HomeMy WebLinkAbout2.a. Fire Station IIAGENDA ITEM: Fire Station II AGENDA SECTION: PREPARED BY: Dawn Weitzel, ssistant City Administrator AGE 2 Y ATTACHMENTS: Potential Cost Savings Revised Project Budget APPROVED BY: RECOMMENDED ACTION: Give direction on how to proceed with the constru ion of Fire Station 1I 1 4 ROSEMOUNT CITY COUNCIL City Council Work Session. November 9, 2005 EXECUTIVE SUMMARY BACKGROUND Bid results of the Fire Station II project have been recorded at approximately $400,000 over the estimated construction hard costs Todd Christopherson, from AMCON, indicated to Council that this is due to a combination of issues: the increase in energy and fuel costs, economic turmoil caused by a natural disaster, underestimation, and items on the bid plan that may have skewed results. At the October 12 Work Session Council gave Staff direction to move forward with the excavation and site utilities portion of the project and re -bid the construction project. Staff was also asked to review the project and "value engineer" when appropriate to reduce the estimated hard construction costs. ISSUE As a result, Staff met with Todd Christopherson and Scott Mohs from AMCON and architect Mark Vetter to discuss ways to reduce the hard construction costs of this project. The group went through a list of 41 possible changes to the project that could potennally save some money. The attachment to this document shows the 17 changes that would least affect the overall aesthetics and quality of the facility. The largest cost savings can be found in the areas of: ehmmanon of winter condition expenses; expansion of the types of manufacturers for the metal panels, the screen wall and metal roof; and ehminanon of the small sunshades over the windows. The window treatments and flag pole will not be bid with the project The cost of these two items will be billed out of FFE The estimated reduction in cost of the 17 items listed will fluctuate up or down. If cost savings in re- bidding the project are greater than anticipated, some of the more desirable items on the hst may be retained (e.g rock -face block pattern on north and west sides of building) The altered bidding document, which will include the potential cost saving "alternates," will be available for review on December 14 REVISED SCHEDULE November 2 November 30: site excavation and utility construction November 9: Council Work Session, review design changes November 1 5: Regular Council Meeting. reject project bids December 14• Council review of redesign and budget Januaty 3 January 26 bidding period January 26 bid opening February 15 Council Work Session, review bids February 21: Regular Council Meeting, award contracts March: Mobilize for construction REVISED PROECT BUDGET The revised budget shows a deficit of approximately $200,000. It has been advised that $100,000 of this deficit can safely be transferred from contingency. It should also be noted that due to the project changes there will be additional charges m architect and construction manager fees; it is unclear at this point what the increase in professional services fees would mean to the budget. 2 Funding Source ROSEMOUNT FIRE STATION #2 PROJECT BUDGET S -1 Bond Referendum (Net Proceeds) 2,500,000 S -2 Interest Income S-4 Transfer of Funds (CIP) 250,000 Total 2,750,000 Code Expenditures Base Design Land Acquisition Development 1 Land Cost 2 Subtotal Project Development Costs 3 A/E Services Allowance (incl Civil, Struct M /E) 154,675 4 A/E Reimbursed Expenses 15,000 5 Geotechnical Services 2,600 6 Construction Testing 7,000 8 City Connnection and SAC/WAC fees 57,250 9 Bid Advertisement and Printing 14,000 Construction Cost 10 Construction Management Fee 77,338 11 Survey Staking 12 General Conditions 158,825 13 Construction Hard Costs 2,430,779 Potential Cost Savings (217,000) 14 Voice, Video, Data Equip. Connectivity (project costs) 13,000 15 FFE (project and design costs) 24,000 16 Contingency 211,000 Fund Balance Subtotal 250,525 Subtotal 2,697,942 Total 2,948,467 (198,467) 11/1/2005 M:104037 Rosemount Fire Station #21Budget\Rosemount Budget .xls 1 Rosemount Fire Station #2 Rosemount, MN 11 -1 -05 Potential Cost Savings I. General winter conditions (heating costs during construction). $25,000 2. Concrete Masonry winter conditions. $50,000 3 Change bituminous base (recycled concrete in lieu of limestone). $2,500 4. Change highland sod to peat sod. $2.000 5. Change linoleum to VCT. $7,500 6. Change metal panel, screen wall and metal roof manufacturer. $30,000 7. Change rock -face block pattern on north and west sides of building. $7,500 8. Eliminate sunshades over windows. $20,000 9. Eliminate window treatments (added $6,000 into FFE). $25,000 10. Change coiling fire door to galvanized metal. $1,000 11 Change counters and window sill to plastic laminate cultured marble. $10,000 12 Eliminate part of screen wall. $1,500 13. Eliminate flag pole. $4,000 14. Change ceiling tile manufacturer. $3,000 15. 4' high tile in bathrooms locker rooms in lieu of tile to ceiling. $8,000 16 Alternative fighting package. $10,000 17. Change generator equipment. $10 000 TOTAL POTENTIAL COST SAVINGS $217,000 These potential cost savings are estimates based on some general discussions. These numbers may fluctuate up or down as more detail becomes available. 11 /1 /2005