HomeMy WebLinkAbout8.a. City Projects Update
City Projects Update
Council
City
Council
Receives
Public Award Assessment Contract Payments %
Project Project NameOpen BidsStart DateContractorSummary
Authorizes
Plans/Specs.
HearingContractHearingAmountTo DateComplete
Authorize Ad
Plans/Specs
Number
For Bid
A preconstruction meeting with E.H. Renner & Sons, Inc. was
E.H. Renner & held on May 11, 2015. Construction of the production well will
$422,585
416Well 1610/01/13N/A11/18/1402/27/1503/17/15N/A
Sons, Inc.be completed in 2015; construction of the well house will be
completed in 2016.
Easement agreement with Canandian Pacific is currently being
reviewed by the City Attorney (agreement is already in place
145th Street Pedestrian
UPRR, CPRR, with Union Pacific). Railroad work will begin after agreement
Improvements at RR 01/02/13N/AN/A
447
TBDis executed. Sidewalk work will begin after railroad work.
Crossing
Sidewalk has already been installed on the southwest corner
adjacent to the Park & Ride.
KRB Development I, LLC is administering the contract
PRIVATEPRIVATE
450Prestwick Place 8thN/AN/A07/28/14N/AS.R. Weidema
privately. Project is substantially complete.
Ryan Final paving was completed the week of May 11. The
Bacardi Avenue
$2,922,416$2,591,61589%
11/19/1302/18/1402/18/1403/21/1406/03/1406/16/1405/06/14Contracting contractor is currently working on the pedestrain bridge
452
Improvements
Companyabutments.
Danbury Way Council authorized the preparation of a feasibility report on
453
Reconstruction11/3/14. Construction is planned for 2016.
This development includes 28 single-family homes by
developer U.S. Home Corporation (Lennar). Curb and gutter
Northwest
$762,308$564,51074%
Bella Vista 2nd11/19/13N/A03/04/1403/21/1406/03/1410/06/14N/Ahas been installed and base course paving was completed the
454
Asphalt, Inc.
week of May 11. Curb backfilling and prep work for small
utility installation continues.
This development includes 26 single-family homes by
$698,832$583,93984%
Prestwick Place 10th07/15/14N/A08/04/1408/12/0408/19/1408/25/14N/AS.R. Weidemadeveloper U.S. Home Corporation (Lennar). The project is
457
substantially complete.
Ryland Homes is administering the contract privately. Base
Nodland course paving is complete and small utilities have been
PRIVATEPRIVATE
458Greystone 3rdN/AN/A09/22/14N/A
Constructioninstalled. Final paving is scheduled to be completed by the
end of May.
This development includes 14 single-family homes by
Friedges developer Friedges Excvating, Inc. Friedges is administering
PRIVATEPRIVATE
459Wilde Lake EstatesN/AN/A04/27/15N/A
Contractingthe contract privately. The subdivision agreement was
executed on November 18, 2014.
This development includes 47 single-family homes by
developer Ryland Homes. Ryland Homes is administering the
Nodland
PRIVATEPRIVATE
Greystone 4thN/AN/A04/13/15N/Acontract privately. Storm sewer installation is scheduled to be
462
Construction
completed the week of May 11. Roadway subgrade prep work
will follow.
This development includes 34 single-family homes by
Nodland developer U.S. Home Corporation (Lennar). Lennar is
PRIVATEPRIVATE
463Prestwick Place 11thN/AN/A05/18/15N/A
Constructionadministering the contract privately. Utility installation is
scheduled to begin mid-May.
This development includes 28 single-family homes by
developer U.S. Home Corporation (Lennar). Lennar is
PRIVATEPRIVATE
464Bella Vista 3rdN/AN/AN/A
administering the contract privately. The subdivision
agreeement is expected to be approved on April 21, 2015.
G:\\ENGPROJ\\Project Tracking\\Project UpdateUpdated: 05/14/2015