HomeMy WebLinkAbout6.h. Steeple Center Addition Project Change Order #2
EXECUTIVE SUMMARY
City Council Regular Meeting: July 7, 2015
AGENDA ITEM: Steeple Center Addition Project Change
Order #2
AGENDA SECTION:
Consent
PREPARED BY: Dan Schultz, Parks and Recreation
Director AGENDA NO. 6.h.
ATTACHMENTS: Proposed Change Order APPROVED BY: ddj
RECOMMENDED ACTION: Motion to approve Change Order #2 for the items listed in the
executive summary and to increase the Steeple Center project contract by $11,758.18.
ISSUE
At the June 2, 2015 regular City Council meeting, the Council approved adding a card reader access system
to the Steeple Center project. The card reader system was approved as Change Order #2 for the project.
Since the June 2 meeting, there have been several small changes to the project that need to be added to
Change Order #2. The changes and dollar amounts are listed below and are also attached to the executive
summary:
Added Item Cost
Extended use of temporary heat $2,660.00
Asbestos abatement $3,196.60
Move duct work for operable partition $1,993.60
Restrooms tile underlayment $666.40
Add wood post column $1,128.86
Add water service $512.96
Add power for portable kiln $1,333.20
Add water filter to ice machine $266.56
Total $11,758.18
Staff has reviewed the change order requests and feels that all of the changes to the project are necessary
and will leave us with a better end product.
SUMMARY
Staff is recommending that the City Council approve Change Order #2 with the additional items listed in
the executive summary, increasing the project contract by $11,758.18.