HomeMy WebLinkAbout20161017 UC Minutes
UTILITY COMMISSION
REGULAR MEETING MINUTES
October 17, 2016
CALL TO ORDER
Pursuant to due call and notice thereof the regular Utility Commission meeting of the City of Rosemount
th
was called to order on October 17, 2016, at 5:30 p.m. in the Conference Room of the City Hall, 2875 145
Street West, Rosemount.
President Connolly called the meeting to order with Commissioners McDonald and Nelson, Rosemount
Mayor Droste, City Administrator Johnson, Public Works Coordinator Watson, Public Works Interim
Director John Morast, and Recording Secretary Erin Fasbender attending.
ADDITIONS OR CORRECTIONS TO AGENDA
AUDIENCE INPUT
None
APPROVAL OF MINUTES
Motion by Nelson Second by McDonald
Motion to approve the minutes of the September 19, 2016 Utility Commission meeting
Ayes: 3.
Nays: 0. Absent: 0. Motion carried.
Motion by Connolly Second by McDonald
Motion to approve the minutes of the October 7, 2016 Utility Commission Work Session
Ayes: 3.
Nays: 0. Absent: 0. Motion carried.
OLD BUSINESS
None
6. NEW BUSINESS
6.a. Hawkins Inc. Sewer Metering
The sewer meter was installed and calibrated in early September and everything is in good working order.
Based on the flow through the meter to-date, it is estimated that Hawkins, Inc. will save approximately
$20,000 in sewer charges after the first full year of operation. The City will lose less than 1% revenue from
the utility fund due to this change. Overall, the meter is doing exactly what Hawkins hoped it would be
doing.
Due to these successful findings, the concern of other large industrial users doing the same as Hawkins once
was came up. Flint Hills has two connections to our main sewer and they use approximately 41 million
gallons a year which they are paying for sewer and water. The question is how much are they actually
dumping into our system? Watson along with Dick Howe (Utility Lead) went to Flint Hills to observe the
man holes and evaluate how much is leaving the system and it appeared to be a reasonable amount. With
that said, because it doesn’t appear a lot of their private water is going into our system, the city will leave it
to Flint Hills to reach out to the city if they’d like to proceed as Hawkins did as Flint Hills appears to be
aware of their usage and where their water is going.
6.b. MCES Water Rebate Update
Fasbender provided an informational overview about the water efficiency grant received from the
Metropolitan Council. The City is using these funds to issue rebates to residential water customers for the
purchase and installation of WaterSense low-flow toilets, EnergyStar washing machines, and WaterSense
irrigation controllers.
Overall, the program has been the most successful during Quarter 3 due mostly to fliers being issued with
resident’s utility bills and fliers handed out during Leprechaun Days. The city contributes 25% to each
rebate.
The initial grant amount was $9,000. The remaining balance as of October 11, 2016 is $3,220.44. Once the
grant funds are depleted, the City may consider continuing the program if internal funding is available.
6.c. Keegan Lake Feasibility Study Update
Keegan Lake is part of our Storm Water Management Plan. The plan determined by WSB, identifies18
projects as high priority and the city anticipates implementing at least some of the items within ten years.
Keegan Lake was determined to be a high priority out of those 18. A feasibility study was performed in 2009
to see if storm water improvements could be included in the Bonaire Path Improvement project. The
improvements were shown to be feasible, but an easement was required by the landowner which they were
not willing to provide. The Bonaire Path Improvement project was then constructed without including
Keegan Lake Draining improvements.
A new property owner now owns the property where the easement was required and has complained about
the water elevations in pond 1521. The pond does not include an outlet. Per the plan, this pond along with
two others would connect into Keegan Lake. WSB has submitted a proposal to do the feasibility study for
this. Morast would like to add to the study to see if we can make these pond connections to the south across
Bonaire potentially eliminating several parts of this project. Currently, this is an estimated seven to eight
hundred thousand dollar project. The question is do we need the entire current plan to move forward? The
Storm Water Management Plan will be updated within the next 18 months as part of a comprehensive plan.
We need to determine what the return on investment for this project is and evaluate how much we need to
do to move forward.
7. PRESIDENT’S REPORT
None
8. EXECUTIVE DIRECTOR’S REPORT
8.a. City Projects Update
Well 16 - Well complete, design is underway for well house. Construction is scheduled for 2017.
Danbury- Substantially complete
Horseshoe Lake Lift Station - Complete, been pumped down and working very well.
SRTS - finishing up currently. There were a couple issues which have now been resolved.
Parking lot maintenance – Rollover to into combined projects for next year.
Updates for irrigation systems are nearly complete. We will see the full effect of it next year.
8.b. 2016 Well Pumping Report
The numbers are lower in September and a special note that Well 12 is off-line.