HomeMy WebLinkAbout8.a. Project Update
City Projects Update
Council
City Council
Receives
Public Award Assessment Contract Payments %
Project Project NameAuthorizes Open BidsStart DateContractorSummary
Plans/Specs
HearingContractHearingAmountTo DateComplete
NumberPlans/Specs
Authorize Ad
For Bid
E.H. Renner &
416$433,424$346,01580%
Well 1610/01/13N/A11/18/1402/27/1503/17/1505/26/15N/ADrilling of the production well is complete. Test pumping is expected to occur in the next few weeks.
Sons, Inc.
145th Street
Easement Agreement recently signed by Canadian Pacific. Agreement already in place with Union Pacific. Railroad work for UP will
Pedestrian UPRR, CPRR,
447
01/02/13N/AN/Abegin soon. An agreement with CP for the track extensions can be established now that the easement agreement has been executed.
Improvements at TBD
Upon execution of the agreement with CP for the track extensions, work will begin. Sidewalk work will begin after railroad work.
RR Crossing
Danbury Way Plans & Specs have been received by Council. The bid opening is scheduled for February 19, 2016 and the contract is expected to be
453
07/21/1507/21/1501/19/1602/19/1604/19/16June 201604/19/16
Reconstructionawarded April 19, 2016.
This development includes 47 single-family homes by developer Ryland Homes. Ryland Homes is administering the contract
Nodland
PRIVATEPRIVATE
462
Greystone 4thN/AN/A04/13/15N/Aprivately. Base course paving, temporary cul-de-sac, sidewalk, trail and utilities are installed. Wear course paving will occur in
Construction
summer 2016.
Prestwick Place Nodland This development includes 34 single-family homes by developer U.S. Home Corporation (Lennar). Lennar is administering the
PRIVATEPRIVATE
463
N/AN/A05/18/15N/A
11thConstructioncontract privately. This project is substantially complete. Wear course paving will occur in summer 2016.
This development includes 28 single-family homes by developer U.S. Home Corporation (Lennar). Lennar is administering the
PRIVATEPRIVATE
464
Bella Vista 3rdN/AN/A08/03/15N/ASR Weidema
contract privately. Base course paving is complete. Sidewalks and wear course paving will be complete in summer 2016.
132nd Street West Council received the feasibility report and assessment agreement on October 6, 2015. This project is on hold until the status of the
465
N/A
ImprovementsDunmore project is determined.
Horseshoe Lake Ryan
466$645,933$405,93363%
05/05/15N/A08/18/1509/04/1509/15/1510/19/15N/AUnderground utilities were completed in November. Electrical work, site work, and restoration will be completed by summer 2016.
Lift StationContracting
Dunmore 1st
467
N/AThis development includes 30 single-family homes by developer Copper Creek. This project is on hold by the developer.
Addition
Prestwick Place This development includes 31 single-family homes by developer KRB Development I, Inc. KRB is administering the contract privately.
PRIVATEPRIVATE
468
N/AN/ATBDN/ATBD
12thBase course paving is complete. Sidewalks and wear course paving will be completed in summer 2016.
This development includes 14 single-family homes by developer U.S. Home Corporation (Lennar). Lennar is expected to administer
PRIVATEPRIVATE
469
Bella Vista 4thN/AN/AN/A
the contract privately. Construction is expected to begin in spring 2016.
Northern Air
ENG-176$144,530$144,530100%
City Hall GeneratorN/A06/16/1507/10/1507/21/1507/27/15N/AThis project is complete. The generator has been tested under full load and is fully functional.
Corporation
WSB & Associates, Inc. is the engineering consultant for the design and construction administration of the tank and booster station.
1.5MG Ground Due to a significant increase in the overall cost estimate for the project ($4.14 million vs. $6.03 million), the plans and specs have
ENG-179
09/01/15N/A12/15/1502/05/16N/A
Storage Tankbeen reviewed by an alternate engineering firm. Bids were opened February 5, 2016 but the award of the contract is on hold pending
the result of the peer review.
Bids were opened September 29, 2015 and a contact was to be awarded October 6, 2015. The low bidder, Keys Well Drilling, was the
original contractor for Well 5 construction in 1963. The contractor produced construction records for Well 5 that have complicated the
Wells 4 & 5 sealing project. Further investigation with the MDH has resulted in the need for adjustments in the abandonment method for Well 5;
Keys Well
ENG-181$39,250
Sealing, New N/A09/01/1509/29/1511/17/15On HoldN/Atherefore, the contract has been awarded for Well 4 only, with a plan to seal Well 4 or convert it to an obersation well, if possible.
A
Drilling
Observation Wellseparate contract will be awarded in the future to seal Well 5, and to construct a new observation well if Well 4 is not able to be
converted with the original contract. The cleaning out of Well 4 is complete. The MDH will televise and inspect the well in the next few
weeks to determine the next course of action.
Short Elliot
An RFP was distributed to three engineering fiirms to conduct a utility study for the area of Rosemount east of US52. SEH is the
East Side Utility and
ENG-183$35,505
N/AN/AN/A11/12/15N/A11/23/15N/Aselected engineering consultant for the study. The study is necessary in order to provide adequate service for a possible large
StudyHendrickson
industrial site development, and to use the opportunity to prepare trunk utility facilities for additional future development.
(SEH)
C:\\Users\\klk\\AppData\\Local\\Temp\\8.a. Project Update_347695\\8.a. Project UpdateUpdated: 02/17/2016