BA HOSE 6000 PSI 60.00 FT 5.72 343.20
1065544 FITTING FLARE 37 6.00 EA 5.14 30.84
COMPRESSOR INSTALL COMPRESSOR 1.00 EA 850.00 850.00
INSTALLATION
FREIGHT Freight ESTIMATE 1.00 EA 400.00 400.00
This Quotation is subject to any applicable sales tax and shipping &handling charges that may apply.
•
All returns must be processed within 30 days of receipt and require a return authorization number and are subject to a restocking fee.
Custom orders are not returnable.Effective tax rate will be applicable at the time of invoice.
if
•.
MES - MIDAM Telephone •402-727-5785
1880 East Military Ave Fax •402-727-5789
Fremont, NE 68025
MES
MUNICIPAL MUMMY SERVICES,INC.
Ship To:
ROSEMOUNT FIRE DEPARTMENT Quotation
2875 145 STREET WEST Number • QT 00226759-3
ROSEMOUNT, MN 55068 Date • 9/12/2013
Page • 2 of 2
Contact: CHRIS DYSON Sales order
Phone: 651-235-7538 Requisition •
•
Your ref.
Our ref • BMcCabe
Bill To: Quotation deadline • 10/11/2013
ROSEMOUNT FIRE DEPARTMENT Payment • Net 30
2875 145 STREET WEST Sales Rep • BMcCabe
ROSEMOUNT, MN 55068 Terms of delivery • Customer Pays
Freight-Taxable
Notes:
HGAC CONTRACT PRICING
INSTALLATION DOES NOT INCLUDE ELECTRICAL HOOK-UP OR
PLACEMENT OF UNITS IN ROOMS.
•s balance Total discount S&H Sales tax Total
0,957.79 0.00 0.00 2,829.18 43,786.97 USD
urns must be processed within 30 days of receipt and require a return authorization number and are subject to a restocking fee.
orders are not returnable.Effective tax rate will be applicable at the time of invoice.
Vs-
Sal,
All re
Gust.