EXECUTIVE SUMMARY
City Council Regular Meeting: May 3, 2016
AGENDA ITEM: Authorize Preparation of Feasibility
Report for 2017 - 2019 Street
Improvements Project, City Project 470
AGENDA SECTION:
New Business
PREPARED BY: Mitch Hatcher, Project Engineer AGENDA NO. 9.b.
ATTACHMENTS: Proposal; Resolution; Map APPROVED BY: ddj
RECOMMENDED ACTION: Motion to Adopt a Resolution Authorizing the Preparation of a
Feasibility Report for the 2017 - 2019 Street Improvements Project, City Project 470.
BACKGROUND:
Beginning in 2010, the City initiated a plan to prepare multi-year feasibility reports with the intention of
providing a longer range look at upcoming projects and allowing for more advance notice to property
owners. As a result, each year’s feasibility study will review and update the current project, as well as
provide information about the proposed improvements for the following two years.
At the February 8, 2016 City Council Work Session, Council was presented the revisions to the Pavement
Management Program and preliminary 10-year Capital Improvement Plan. From the 10-year CIP, the
following table highlights the proposed projects for 2017-2019.
The attached map identifies the roadways proposed to be evaluated in the 2017 - 2019 feasibility report.
The following information will be included in the report:
Existing conditions with detailed information on the existing materials
Proposed improvements
Detailed cost estimates and proposed funding sources
Estimated assessments
Year Project Area Classification Current
PCI Project Type
2017 Shannon Hills B Local 29 M&O
Shannon Parkway A - CSAH 42 to CSAH 46 MSA 20 Reconstruction
2018
Motz Local 48 M&O
Biscayne Pointe A Local 45 M&O
Biscayne Avenue C - Connemara Trail to CSAH 42 MSA 49 M&O
2019
O'Leary's Hills A Local 48 M&O
O'Leary's Hills B Local 55 M&O
Carrollton C Local 55 M&O
145th Street C - TH 3 to CSAH 42 MSA 58 M&O
Oak Ridge Estates Rural 48 M&O
2
WSB & Associates, Inc. has provided a proposal for the engineering services to complete the Feasibility
Report. The estimated engineering fee is $20,998. This includes the following activities:
Preparation of feasibility report
Conducting one public informational meeting
Public coordination including the preparation of informational letters, invitations, web page
updates, and response to resident questions and inquiries
Presentation of final report to City Council at the Public Hearing
A detailed breakdown of the proposal scope and fee has been attached.
The preliminary estimated cost for improvements proposed in 2017 is $980,000. This represents an
estimated fee percentage of 2.1%.
SUMMARY:
Staff recommends Council approval of the attached resolution to authorize the preparation of a feasibility
report for the 2017 - 2019 Street Improvements Project.
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2016 –
A RESOLUTION AUTHORIZING THE PREPARATION
OF A FEASIBLITY REPORT FOR THE
2017 - 2019 STREET IMPROVEMENTS PROJECT
CITY PROJECT 470
WHEREAS, the City Council of the City of Rosemount deems it necessary to investigate the
feasibility of the 2017 - 2019 Street Improvements Project.
NOW THEREFORE BE IT RESOLVED, The City Engineer is directed to have the necessary
feasibility report prepared for the 2017 - 2019 Street Improvements Project.
ADOPTED this 3rd day of May, 2016.
William H. Droste, Mayor
ATTEST:
Clarissa Hadler, City Clerk
Building a legacy ǤƚǒƩ legacy. 540 Gateway Boulevard
Burnsville, MN 55337
Tel: 952-737-4660
Fax: 763-541-1700
May 3, 2016
Mr. Patrick Wrase
Director of Public Works/City Engineer
City of Rosemount
th
2875 145 Street West
Rosemount, MN 55068
RE: Scope and Estimated Fee to Provide Professional Engineering Services for
2017-2019 Street Improvement Program Feasibility Report
Dear Mr. Wrase:
We appreciate the opportunity to present this proposal for professional services related to the pavement
management program and 2017-2019 Street Improvement Program. This letter proposal outlines the
services required to prepare all necessary documents to complete the 2017-2019 Street Improvement
Program Feasibility Report.
PROJECT BACKGROUND
Beginning in 2010, the City initiated a plan to prepare multi-year feasibility reports with the intention of
providing a longer range look at upcoming projects and allowing for more advance notice to property
owners.
At the February 8, 2016 City Council Work Session, Council accepted the revisions to the Pavement
Management Program (PMP) and preliminary 10-year Capital Improvement Plan. From the 10-year CIP, the
following table highlights the proposed projects for 2017-2019.
Year Project Area Classification Project Type
Shannon Hills B Local M&O
2017
Shannon Parkway A - CSAH 42 to CSAH 46 MSA Reconstruction
Motz Local M&O
2018 Biscayne Pointe A Local M&O
Biscayne Avenue C - Connemara Trail to CSAH 42 MSA M&O
O'Leary's Hills A Local M&O
O'Leary's Hills B Local M&O
2019 Carrollton C Local M&O
145th Street C - TH 3 to CSAH 42 MSA M&O
Oak Ridge Estates Rural M&O
Equal Opportunity Employer
wsbeng.com
K:\\02235-100\\Admin\\Docs\\LTR Proposal - Rosemount - 050316 - 2017-2019 SIP.docx
Mr. Patrick Wrase
May 3, 2016
Page 2
PROJECT UNDERSTANDING
The feasibility report will take the information from the PMP and detail the 2017-2019 street improvement
projects.
The City's PMP evaluates projects based on pavement conditions. During the feasibility stage of projects,
city utilities should be evaluated. Of the project areas identified for 2017-2019, the Motz neighborhood in
particular should be evaluated as it was originally constructed in 1960. The sanitary sewer is vitrified clay
pipe (VCP) sanitary sewer and cast iron pipe (CIP) watermain. Additionally, there has been a question in the
past about the capacity of the sanitary sewer along 143`d Street that receives flow from the sanitary lift
station for the school district.
To evaluate the city utilities in this area, WSB will meet with city staff to discuss items such as watermain
breaks, tree root intrusion, sewer capacity, hydrant and gate valve operation, and determine if a sanitary
sewer televising report is necessary for further evaluation.
PROJECT APPROACH/SCOPE OF SERVICES
WSB's project scope and proposed work plan are based on our understanding of the project as previously
described. In order to complete the project,we propose the following scope of services:
Task 1: Feasibilitv Report
WSB will complete the feasibility report for the 2017-2019 Street Improvement Program, including, but
not limited to:
■ Data collection
■ Existing conditions
■ Drawings and figures
■ Quantity and cost estimates
■ Funding breakdown
■ Preliminary assessment rolls and calculations
■ Project schedule
■ Feasibility and recommendation
Cost: $14,132
Task 2: Pavement Analvsis
WSB will conduct pavement cores throughout the proposed project areas to confirm the assumptions
made with the PMP, and for informational purposes while completing the preliminary and final design.
The most recent set of pavement cores were completed was in 2012. Pavement cores will be conducted
in the 2017-2019 project areas totaling approximately fifty(50)cores.
Cost: $2,250
K:\02235-300\Atlmin\Docs\LTR Proposal-Rosemowt-050316-2017-2019 SIP.doa
Mr. Patrick Wrase
May 3, 2016
Page 3
K:\02235-100\Admin\Docs\LTR Proposal - Rosemount - 050316 - 2017-2019 SIP.docx
Task 3: Utility Analysis
As is the case with older neighborhoods in Rosemount, many city utilities are in need of improvement.
It is practical, cost effective, and provides limited disturbance to residents to complete utility and street
improvements project concurrently. WSB will review and evaluate, with City Staff, televising reports
provided by others to determine the need for utility work in the project areas.
Cost: $1,260
Task 4: Public Involvement
WSB will prepare meeting materials and presentations and attend neighborhood open house meetings
and City Council meetings that pertain to the 2017-2019 street improvements.
Cost: $1,536
Task 5: City Project Engineer Coordination
As the role of Assistant City Engineer/Project Engineer, WSB will provide city related tasks and
coordination at reduced hourly rates.
Cost: $600
SCHEDULE
WSB will complete the project within three months of receipt of a written authorization.
PROPOSED FEE
We propose to conduct the work listed above on an hourly basis for an estimated total fee of $20,998.00.
We will review our progress weekly and will not exceed this amount without your prior approval should the
scope of the project change.
This letter represents our entire understanding of the project scope. If you are in agreement, please sign on
the space provided and return one original signed copy to us for our records. We will start immediately
upon receipt of the signed agreement.
If you have any questions concerning the work plan or fee as discussed, please feel free to contact me at
(763) 287-7191. We look forward to working with you and greatly appreciate the opportunity to assist you
and your staff in the completion of this project.
Mr. Patrick Wrase
May 3, 2016
Page 4
K:\02235-100\Admin\Docs\LTR Proposal - Rosemount - 050316 - 2017-2019 SIP.docx
Sincerely,
WSB & Associates, Inc.
Andy Brotzler, PE Krista Anderson, PE
Principal/Senior Project Manager Project Engineer
Enclosures
cc: Mitch Hatcher, WSB & Associates, Inc.
jmh
ACCEPTED BY: CITY OF ROSEMOUNT, MN
Signature:
Name/Title:
Date:
Task Description11.1 Project Management 4 8 820$2,312.001.2 Project Meetings 4 2 4 212$1,418.001.3 Data Collection4812$1,072.001.4 Report 8142226$2,608.001.5 Drawings / Figures268$764.001.6 Quantity Tabulations and Cost Estimate 2 8 12 1234$3,408.001.7 Assessments2248$760.001.8 QA / QC 6 6214$1,790.00Task 1 Total Estimated Hours and Fee 16 34 44 30 4 6 134 $14,132.0022.1 Coring 66$1,410.002.2Analysis448$840.00Task 2 Total Estimated Hours and Fee 4 46 14 $2,250.0033.1 Sanitary Sewer and Water Main Analysis 4 6 6 622$1,260.00Task 3 Total Estimated Hours and Fee 4 6 6 622 $1,260.0044.1 Presentation and Meeting Prep44$392.004.2 Neighborhood Open House Meetings44$392.004.3 City Council Meetings4610$752.00Task 4 Total Estimated Hours and Fee12 6 18 $1,536.0055.1 City Coordination1010$600.00Task 5 Total Estimated Hours and Fee10 10 $600.00Total Estimated Hours 16 4 44 6 66 30 4 16 6 6 198Average Hourly Billing Rate158.00 158.00 112.00 98.00 98.00 85.00 85.00 60.00 235.00 99.00Total Fee by Labor Classification $2,528.00 $632.00 $4,928.00 $588.00 $6,468.00 $2,550.00 $340.00 $960.00 $1,410.00 $594.00 $20,998.00TOTAL PROJECT COST $20,998.00Two Person Coring CrewCostTotal HoursGIS SpecialistFeasibility ReportProject Manager Project EngineerEstimate of CostCity of Rosemount, MinnesotaProfessional Engineering Services2017 - 2019 Street ImprovementsEstimated HoursCity Project EngineerCity Project Engineer Coordination Pavement AnalysisUtility AnalysisPrincipalAdminPublic InvolvementGraduate EngineerWater/Waste Water Project ManagerWater/Waste Water Project Engineer
M
e
a
d
o
w
s P
a
r
k
CentralParkInnisfree ParkBirchPark
B loom field P arkClaretPark
EricksonPark
CarrollsWoodsPark
RMSPark
Charlie's Park
JayceePark
LionsPark
ShannonPark
Winds ParkTwin PuddlesKidderParkBiscayne ParkConnemaraPark
Schwarz Pond Park
Tw in PuddlesDallaraPark
Innisfree Park
Schwarz Pond Park
FamilyRes Ctr
ChippendalePark
CamfieldPark
BrockwayPark
BrockwayPark
Ames SoccerComplex
UMore BallPark
Ailesbury Park
Flint HillsAthletic Complex
WiklundPreserve
Horseshoe Park
Proposed 3-Year CIPImprovements 2017,2018 & 2019
Document Path: T:\GIS\City\Maps\Departmental Maps\Engineering\CIP\Proposed 3 Year CIP_Pavement_8x11.mxd
2017 2018 2019