HomeMy WebLinkAbout8.a. City Projects Update City Projects Update
Council
City Council Public Receives Award Assessment Contract Payments %
Project Project Name Authorizes Hearing Plans/Specs. Open Bids Contract Start Date Hearing Contractor Amount To Date Complete Summary
Number Plans/Specs 9 Authorize Ad 9
For Bid
Easement agreement with Canandian Pacific is currently 1
145th Street Pedestrian being reviewed by the City Attorney(agreement is already in
447 Improvements at RR 01/02/13 N/A N/A UPRR,CPRR, place with Union Pacific). Railroad work will begin after
Crossing TBD agreement is executed. Sidewalk work will begin after
railroad work. Sidewalk has already been installed on the
southwest corner adjacent to the Park&Ride.
KRB Development I,LLC is administering the contract
450 Prestwick Place 8th N/A N/A PRIVATE 07/28/14 N/A S.R.Weidema PRIVATE privately. Base course paving is complete and small utilities
have been installed. Project is on hold for the winter.
Ryan Project is on hold for the winter. The roadway will remain
452 Bacardi Avenue 11/19/13 02/18/14 02/18/14 03/21/14 06/03/14 06/16/14 05/06/14 Contracting $2,922,416 $2,320,510 79% gravel through the winter. Roadway and trail paving will be
Improvements
Company completed in 2015.
Danbury Way Council authorized the preparation of a feasibility report on
453 Reconstruction N/A N/A 11/3/14. Construction is planned for 2016.
Northwest This development includes 28 single-family homes by
454 Bella Vista 2nd 11/19/13 N/A 03/04/14 03/21/14 06/03/14 10/06/14 N/A Asphalt,Inc. $762,308 $535,709 70% developer U.S.Home Corporation(Lennar). Project is on
hold for the winter.
455 2014 Street 01/07/14 05/20/14 03/18/14 04/04/14 06/03/14 06/09/14 05/20/14 Valley Paving, $630,418 $525,991 83% Project is substantially complete.
Improvement Project Inc.
This development includes 26 single-family homes by
457 Prestwick Place 10th 07/15/14 N/A 08/04/14 08/12/04 08/19/14 08/25/14 N/A S.R.Weidema $698,832 $546,343 78% developer U.S.Home Corporation(Lennar). Project is on
hold for the winter.
Nodland Ryland Homes is administering the contract privately. Base
458 Greystone 3rd N/A N/A PRIVATE 09/22/14 N/A Construction PRIVATE course paving is complete and small utilities have been
installed. Project is on hold for the winter.
Council approved development on 11/18/14. Design will
459 Wilde Lake Estates N/A N/A PRIVATE N/A PRIVATE begin when the subdivision agreement is executed by the
developer.
G:IENGPROJIProject Tracking\Project Update Updated: 1/5/2015