HomeMy WebLinkAbout2.a. Fire Station No. 2AGENDA ITEM: Fire Station #2
AGENDA SECTION:
PREPARED BY: Dawn Weitzel, Assistant City
Administrator
AGENDA NO.
ATTACHMENTS: None
APPROVED BY
RECOMMENDED ACTION: Discussion
4 ROSEMOUNT
CITY COUNCIL
Special City Council Work Session: October 4, 2005
EXECUTIVE SUMMARY
ISSUE
The bid opening for the Fire Station #2 project was held on September 29, 2005. Todd Christopherson
from MOON and architect Mark Vetter will be present to discuss the results of the bid opening and
opuons Council may want to consider as the City goes forth in construction of this project.
AGENDA ITEM: Fire Station #2
AGENDA SECTION:
Discussion
PREPARED BY: Jamie Verbrugge, City Administrator
AGENDA NO.
ATTACHMENTS: Amortization schedule for financing
option #4
APPROVED BY:
RECOMMENDED ACTION: Give staff direction on how to proceed with the Fire Station #2
project
4 ROSEMOUNT
CITY COUNCIL
City Council Special Work Session. October 4, 2005
SUPPLEMENTAL
EXECUTIVE SUMMARY
BACKGROUND
Bid results for Fire Station #2 came m approximately $350,000 over the estimated project cost. Staff is
presenting options for Council consideration on how to proceed with the project.
ISSUE
In order to help Council better understand the issues surrounding the higher than expected bid results of
the Fire Station #2 construction project, staff has requested that the construction manager, AMCON, and
architect, Mark Vetter, be present for the discussion.
AMCON will provide an overview of the project cost estimation process as well as walk Council through
the process used to solicit bidder interest. AMCON will also overview some of the bidding climate
conditions that possibly contributed to the resulting overage in project costs. The items that appear to
have contributed to the bid results include• a lack of bidder interest on a number of the project
components; market volatility m the price of steel; and unforeseen issues related to the cost of masonry.
In terms of evaluatmg options for proceeding with the project, staff provides the following options for
consideration:
Option #1 Reject Bids /Readvertise in Early 2006
the decision to reject all bids and re -bid the project at a later date, say February 2006, is a calculated risk.
Among the issues that factor into this calculation are whether the bidding climate will improve
substantially in several months where more contractors looking for projects will result in more competitive
bids for project elements; whether fluctuations m the price of steel are temporary or may continue to
increase as a result of market demand (e.g., the Katrina effect on building projects nationwide); and,
whether potential inflationary increases in materials will negate the potential savings m a more competitive
bidding environment.
There are some savings to be realized by delaying the project due to costs related to winter construction.
These costs are estimated to be anywhere between $40,000- 80,000 Winter construction costs are not
specifically itemized within the bidding documents but are reflected in contractor pricmg based on their
estimation of cover and heating costs (masonry and concrete work).
Option #2 Alter the Project Scope /Design
Costs for the project may be reduced by scaling down the building footprint or reducing the aesthetics of
the design. It is uncertain how much cost savings can be achieved through redesign, as there will be
offsetting costs incurred for the architectural changes. Much of the space that is ancillary to the
equipment bays (meeting rooms and offices) has already been reduced during the original design process.
Additional reduction of footprint would hkely be seen in eliminating one of the bays (from three to two).
Option #3 Absorbing Cost Overage through Use of Encumbered Funds
The City has encumbered funds of $590,000 for building improvements The prelmunary 2006 budget
included a recommendation by the City Administrator to transfer approximately $40,000 to estabhsh a
repair and replacement fund for the St. Joseph property, which would leave $550,000 m the encumbered
account.
The original Fire Station #2 project included a contingency fund of approximately $210,000. After
reviewing the bid results, staff and consultants are comfortable maintaining a contingency of
approximately $100,000 If that $110,000 of contingency were applied to the $350,000 cost overage, it
would reduce the remaining gap to approximately $240,000 Utili7mg the encumbered funds for building
improvements to cover that gap would leave approximately $310,000 m that fund for future building
projects. This would allow the project to continue forward, albeit at a higher cost than originally
anticipated.
Option #4 Internally Borrow Funds to Cover the Gap
Using the same methodology in Option #3 for reordering the project contingency, staff prepared a
financing sheet showing absorption of the $240,000 overage In this scenario, funds would be borrowed
from CORE, funds and repaid over a 20 -year term paying 5% interest. Interloan funds have been used
previously to finance the Pubhc Works Facility expansion and more recently to make funds available for
acquisition of property m the downtown area The downside of this approach is there is no security or
obligation on the part of future councils to repay the borrowed funds. These obligations could be wiped
off the books to the detriment of the CORE funds.
Other Items
One other issue that needs to be resolved has to do with landscaping and grading between the west side of
the budding and the property line. Options to correct the grading issue range from $5,000 to maintain the
designed grade with cover vegetation, up to $50,000 for physical improvements including a retaining wall.
This cost would need to be factored into the overage absorbed or by further reducing the contingency.
It is also possible to defer some project costs for interior equipment and furnishings (e.g., blinds, hoist,
and audio visual equipment) until later in the process. These items came in higher than estimated and
should be able to be purchased at lesser cost.
SUMMARY
Council has a difficult decision. Staff recommends that Option #3 be pursued to keep the project on
track and to maintain the quality design of the facility. However, if Council determines that the increased
project cost is unacceptable for reasons of pubhc pohcy or public perception, then consideration should be
given to the risk equation of delaying the project.
2
Dated 12101/2005 i Delivered 12/01/2005
Sources Of Funds
Par Amount of Bonds
Total Sources
Uses Of Funds
Deposit to Project Construction Fund
Total Uses
are ffihw, -20 Ymr A .VNGLEPURM0SE !0/4/2005 10712 AM
spr'..n steel
$240,000
City of Rosemount, Minnesota
Fire Station 20 Years Amortization
Sources Uses
$240,000 00
$240,000 00
240,000 00
$240,000 00
02/01/2006 16,500 00
02/01/2007 7,300 00
02/01/2008 7,700 00
02/01/2009 8,1000D
02/01/2010 8,50000
02/01/2011 8,900 00
02/01/2012 9,300 00
02/01/2013 9,80000
02/01/2014 10,300 00
02/01/2015 10,800 00
02/01/2016 11,400 00
02/01/2017 11,900 00
02/01/2018 12,500 00
02/01/2019 13,100 00
02/01/2020 13,800 00
02/01/2021 14,500 00
02/01/2022 15,200 00
02/01/2023 16,000 00
02/01/2024 16,800 00
02/01/2025 17,600 00
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5 000%
5.000%
5.000%
5 000%
5 000%
5 000%
5.000%
5.000%
2,000 00
11,175 00
10,810 00
10,425 00
10,020 00
9,595 00
9,150 00
8,685 00
8,195 00
7,680 00
7,140 00
6,570 00
5,975 00
5,350 OD
4,695 OD
4,005 0D
3,280 00
2,520 OD
1,720 00
880 OD
18,500 00
18,475 00
18,510 00
18,525 00
18,520 00
18,495 00
18,450 00
18,485 00
18,495 00
18,480 00
18,540 00
18,470 00
18,475 00
18,450 DO
18,495 00
18,505 00
18 480 00
18 520 00
18,520 00
18,480 00
Total $240,000 DO $129,870 00 $369 870 00
Date
Yield Statistics
Bond Year Dollars
Average Life
Average Coupon
Net Interest Cost (NIC)
True Interest Cost (TIC)
Bond Yield for Arbitrage Purposes
All Inclusive Cost (AIC)
IRS Form 8038
Net Interest Cost
Weighted Average Maturity
))3 fvhon -20fla 4 1 s Pf4'OVE 10/4/_/00 10 32,IM
$240,000
City of Rosemount, Minnesota
Fire Station 20 Years Amortization
Debt Service Schedule
Principal Coupon Interest Total Pi-I
$2,597 40
10 823 Years
5 0000000%
5 0000000%
5 0008762%
5 0008762%
5 0008762%
5 0000000%
10.823 Years
CONTRACT
C -01
C -02
C -03
C -04
C -05
C -06
C -07
C -08
C -09
C -10
C -11
C -12
C -13
C -14
C -15
C -16
C -17
C -18
C -19
C -20
C -21
C -22
C -23
C -24
C -25
C -26
C -27
C -28
C -29
C -30
C -31
C -32
C -33
C -34
Extra
ALAIVICOI'J
DESIGN /BUILD I CONSTRUCTION MANAGEMENT I GENERAL CONTRACTING
ROSEMOUNT FIRE STATION #2
ROSEMOUNT, MN
BIDS VS. BUDGET
DESCRIPTION BUDGET
Excavation 120,960
Site Utilities comb. w /C -01
AC Paving 64,350
Landscaping 51,350
Exterior Concrete 39,640
Concrete 119,190
Masonry 366,669
Steel Fabrication 153,034
Steel Erection 36,320
Precast Concrete 11,040
Carpentry 18,940
Drywall 60,620
Roofing 115,935
Caulking 4,000
Specialties 13,750
HM, Doors, Frames 30,250
Glass Glazing 50,481
Specialty Doors 26,394
Plumbing 247,093
HVAC /Controls comb. w /C -19
Fire Protection 30,000
Electrical 287,896
Tiling 30,360
Flooring 15,146
Painting Coatings 36,225
Acoustical Ceilings 9,625
Lockers 13,260
Signage 8,000
Flag Pole 4,000
Architectural Woodwork 41,020
Window Treatments 2,250
Metal Panels 14,520
Audio Visual Systems 3,500
Electrical Chain Hoist
Spray Insulation
TOTAL 2,025,818
LOW BID
110,969
comb w /C -01
70,000
57,483
43,900
106,500
515,900
213,200
64,800
8,789
42,380
57,969
176,300
1,834
18,932
34,800
76,700
26,394
214,000
comb w /C -19
35,400
281,000
48,600
19,320
27,109
12,250
12,300
4,000
4,000
46,025
25,345
49,990
8,590
6,200
9,800
2,430,779
DELTA
9,991
(5,650)
(6,133)
(4,260)
12,690
(149,231)
(60,166)
(28,480)
2,251
(23,440)
2,651
(60,365)
2,166
(5,182)
(4,550)
(26,219)
33,093
(5,400)
6,896
(18,240)
(4,174)
9,116
(2,625)
960
4,000
(5,005)
(23,095)
(35,470)
(5,090)
(6,200)
(9,800)
(404,961)
10 4 2005 1715 Yankee Doodle Road, Suite 200 1 Eagan, Minnesota 55121 -1616 1 Tel 651 379 9090 I Fax: 651.379.9091
Email custsery @amconconstruction.com Webs to www amconconstruction com
s -1 Bond Referendum (Net Proceeds)
S -2 I nterest Income
S-4 Transfer of Funds (CIP)
10/4/2005
Funding Source
AAicoN
DESIGN /BUILD 1 CONSTRUCTION MANAGEMENT 1 GENERAL CONTRACTING
ROSEMOUNT FIRE STATION #2
ROSEMOUNT, MN
PROJECT BUDGET
Total
2,500,000
250,000
2,750,000 2,750,000
Code Expenditures
Base Design Current
Land Acquisition Development
1 Land Cost
2
Project Development Costs
3 A/E Services Allowance (incl Civil, Struct M /E) 154,675
4 A/E Reimbursed Expenses 15,000
5 Geotechnical Services 2,600
6 Construction Testing 18,000
8 SAC/WAC fees 5,800
9 Bid Advertisement and Printing 25,000
Subtotal
Subtotal 221,075 221,075
Construction Cost
10 Construction Management Fee 77,338 $77,338
11 Survey Staking $0
12 Construction Hard Costs 2,209,646 $2,614,607
13 Voice, Video, Data Equip Connectivity (project costs) 13,000 $13,000
14 FFE (project and design costs) 17,941 $17,941
15 Contingency 211,000 $211,000
Subtotal 2,528,925 2,933,886
Total 2,750,000 3,154,961
Fund Balance 0 (404,961)
1715 Yankee Doodle Road, Suite 200 1 Eagan, Minnesota 55121 -1616 1 Tel 651.379 9090 1 Fax 651 379 9091
Email custsery @amconconstruction com 1 Website www amconconstruction com