HomeMy WebLinkAbout8.a. City Projects UpdateG:\ENGPROJ\Project Tracking\Project Update Updated: 11/9/2016
City
Project
Number
Project Name
Council
Authorizes
Plans/Specs
Public
Hearing
Council
Receives
Plans/Specs
Authorize Ad
For Bid
Open Bids Award
Contract Start Date Assessment
Hearing Contractor Contract
Amount
Work
Certified To-
Date
%
Complete Summary
416 Well 16 10/01/13 N/A 11/18/14 02/27/15 03/17/15 05/26/15 N/A E.H. Renner &
Sons, Inc.$433,105 $380,658 88%Drilling of the production well is complete. Well house design is underway, with construction scheduled for 2017.
447
145th Street
Pedestrian
Improvements at
RR Crossing
01/02/13 N/A N/A UPRR, CPRR,
TBD
Easement Agreement recently signed by Canadian Pacific. Agreement already in place with Union Pacific. Railroad work for UP will
begin soon. An agreement with CP for the track extensions can be established now that the easement agreement has been executed.
Upon execution of the agreement with CP for the track extensions, work will begin. Sidewalk work will begin after railroad work.
453 Danbury Way
Reconstruction 07/21/15 07/21/15 01/19/16 02/19/16 04/19/16 June 2016 04/19/16 McNamara
Contracting $1,234,504 $1,203,825 98%Project is complete.
465 132nd Street West
Improvements N/A Council received the feasibility report and assessment agreement on October 6, 2015. This project is on hold until the status of the
Dunmore project is determined.
466 Horseshoe Lake
Lift Station 05/05/15 N/A 08/18/15 09/04/15 09/15/15 10/19/15 N/A Ryan
Contracting $656,571 $651,571 99%Project is substantially complete. Lift station is online and running. Punch list items remain.
467 Dunmore 1st
Addition N/A This development includes 30 single-family homes by developer Copper Creek. Copper Creek is expected to administer the contract
privately, but the project is temporarily on hold.
469 Bella Vista 4th N/A N/A N/A SR Weidema Project is substantially complete. Punch list items remain.
473 Prestwick Place
13th N/A N/A N/A This development includes 28 single-family homes by developer KRB Development I, Inc. Project is nearing completion for this
season. Sidewalks and wear course will be completed Spring 2017.
474 Greystone 5th N/A N/A N/A This development includes 23 single-family homes by developer CalAtlantic Homes (formerly Ryland Homes). The developer will
administer the contract privately. Final plat approval is expected in November, 2016. Construction to begin in Spring 2017.
ENG-180 Safe Routes to
School 10/20/15 04/05/16 06/21/16 08/02/16 August
2016
Max
Steininger,
Inc.
$450,550 $234,358 52%Project is substantially complete. Punch list items remain.
ENG-181
Wells 4 & 5
Sealing, New
Observation Well
N/A 09/01/15 09/29/15 11/17/15 On Hold N/A Keys Well
Drilling $39,250 $31,750 81%Well 4 has been converted to an observation well. Well 5 has been drilled out, ready to be sealed in the future. Final payment was
authorized by Council on October 18, 2016.
ENG-186
ENG-188
Parking Lot
Maintenance N/A N/A N/A N/A N/A Spring
2017 N/A
The Connemara Park and City Hall parking lots are scheduled for maintenance in 2016. In-house staff is working on the design for the
Connemara Park lot; WSB is doing the design for the City Hall lot. Both projects will be bid together and will include curb & gutter
enhancements/replacement, as well as full pavement replacement. Construction is expected in spring 2017.
City Projects Update