Loading...
HomeMy WebLinkAbout6.h. Steeple Center Addition Project Change Order #2 EXECUTIVE SUMMARY City Council Regular Meeting: July 7, 2015 AGENDA ITEM: Steeple Center Addition Project Change Order #2 AGENDA SECTION: Consent PREPARED BY: Dan Schultz, Parks and Recreation Director AGENDA NO. 6.h. ATTACHMENTS: Proposed Change Order APPROVED BY: ddj RECOMMENDED ACTION: Motion to approve Change Order #2 for the items listed in the executive summary and to increase the Steeple Center project contract by $11,758.18. ISSUE At the June 2, 2015 regular City Council meeting, the Council approved adding a card reader access system to the Steeple Center project. The card reader system was approved as Change Order #2 for the project. Since the June 2 meeting, there have been several small changes to the project that need to be added to Change Order #2. The changes and dollar amounts are listed below and are also attached to the executive summary: Added Item Cost Extended use of temporary heat $2,660.00 Asbestos abatement $3,196.60 Move duct work for operable partition $1,993.60 Restrooms tile underlayment $666.40 Add wood post column $1,128.86 Add water service $512.96 Add power for portable kiln $1,333.20 Add water filter to ice machine $266.56 Total $11,758.18 Staff has reviewed the change order requests and feels that all of the changes to the project are necessary and will leave us with a better end product. SUMMARY Staff is recommending that the City Council approve Change Order #2 with the additional items listed in the executive summary, increasing the project contract by $11,758.18.