Project Project Name Authorizes Hearing Plans/Specs. Open Bids Contract Start Date Hearing Contractor Amount To Date Complete Summary
Number Plans/Specs Authorize Ad
For Bid
Construction of the railroad crossing improvements will begin
145th Street Pedestrian upon execution of an agreement with CPRR(currently
UPRR,CPRR,
447 Improvements at RR 01/02/13 N/A N/A working on this agreement). Agreement is already in place
Crossing TBD with UPRR. Sidewalk has been installed on the southwest
corner adjacent to the Park&Ride.
LaTour o Final paving and punch list items will be completed Summer
448 Prestwick Place 7th 04/16/13 N/A 06/18/13 06/28/13 07/16/13 07/29/13 N/A Construction, $1,537,521 $1,299,404 85/0 2014.
Inc.
449 Greystone 2nd 05/07/13 N/A 06/04/13 06/07/13 06/18/13 07/01/13 N/A Friedges $519,194 $438,985 85% Final paving and punch list items will be completed in
Contracting,Inc. Summer 2014.
This development includes 33 single-family homes by
450 Prestwick Place 8th N/A N/A N/A N/A N/A 07/28/14 N/A S.R.Weidema N/A N/A N/A developer KRB Development I,LLC. The developer has
chosen to administer the contract privately. Construction is
expected to be completed Fall 2014.
This project will upgrade Bacardi Avenue to a paved urban
section,from Bonaire Path to the north approximately 1/2
Ryan mile. Trunk water main and sanitary sewer will be installed to
452 Bacardi Avenue 11/19/13 02/18/14 02/18/14 03/21/14 06/03/14 06/16/14 05/06/14 Contracting $2,661,605 $214,422 8% serve future residential development to the east of Bacardi
Improvements Company Avenue. An 8-foot wide bituminous trail will also be added
along the east side of Bacardi Avenue. The contractor is
currently installing utilities.
Northwest This development includes 28 single-family homes by
454 Bella Vista 2nd 11/19/13 N/A 03/04/14 03/21/14 06/03/14 07/01/14 N/A Asphalt,Inc. $762,308 $0 - developer U.S.Home Corporation(Lennar). Construction is
expected to begin in September,2014.
2014 Street Valley Paving, o Milling and paving on Shannon Parkway and Carrollton 2nd
455 01/07/14 05/20/14 03/18/14 04/04/14 05/20/14 06/09/14 05/20/14 $630,418 $5,808 1/u Addition is completed. The contractor is working on final
Improvement Project Inc. restoration.
This project is substantially complete. It included the removal
Pember of the existing curb and sidewalk,relocation of storm sewer
456 TH 3 Turn Lane 11/19/13 N/A 04/15/14 04/25/14 05/06/14 05/19/14 N/A Companies,Inc. $290,869 $207,352 71% and street lights,and construction of the right turn lane just
south of Lower 147th Street. Project will be funded with TIF
and grant funds.
This development includes 26 single-family homes by
457 Prestwick Place 10th 07/15/14 N/A 08/04/14 08/12/04 08/19/14 08/25/14 N/A developer U.S.Home Corporation(Lennar). Construction is
expected to begin in late August,2014.