HomeMy WebLinkAbout6.g. Approve Agreement with Xcel Energy for Utility Relocation Design - Old County Rd 38, City Project 387AGENDA ITEM: Approve Agreement with Xcel Energy for
Utility Relocation Design -Old County
Road 38, City Project #387
AGENDA SECTION:
Consent
PREPARED BY: Andrew J. Brotzler, P.E., City Engine- II
i
�AGEND
ATTACHMENTS: Preliminary Engineering Agreements O
v
APPROVED BY: LW
RECOMMENDED ACTION: Motion to Approve an Agreement with Xcel Energy for the
Utility Relocation Design to Accommodate Improvements on Old County Road 38 and
Authorize the Necessary Signatures.
4 ROSEMOUNT
ISSUE:
BACKGROUND:
SUMMARY:
CITY COUNCIL
City Council Meeting: March 21, 2006
EXECUTIVE SUMMARY
City staff requests Council authorization for staff to execute two agreements with Xcel Energy for
preliminary engineering services associated with relocation of transmission power poles along the Old
County Road 38 project corridor.
Several Xcel Energy transmission line poles along the Old County Road 38 corridor need to be relocated
to accommodate roadway widening. Engineering design, as well as construction of these relocations is
performed in -house by Xcel Energy. Because the current pole locations now exist within utility easements
previously secured by Xcel, compensation to Xcel Energy by the City for both design services and
construction related to the relocations are required. The agreements in question provide for Xcel's
preliminary engineering services (including, but not limited to engineering, right of way, surveying, and
drafting) and other associated activities that must be performed in order to arrive at a detailed cost
estimate for the relocation project.
Two Preliminary Engineering Agreements, attached here, have been drafted by Xcel Energy, one for Old
County Road NSP Line 0703, and one for Old County Road 38 NSP Line 0742. Both agreements have
been reviewed by the City's Attorney, and a minor revision has been included in paragraph 5 as a result.
This revision is acceptable to Xcel Energy and has been reviewed and initialed by Xcel Energy
representatives.
Xcel Energy's preliminary engineering fees are based on 9% of a rough estimation of project construction
costs and are as follows: $22,158 for NSP Line 0703 and $50,580 for NSP Line 0742. Payment of these
fees are required before design services can be started.
Staff recommends Council authorization of staff execution of the attached two Preliminary Engineering
Agreements with Xcel Energy and payment to begin design.
G.I ENGPROJ13871XcelEnergyAgreementCC3- 21- 06.doc
0 Xcel Energy
January 11, 2006
Andy Brotzler
City of Rosemount
2875 145 Street West
Rosemount, MN 55068 -4997
RE Transmission Line Relocation
NSP Line 0703
PRELIMINARY ENGINEERING AGREEMENT
414 Nicollet Mall
Minneapolis, Minnesota 55401 -1993
NSP has received a request from your office that NSP investigate replacing structures on Line 0703
in Rosemount, MN.
As with any construction project, preliminary engineering (including, but not limited to
engineering, right of way, surveying and drafting) and other associated activities must be
performed in order to arrive at a detailed cost estimate for the whole project. It is NSP's policy
that before these activities begin, the party requesting the detailed cost estimate must agree to pay
the costs of these preliminary activities; in addition, NSP requires advance payment of 80% of the
rough estimate of these preliminary costs. For this project, a rough estimate of the preliminary
engineering costs is 522,158, so NSP will require a deposit of 517,726 advance and your
agreement to pay, following completion of the preliminary activities, the balance of costs actually
incurred by NSP If you wish NSP to proceed with the preliminary activities, please execute this
letter as provided below and return it to the undersigned with a check in the amount of 517,726
payable to Northern States Power Company.
Upon receipt of the above, NSP will prepare detailed plans and cost estimates for the entire
relocation project, plus any costs associated with the acquisition of new right of way (including
costs of easements) The detailed plans and estimates will be forwarded to you for your review and
if you desire to proceed with construction, you should notify NSP in writing NSP will then prepare
a Relocation Agreement covering the terms of such relocation, including, but not limited to:
City of Rosemount will pay the actual costs of such relocation Such actual costs shall
include the wages (including all fringe benefits) of all employees of NSP devoting tune
toward design, engineering, construction, acquisition of right of way, administration or any
other activity associated with said relocation project; costs of any necessary right of way;
overhead costs associated with surveying, construction and other operations in the field
1/11/2006
Page 2
(including, but not limited to charges for mileage, equipment rental or cost, etc); and
material costs for all Items associated with said relocation
2. Upon execution of the Relocation Agreement, City of Rosemount will pay NSP 80% of the
estimated cost of the relocation; the estimated cost will be the cost estimate determined
from the preliminary activities discussed earlier in this letter.
3. Upon completion of the relocation project, City of Rosemount will pay NSP any excess of
the actual costs over the 80% deposit received by NSP, any overpayment will be refunded
by NSP.
4. NSP will reconstruct its transmission lines as quickly as is possible, subject to allowances
of extra time for strikes or unforeseen delays in delivery of necessary materials, or other
unforeseen contingencies, or because of NSP's need to transfer electrical energy without
interruption.
5. City of Rosemount will indemnify and hold NSP harmless from and against all claims,
damages, liabilities, costs and expenses (including attorney's fees) arising in connection
with the relocation project, except such claims, liabilities, costs and expenses (including
attorpe s fees) c ?f
sed by the egligence No th rn States p Company. 001.1" kalti,�
stall �y J ck alr�c r o R e G ep lta. l a V:4:01 yet 4
After execution of t e Relocation Agreement, actual field construction will begin as soon as
possible, but not until the necessary right of way has been obtained. In the event such right of way
cannot be obtained, the relocation project will terminate and City of Rosemount will pay NSP for
all costs incurred up until such termination.
Alternatively, if after reviewing the detailed cost estimate you decide against proceeding with
construction, the $17,726 deposit made with the return of this letter will be applied towards the
costs of the preliminary activities; any deficiency shall be paid by you to NSP and any excess will
be refunded by NSP.
The minimum schedule duration for planning, engineering, material procurement and construction
for this project work is 9 months. Spec fc outage restraints and scope of project may require
additional time and planning.
If the above terms are acceptable to you, please signify your assent to them by executing the
original copy of this letter and returning it to the undersigned along with a check for $17,726
10/10/05 AU Documentl
1/11/2006
Page 3
A
Scott Johnson
Highway and Railroad Liaison
414 Ntcollet Mall
Minneapolis, MN 55401
(612)330 -6078
cc: Mike Hawkinson
City of Rosemount hereby requests NSP to begin prekmznary engineering and related activities for
the above relocation project and agrees to the terms set out above relating to such activities.
10/10/05 AU Documentl
Dated
By
Its
I Xcel Energy°
A Scoping Estimate" is provided by Xcel Energy for the convenience of the requesting entity
(Requester) It is produced before engineering design has been completed. Xcel Energy will
make every effort to produce a representative estimate that will incorporate as many project-
specific factors as possible However, a Scoping Estimate is frequently based on typical
conditions encountered on past construction projects and utilizes historical cost data from other
Xcel Energy projects which may or may not be directly comparable
Requester Name
Address
Andy Brotzler
City of Rosemont
2875 145 Street West
Rosemont, MN 55068 -4997
Scoping Estimate
T.R.# 830A
Phone (651)423 -4411
FAX (651)322 -2694
A Requester should not rely solely on a Scoping Estimate and Xcel Energy will not proceed to
construction based on this estimate. A Scoping Estimate will only give a broad -based estimate
of the possible costs that may be incurred during a potential construction project. If a Requester
wants a more definitive estimate of the cost of a project, an "Engineering Estimate" should be
requested.
Requester agrees to pay Xcel Energy $17,726 for this Preliminary Engineering
Agreement.
Requester Initial
Project Information
Date
Name County Rd hwy 38 State Aid Project SAP208- 105 -01
Location Rosemont MN between Robert Trail South to Akron Avenue
Scope A section of 69KV line 0703 kegan Lake to west to open line is impacted
by the City of Rosemont's hwy 38 work. The transmission line will
remain on the south side of hwy 38 until it crosses to north into Kegan
Lake Substation. Almost every structure between Robert Trail South and
the Kegan Lake Substation will need to be replaced due to road grading
and moving the Xcel Energy distribution line from north side of road to
this section of line as underbuild.
Project Assumptions:
Preliminary designs are based on plan drawing received by Xcel Energy. Any changes to these
plans must be communicated to Xcel Energy in a timely manner as the design options could
change
By signing below Requester agrees that this document sets forth the correct Project
Information and Project Assumptions.
Estimate of Costs by Xcel Energy
$246,200
Permanent Installation:
Transfer 5,100 ft of existing
Conductor and 1,700 ft of
Shield wire to new structures
1) Detailed Engineering including soil borings and survey will not
start until the Preliminary Engineering Agreement is signed and
returned with appropriate fee.
2) Distribution circuit will be removed from north side of road and
designed for on all new Transmission line structures.
Distribution impacts to the structures will be considered as
betterment and not charged to the City of Rosemont.
3) Every effort will be made to use wood pole design but if this is
note feasible steel mono poles on drilled pier foundations may
be required and their lead -time will add almost 6 months to the
process. NOTE: two key areas that will impact the use of wood
poles is the assumption that the guy stub pole on the north side
of the road for structure #1031 can be reused or replaced on the
north side of the road again with some new anchoring And, the
assumption that the City contractor can do grade lowering
behind structure #1034 so new anchors can be installed at
rough grade.
Install four (4) tangent wood
Poles [strs 1027,1029, 1032,
and 1033] $105,000 minus
Distribution betterment
$1000 per pole
Install three (3) bisector guyed
Wood Poles and anchors [strs
1028,1031 and 1034]
$52,000 minus distribution
betterment $1000 per pole
Install two (2) direct embed steel
Non guyed LD Poles for light
Angles [strs 1028, 1030]. $62,000
Minus distribution betterment
$1000 per pole
16,200
80,000
75,000
$60,000
Removal of seven existing
Wood pole structures 10,000
Contingencies 5,000
Total Indicative Estimate $246,200
Estimated typical engineering Agreement based
On 9% of Estimated engineering costs $22,158
Preliminary Engineering Agreement based on 80% of
Estimated engineering costs $17,726
An Scoping Estimate must be signed by both parties and dated. Each signature below is made
contingent upon this document being signed by the other party.
Requester Xcel Energy
Name (Printed)
Signature Date Signatur Date
Requester Xcel Energy
Name (Printed)
1 Ants.
Bruce LaMar
Name(Pnnted)
1 IC -6 6
n Jandro
e(Printed)
AAA!"
1
Signature Date Si. ature Date
Xcel Energy-
February 16, 2006
Andy Brotzler
City of Rosemount
2875 145 Street West
Rosemount, JI4N 55068 -4997
RE Transmission Line Relocation
NSP Lzne 0742
PRELIMINARY ENGINEERING AGREEMENT
414 Nicollet Mall
Minneapolis, Minnesota 55401 -1993
NSP has received a request from your office that NSP investigate replacing structures on Line 0742
in Rosemount, MN.
As with any construction project, preliminary engineering (including, but not limited to
engineering, right of way, surveying and drafting) and other associated activities must be
performed in order to arrive at a detailed cost estimate for the whole project. It is NSP's policy
that before these activities begin, the party requesting the detailed cost estimate must agree to pay
the costs of these preliminary activities, in addition, NSP requires advance payment of 100% of the
rough estimate of these preliminary costs. For this project, a rough estimate of the preliminary
engineering costs is $50.580, so NSP will require a deposit of $50,580 advance and your
agreement to pay, following completion of the preliminary activities, the balance of costs actually
incurred by NSP. If you wish NSP to proceed with the preliminary activities, please execute this
letter as provided below and return it to the undersigned with a check in Me amount of $50,580
payable to Northern States Power Company.
Upon receipt of the above, NSP will prepare detailed plans and cost estimates for Me entire
relocation project, plus any costs associated with the acquisition of new right of way (including
costs of easements). The detailed plans and estimates will be forwarded to you for your review and
f you desire to proceed with construction, you should not fy NSP in writing. NSP will then prepare
a Relocation Agreement covering the terms of such relocation, including, but not limited to.
1. City of Rosemount will pay the actual costs of such relocation. Such actual costs shall
include the wages (including all fringe benefits) of all employees of NSP devoting time
toward design, engineering, construction, acquisition of right of way, administration or any
other activity associated with said relocation project, costs of any necessary right of way,
overhead costs associated with surveying, construction and other operations in the field
2/16/2006
Page 2
(including, but not limited to charges for mileage, equipment rental or cost, etc.); and
material costs for all items associated with said relocation.
2. Upon execution of the Relocation Agreement, City of Rosemount will pay NSP 100% of the
estimated cost of the relocation; the estimated cost will be the cost estimate determined
from the preliminary activities discussed earlier in this letter.
3. Upon completion of the relocation project, City of Rosemount will pay NSP any excess of
the actual costs over the 100% deposit received by NSP; any overpayment will be refunded
by NSP.
4. NSP will reconstruct its transmission lines as quickly as is possible, subject to allowances
of extra time for strikes or unforeseen delays in delivery of necessary materials, or other
unforeseen contingencies, or because of NSP's need to transfer electrical energy without
interruption.
5. City of Rosemount will indemnify and hold NSP harmless from and against all claims,
damages, liabilities, costs and expenses (including attorney's fees) arising in connection
with the relocation project; except such claims, habilitzes, costs and expenses (including
attorney's fees) caused by the negligence ofNorthern States Power Company IJ .k.: h
SL..,, It 4 e. �err�d ��.xI6 ,ht C;� 4 to I:.��+.t:� 4 A. tab:� L
14,g",44 Ass,. 1-6.L CLwPke 44G.
After execution of the Relocation Agreement, actual field construction will begin as soon as
possible, but not until the necessary right of way has been obtained In the event such right of way
cannot be obtained, the relocation project will terminate and City of Rosemount will pay NSP for
all costs incurred up until such termination.
Alternatively, if after reviewing the detailed cost estimate you decide against proceeding with
construction, the $50,580 deposit made with the return of this letter will be applied towards the
costs of the preliminary activities, any deficiency shall be paid by you to NSP and any excess will
be refunded by NSP.
The minimum schedule duration for planning, engineering, material procurement and construction
for this project work is 9 months. Specific outage restraints and scope of project may require
additional tune and planning.
If the above terms are acceptable to you, please signify your assent to them by executing the
original copy of this letter and returning it to the undersigned along with a check for $50,580
2/16/06 AU H:\ WORD \Hwyletters \PREENGRagreemen.DOC
2/16/2006
Page 3
Scott ,rohnson
Highway and Railroad Liaison
414 Nicollet Mall
Minneapolis, MN 55401
(612)330 -6078
Attachment
cc: Mike Hawkinson
City of Rosemount hereby requests NSP to begin preliminary engineering and related activities for
the above relocation project and agrees to the terms set out above relating to such activities.
Dated
By
Its
2/16/06 AU H-\ WORD \Hwyletters \PREENGRagreemen.DOC
0 Xcel Energy
Requester Name
Address
Requester Initial
Project Information:
Andy Brotzler
City of Rosemont
2875 145` Street West
Rosemont, MN 55068 -4997
Scoping Estimate
T.R.# 830B
A "Scoping Estimate" is provided by Xcel Energy for the convenience of the requesting entity
(Requester). It is produced before engineering design has been completed. Xcel Energy will
make every effort to produce a representative estimate that will incorporate as many project-
specific factors as possible. However, a Scoping Estimate is frequently based on typical
conditions encountered on past construction projects and utilizes historical cost data from other
Xcel Energy projects which may or may not be directly comparable
Date
1 of 3
Phone (651) 423-4411
FAX (651) 322 -2694
A Requester should not rely solely on a Scoping Estimate and Xcel Energy will not proceed to
construction based on this estimate A Scoping Estimate will only give a broad -based estimate
of the possible costs that may be incurred during a potential construction project. If a Requester
wants a more definitive estimate of the cost of a project, an "Engineering Estimate" should be
requested
Requester agrees to pay Xcel Energy $50,580 for this Preliminary Engineering
Agreement.
Name County Rd Hwy 38 State Aid Project SAP208- 105 -01
Location Rosemont MN between Robert Trail South to Akron Avenue
Scope A section of 69KV line 0742 Kegan Lake to Wescot line is impacted by the
City of Rosemont's hwy 38 work. The transmission line will remain on
the adjacent to hwy 38 where it is located now. Between the Kegan Lake
Substation and Akron Avenue Xcel Energy will need to lower three
structures, bandage nine structures, and replace eleven structures with
ten new ones.
Proj As
1) Detailed Engineering work, including soil borings and surveying
will not start until the Preliminary Engineering Agreement is
signed and returned with the appropriate fee.
2) The distribution under build will remain on the structures it is
presently on in the new design
3) Every effort will be made to use a wood pole design except for
the section of line near the pond. In this area steel poles on
drilled pier foundations may be used if soil conditions are poor.
4) It will be necessary to Reconductor this portion of the line due to
the age and currant condition of the wire Our currant procedure
with this size line is to Reconductor with the smallest standard
wire size in only the necessary location of the project
5) Existing shield wire to be transferred to new structures.
Preliminary designs are based on plan drawing received by Xcel Energy Any changes to these
plans must be communicated to Xcel Energy in a timely manner as the design options could
change
By signing below Requester agrees that this document sets forth the correct Project
Information and Project Assumptions.
Estimate of Costs by Xcel Energy
Permanent Installation:
$562,000
Transfer 7,500 ft of existing
Shield wire to new structures 22,500
String 22,500 feet of new
conductor 40,500
Install two (2) steel Poles $140,000
Install two (2) drilled pier
Foundations 50,000
Install eight (8) tangent wood
poles [Str's 1051, 1047, 1036,
1039, 1035, 1033, 1032 and
1031]
Install two (2) direct embed
unguyed light angle steel poles
[str #1037 1038]
Install two (2) bisector guyed wood
poles and anchors [strs 1053 and
1052].
2 of 3
168,000
62,000
52,000
Key Activity
Lead -time (mo.)
Permitting
Engineering Design /Mtrl. Req. /Purch /Deliv
10 mos
Structural Construction
1 mo
Line Construction
1 mo
Total Lead -time
12 mo.
Requester
Removal of eleven (11) existing
Wood pole structures 22,000
Contingencies 5 000
Total Indicative Estimate $562,000
Estimated typical engineering Agreement based
On 9 °l0 of Estimated project costs $50,580
Preliminary Engineering Agreement based on 100% of
Estimated project costs $50,580
Preliminary Schedule: Construction manpower, engineering, and outage availabilities may
affect the project lead -times indicated below:
A Scoping Estimate must be signed by both parties and dated Each signature below is made
contingent upon this document being signed by the other party.
Bruce LaMar
Name (Printed) Name(Printed)
ail
Signature Date Signe ure
Requester Xcel Energy
Name (Printed)
Signature Date
3 of 3
Xcel Energy
Anthony ..ndro
Name(' i nted)
Principal Engineer
Title
Z t'ti -D.6
Date
Manager
Title