HomeMy WebLinkAbout6.h. Approve Change Order No. 1 - City Hall Roof Replacement � ROSEI�✓IOLINT EXECUTIVE SUMMARY
CITY tOUNCIL
City Council Meeting: October 7, 2014
AGENDA ITEM: Approve Change Order No. 1 — City Hall AGENDA SECTION:
Roof Replacement Consent
PREPARED BY: Andrew J. Brotzler, PE, Director of Pu i AGENDA NO.
Works / City Engineer �p . .
ATTACHMENTS: Recommendation Letter from CNH APPROVED BY:
Architects; Change Order 1
RECOMMENDED ACTION: Motion to approve Change Order 1 for the City Hall Roof
Replacement
BACKGROUND
The roofmg contractor has encountered a significant amount of rotted ply�vood and several areas of
inadequate and/or ineffective insulation during the roof replacement project. To resolve these issues, they
have replaced the rotted pl��vood, replaced the water-damaged batt insulation, and added foam insulation
wherever necessary to address air flo�v issues. The attached letter from Quinn Hutson from CNH
Architects summarizes the damages and repairs in greater detail.
These unexpected issues have resulted in an additional $25,859 being added to the contract, Uringing the
new contract amount to $259,859. The additional charges are not covered by the insurance claim and will
be paid from the City's operating budget for building repairs. Change Order 1 also extends the
complerion deadline fYOm OctobeY 10 to October 24, 2014.
SUMMARY
Staff recommends Council appro�al of Change Order 1 for the City Hall Roof Replacement.
G:APublic�Xlurks\Storm llamage\2013,August G\20141UU7 CC Change Order 1.doc�
7300 WEST 147T"STREET SUITE 504 APPLE VALLEY, MN 55124-7580 (952) 431 -4433 � �
October 1, 2014
Mr. Andy Brotzler
City of Rosemount
2875 145th Street West
Rosemount, MN 55068-4997
Re: Rosemount City Hall Roof Replacement
Review of Change Order#1
CNH No.: 14017
Mr. Brotzler:
The following is a summary review of added costs and construction time associated with Change
Order#1 for the City Hall Roof Replacement project. All of these changes have been reviewed by
CNH Architects and with City of Rosemount staff as they were identified. My goal in this review is
to summarize these in a single document. All items listed below were in concealed areas that were
not able to be investigated prior to roofing or facia removal.
Item #1 —Insulation over Upper Level Vestibule Doors
When opening the facia in the area over the upper level exterior vestibule doors it was discovered
that the stud header ���all ���as exposcd batt ins�ilation ���ithout exterior sheathing, see photo below.
° :<�,� ,;ry.�, u-P�;
' �� �a�
, ,. _ _ _ . . .
� � ..�;.
, �� � �M r�
��;� �t� ° `�'� _
� �
�����
� ...,,. .
> �
„ . �
r:.. "�v$4' % ..,, � ..... � ".4�..`.. � . "�".+.�
.�p.= ._a '�+'� �
,t�5`" ' ....
�s �;�*'.?M%�l,� . .
�
; � �`�
:
;��;
� � �
This exposed batt insulation in a vented soffit was not only unexpected, but not a standard
construction practice. Not only does it provide poor insulation, it also would allow for condensation
on the back side of the interior gypsum board wall. Due to this, CNH Architects recommended
P�.\Projects\2014\14017�5-Constructwn Adrtun�.Correspondence�l.et�er01 Change Order#01 OvercieH�.doc
adding spray foam insulation over the exposed batt insulation. This will not only seal the air flow
gaps, add insulation R-value, but will act as a vapor barrier for this insulation.
Item #2—Water Dama�ed Existin� Roof Deckin�and Insulation
Water damage was discovered under the existing standing seam roof at the original portion of City
Hall at the eave portions of both the east and west roof slopes. Over the years water had infiltrated at
the upper window areas and at the internal gutter locations over each of the two entries. It was
known that there had been leaking in these areas from water dripping inside the building or at soffit
areas, but until the roofing was removed the condition of the plywood decking and rigid insulation
could not be determined or quantified.
Upon opening up these portions of the roof it was immediately evident that significant deterioration
had occurred covering over I,200 square feet of the existing roof. This water damage was
�articularly evident in the crumblin� Iv�vood sheathing shown in the photo below.
_ ,. - - . -,��
K ..
'�';.,x ,,<�s !s. ,.,.� �.. ., .
'.'�� � -4 ;,��'r
,�,_.
. t. ,.,� + ,yih,` w,^ ��
n �¢x, °*�r^ � � -�
4 ��yy� ��Gw.,'^�y,�}�.,,. _ �:'Y^�.
-� � �"�:::
',,,� �` •-
.
_ ��"• �
��, .
_x � �~�? .. ,�'�y ��°* �, . �
� � fi � *�:�. �,
. �um.�Sw,l�� . .�� ,. ,�a..�'1 'jl��r ti� v 0
r •,fs -s >, t�,;r.
`�+'� i .\� �y���:�
� 5`°,0�:�. *��� �.w�*.,;YC�'�+�^^'�'.
r'r 'p►�� �,e��",�r. 4 �,,'y aY �
v 1 � � ^y, �
�, �.,�„�-s �� �.����y��'���.. �...
�.���'�--�;��,,�,�?�;��., }:���-_
� � �
�',,, �� '„ °�. t�►a,,.z 7'.
, ,,;v .��. ±,�,�.�.. �,�,�,�° ,.,�
.,� �
�P� � ��
� �`y, ���' �,
� ` � �`�"
. , " �;:d�;�' ;
With the amount ofwater intrusion evidenced bythe water damaged plywood,CNH Architects was
not surprised to find that the Styrofoam insulation below the plywood was soaked with water. This
type of insulation is open-celled absorbing moisture into its structure and holding it there. CNH
Architects recommended replacing both the plywood and the wet insulation for structural integrity
and to restore the intended R-value lost with the wet insulation. In addition,wet insulation left in the
roof system would void the new roof system warranty.
ltem #3 —Added Spray Foam Insulation at Wall to Deck Areas
The last item is areas along most facias were the wall to roof deck construction was not built to
match the detailing on the construction documents resulting in additional areas where spray foam
insulation was recommended to be installed to prevent heatloss directly from the building interioc to
the vented soffit areas.
P�.�PrqecU\?014\14017\5-ConsVUCtion Adrtun\Correspondznce\Letter0l Change Order#01 Overciew.doc
One of the most notable areas of this is shown in the picture below which is inside the west facia
constructio»at the north addition area. The photo shows that the yellow sheathing does not extend
up to the roof decking per the original construction, but instead leaves the full stud area open with
just some batt insulation stuffed in the gap (batt insulation not visible).
� �
,
� �
� �,�.
� �.. �
�,
$�.K_
��
;-
� �,
��
CNH Architects recommended installing spray foam insulation into this top of wall conditions,again
for both preventing heatloss through the gap as well as prevent moisture issues from condensation.
Altogether there were over 500 lineal feet of added spray foam insulation within soffit areas, all of
which was only accessible to be installed during this reroofing project.
Chan�e Order Value and Time Extension
John A. Dalsin& Son, Inc.,the general contractor for this project,submitted costs for the work listed
above which was reviewed by CNH Architects and found to be acceptable for the type and quantity
of work performed. This extra work not only resulted added time to complete the work, but also
caused small delays while the areas were reviewed and a direction was provided. Altogether CNH
Architects has determined that approximately 10 �vork days were added based on this additional
work (this represents 14 calendar days).
P-\Pro�ects�2014U401 TS-Construc�ion Adinin\Correspondence�l.etter-01 Change Order MOl O�erview doc
In conclusion,the work shown above will restore the structural integrity of water damaged areas of
the existing roof and provide a complete thermal and air barrier between the interior of the building
and the exterior soffits. The items discovered were not visible or discoverable during design or by
the contractor during bidding. Finally,upon review of the costs and time extension CNH Architects
recommends the approval of the attached Change Order#1.
Sincerely,
�_ i
Quinn S. Hutson, AIA, LEED AP
Principal
CNH Architects, Inc.
P:V'rojects�2014U401T5-Construction Adimn\Correspondence\Lzlterv0l Change Order r�01 Ocen�itw.doc
0
5���/1 TM
=�_= Document G701 - 2001
Change Order
PROJECT(Name and address�: CHANGE ORDER NUMBER:001 OWNER:❑
Rosemount City Hall Roof Replacement DATE:October l,2014 ARCHITECT:❑
2875 145th Street W
Rosemount,MN 5�068 CONTRACTOR:❑
TO CONTRACTOR(1Vame and address): ARCHITECT'S PROJECT NUMBER: 14017 FIELD:❑
John A. Dalsin&Son,Inc. CONTRACT DATE:August 08.2014
2830 South 20th Avenue CONTRACT FOR:General Construction OTHER:❑
Minneapolis,MN 55407
THE CONTRACT IS CHANGED AS FOLLOWS:
(Inelude,where applieable,any undisputed nmount attributable to previously exeeuted Constri�ction Change Directives)
PR#1,CR#1 East:Vestibule extra sprayfoam. Add$862.00
CR#2 East:Ply and insulation. Add$5,917.00
CR#3 East:Wet ply and insulation replacement. Add$2,024.00
CR#3 West:Temp protection of wet areas. Add$1,214.00
CR#3 West:Wet ply and insulation replacement. Add$7,537.00
CR#3 Additional spray foam wark. Add$8,305.00
The original Contract Sum was $ 234,000.00
The net change by previously authorized Change Orders $ 0.00
The Contract Sum prior to this Change Order was $ 234,000.00
The Contract Sum will be increased by this Change Order in the amount of $ 2�,8�9.00
The new Contract Sum including this Change Order will be $ 2�9,8�9.00
The Contract Time will be increased by Fourteen(14)days.
The date of Substantial Completion as of the date of this Change Order therefore is October 24,2014.
NOTE:This Change Order dces not include changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which have
been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and
Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
CNH Architects,Ine. John A. Dalsin c& Son,Inc. City of Rosemount
ARCHITECT(Firm name) CONTRACTOR(Firm nnme) OWNER(Firnz name�
7300 West 147th Street,Suite 504, 2830 South 20th Avenue, 2875 14�th Street W,
Apple Valley, MN 55124 Minneapolis,MN 55407 Rosemount,MN 55068
ADDRESS ADDRESS ADDRESS
BY(Signnti�re) BY(Signati�re) BY(Signntzrre)
Quinn Hutson
(Typed name) (Typed name) (Typed name)
DATE DATE DATE
AIA Document G701 T"'—2001.Copyright OO 1979,1987,2000 and 2001 by The American Institute of Architects.All rights reserved.WARNING Th�s AlA
Document is protected by U.S.Copynght Law and intemational Treaties.Unauthorized reproduc[ion or distribution ot this AIA Document,or any .�
portion ot it may result in severe civil and criminal penalties.and will be prosecuted to the maximum extent possible under the law This documentwas
produced by AIA software at 15:07:51 on 10/01/2014 under Order No.7178443584_1 which expires on 01/16/2015,and is not for resale.
User Notes: (726563138)