City Projects Update
Council
City Council Receives
Public Award Assessment Contract Payments %
Project Project NameAuthorizes Plans/Specs Open BidsStart DateContractorSummary
HearingContractHearingAmountTo DateComplete
NumberPlans/SpecsAuthorize Ad
For Bid
Drilling of the production well began in May. An obstruction was encountered during installation of the 30-inch casing at approximately
E.H. Renner &
416$422,585$63,15315%
Well 1610/01/13N/A11/18/1402/27/1503/17/1505/26/15N/A141 feet. The design was modified to a triple-cased design: a 24-inch casing will be drilled to the original depth (approximately
203 feet)
Sons, Inc.
and an additional 18-inch inner liner casing will be added to the design. Completion is expected in January, 2016.
Wells 4 & 5 Abandoned Well 5 in Chippendale Park, which was originally planned to be used as observation well, will not be suitable. Well 5 will be
N/A
Sealing, New N/A09/01/1509/29/1510/06/15Oct 2015N/Asealed along with Well 4 later this year. A new observation well will be constructed at Chippendale Park to satisfy the requirements
of
Observation Wellthe appropriations permit for Well 16. MDH and Dakota County grants have been obtained to help offset the cost of these projects.
145th Street
Easement agreement with Canandian Pacific is currently being reviewed by the City Attorney (agreement is already in place with Union
Pedestrian UPRR, CPRR,
447
01/02/13N/AN/APacific). Railroad work will begin after agreement is executed. Sidewalk work will begin after railroad work. Sidewalk has already been
Improvements at TBD
installed on the southwest corner adjacent to the Park & Ride.
RR Crossing
Danbury Way Council authorized the preparation of a feasibility report in November 2014. A Public Hearing was held on July 21, 2015. Council
453
07/21/1507/21/15
Reconstructionordered the prorject and authorzied the Plans & Specs on July 21, 2015. Construction is planned for 2016.
Friedges This development includes 14 single-family homes by developer Friedges Excvating, Inc. Friedges is administering the contract
PRIVATEPRIVATE
459
Wilde Lake EstatesN/AN/A04/27/15N/A
Contractingprivately. Contractor is waiting for materials to be deliverd to the site before continuing with construction.
Nodland This development includes 47 single-family homes by developer Ryland Homes. Ryland Homes is administering the contract privately.
PRIVATEPRIVATE
462
Greystone 4thN/AN/A04/13/15N/A
ConstructionBase course paving, sidewalk, trail and utilites are installed.
Prestwick Place Nodland This development includes 34 single-family homes by developer U.S. Home Corporation (Lennar). Lennar is administering the contract
PRIVATEPRIVATE
463
N/AN/A05/18/15N/A
11thConstructionprivately. Small utility installation is underway.
This development includes 28 single-family homes by developer U.S. Home Corporation (Lennar). Lennar is administering the contract
PRIVATEPRIVATE
464
Bella Vista 3rdN/AN/A08/03/15N/ASR Weidema
privately. Mass grading has been completed, saniary sewer installation is underway.
132nd Street West
465
09/01/15Council authorized the preparation of a feasibility report on June 2, 2015.
Improvements
Horseshoe Lake Council authorized final design on May 5, 2015. Plans and specifications will be complete in August. Construction is anticipated Fall,
466
05/05/15N/A08/18/1509/04/1509/15/15N/A
Lift Station2015.
Dunmore 1st This development includes 30 single-family homes by developer Copper Creek. The final plat and subdivision agreement are expected
467
N/A
Additionto be approved at the August 18, 2015 City Council meeting.
Prestwick Place This development includes 31 single-family homes by developer KRB Development I, Inc. KRB is administering the contract privately.
PRIVATEPRIVATE
468
N/AN/ATBDN/ATBD
12thMass grading is currently being completed.
Request for Proposals have been received from five engineering consultants for the design and construction administration of a new
1.5MG Ground Winter
ENG-179
N/AN/A1.5MG ground storage tank and booster station to be located adjacent to the Bicardi Elevated Storage Tank (Tower). Staff will review
Storage Tank2016
the proposals and make a selection in late-August.