HomeMy WebLinkAbout6.l. Payment #9 & Final - Glendalough 4th Addition Street and Utility Improvements City Project #386AGENDA ITEM: Payment #9 Final Glendalough 4th
Addition Street and Utility Improvements,
City Project #386
AGENDA SECTION:
Consent
PREPARED BY: Andrew J Brotzler, P.E., City Engineer
AGENDA NO. 61
ATTACHMENTS: Payment #9 Final
APPROVED BY:
1 RECOMMENDED ACTION: Motion to Approve Payment #9 and Final to Three Ri ers
Construction for Glendalough 4 Addition Street and Utility Improvements, City Pr ject
#386 and accept for perpetual maintenance.
4 ROSEMOUNT
CITY COUNCIL
City Council Meeting: August 2, 2006
EXECUTIVE SUMMARY
BACKGROUND:
This item is on the agenda to request Payment #9 and final to Three Rivers Construction for Glendalough
4t Addition Street and Utihty Improvements, City Project #386. This project included the construction of
streets and utilities to serve 19 lots within the Glendalough 4th Addition of the Evermoor development
The project area is located east of Evermoor Parkway and north of Connemara Trail.
The final construction amount of $225,320.79 is 3.7 °/o above the contract amount of $217,246.76. All
costs associated with the project have been paid by the Developer, Lundgren Brothers Construction.
SUMMARY:
Staff recommends that Council approve Payment #9 and final for the project and accept the project for
perpetual maintenance subject to the following conditions.
1 Satisfactory showing that the contractor has comphed with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or sausfactorily secured
3. Consent of Surety to Final Payment certification from the contractor's surety.
4 Two -year maintenance bond.
G \ENGPROJ 386 \Pavmem #9 &FinalCC8 -2 -06 doc
WSB
�7B
Assoc Infrastructure 1 Engineering 1 Planning 1 Construction
-July 26, 2006
Honorable Mayor and City Council
City of Rosemount
2875 145 Street West
Rosemount, MN 55068
Attn: Cindy Domiden, City of Rosemount
Re: Construction Pay Voucher No 9 and Final
Glendalough 4 Addition
Street and Utility Construction and Appurtenant Work
City of Rosemount Project No 386
WSB Project No. 1556 -16
Dear Mayor and Council Members:
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel 753 -541 -4800
Fax 763 541 -1700
Please find enclosed the final Construction Pay Voucher No. 9 (Final) for the above referenced
project in the amount of $21,965.32. We recommend final payment subject to receipt of the
following items:
1. Satisfactory showing that the contractor has complied with the provisions of Minnesota
Statutes 290.92 requinng withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of
the contract have been fully paid or satisfactonly secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year maintenance bond.
Please make payment in this amount to Three Rivers Construction at your earliest convenience.
Sincerely,
WSB Associates, Inc.
Enclosures
cc: Andy Brotzler, City of Rosemount
Three Rivers Construction
tsf
Minneapolis 1 St, Cloud
Equal Opportunity Employer
6 ENGPROJO86ILTR PO 9FNL C(Y- AmmO]T606dx
Project Summa
1
Original Contract Amount
$217,246 76
2
Contract Changes Addition
$0 00
3
Contract Changes Deduction
$0 00
4
Revised Contract Amount
$217,246 76
5
Value Completed to Date
$225,320 79
6
Matenal on Hand
$0 00
7
Amount Earned
$225,320.79
8
Less Retainage
$0 00
9
Subtotal
$225,320 79
10
Less Amount Paid Previously
$203,355 47
11
Liquidated Damages
$0.00
12
AMOUNT DUE THIS PAY VOUCHERS NO 9 FINAL
$21,965.32
01556 -16 Pay Vouchers 9
A
WSB
Associates, inc.
Recommended for Approval by:
WSB Associates, Inc.
Approved by Contractor
Three ivers Constr 1. ion
ontrai Corri
Specifie
7/21/2005
ion Date:
Owner: City of Rosemount
2875 145th Street West
Rosemount, MN 55068 -4941
10/1/2005 to 2/1/2006
Three Rivers Construction
15001 Hudson Road
Lakeland, MN 55043
Pay Vouchers
RSMT Glendalough 4th Addition
Client Contract No.
Project No.: 01556 -16
Client Project No. 374
For Period:
Contractor:
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT
THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL
VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE
WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER
Construe o- Observer:
Approved by fawner
City of Rosemount
Date
Comment
Thursday, February 02,2006•
Date: 2/2/2006
Request No.: 9 FINAL
1 of 4
Item
No
Item
Description
Units
Unit Pnce
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
SCHEDULE A SURFACE IMPROVEMENTS
1
2021 501
MOBILIZATION
LUMP SUM
$4,81500
1
1
02
54,81500
2
2104 501
REMOVE CURB AND GUTTER
LIN FT
$5 00
60
88
0
$440 00
3
2104 505
REMOVE BITUMINOUS PAVEMENT
SO YD
55 00
30
185
0
$925 00
4
2104 513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
$3 00
84
119
0
5367 00
5
2105 507
SUBGRADE EXCAVATION
CU YD
$6 00
30
0
0
$0 00
6
2105 522
SELECT GRANULAR BORROW (CV)
CU YD
$9 35
2450
1711
674
$15,997 85
7
2105 525
TOPSOIL BORROW (CV)
CU YD
$15 00
20
0
0
$0 00
8
2112 501
SUBGRADE PREPARATION
ROAD STA
515000
962
962
0
$1,44300
9
2211 501
AGGREGATE BASE CLASS 5
TON
510 60
1330
1378
0
514,606 80
10
2350 501
TYPE LV 3 WEARING COURSE MIXTURE (C)
TON
$40 17
340
365 5
0
$14,682 14
11
2350 502
TYPE LV 3 NON WEARING COURSE MIXTURE (C)
TON
$39 66
340
363
0
$14,396 58
12
2357 502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
52 58
155
175
0
$451 50
13
2451 602
GRANULAR FOUNDATION AND /OR BEDDING
TON
51800
20
465
0
583700
14
2521 501
6" CONCRETE WALK
SQ FT
$3 25
4485
11857
1230
538,535 25
15
2531 501
CONCRETE CURB GUTTER, DESIGN MODIFIED S
LIN FT
$8 05
1900
1934
0
$15,568 70
16
2545 523
4" NON METALLIC CONDUIT
LIN FT
$7 00
140
180
0
$1,260 00
17
2563 601
TRAFFIC CONTROL
LUMP SUM
$772 50
1
1
0
$772 50
18
2564 531
SIGN PANELS TYPE C
SQ FT
536 05
6 25
6 25
0
$225 31
19
2564 602
FURNISH INSTALL SIGN PANEL TYPE D
EACH
$309 00
2
2
0
$618 00
20
2564 603
12" SOLID LINE WHITE -PAINT
LIN FT
$5 15
16
0
0
50 00
21
256460312"
SOLID LINE WHITE -EPDXY
LIN FT
$10 30
16
0
0
$000
22
2573 501
BALE CHECK
EACH
$10 30
40
0
0
$0 00
23
2573 502
SILT FENCE TYPE HEAVY DUTY
LIN FT
51 70
500
0
0
$0 00
24
2575 501
SEEDING
ACRE
$1,33900
15
0
0
5000
25
2575 505
SODDING TYPE LAWN
SQ YD
$3 40
2350
0
0
50 00
26
2575 523
EROSION CONTROL BLANKETS CATEGORY 3
SQ YD
51 24
1000
0
0
$0 00
Totals For Section SCHEDULE A SURFACE IMPROVEMENTS
$125,931 63
SCHEDULE B SANITARY SEWER IMPROVEMENTS
27
2503 602
CONNECT TO EXISTING SANITARY SEWER
EACH
5696 00
1
1
0
$696 00
28
25036028
"X4" PVC WYE
EACH
$45 00
17
17
0
576500
29
2503 603
SANITARY SEWER INSPECTION (TELEVISING)
LIN FT
5070
866
866
0
$60620
30
2503 603
4" PVC PIPE SEWER SDR 26
LIN FT
511 00
800
762
0
$8,382 00
31
2503 603
8" PVC PIPE SEWER SDR 35
LIN FT
$13 00
866
866
0
511,258 00
32
2506 516
CASTING ASSEMBLY
EACH
$426 00
6
6
0
52,55600
33
2506 603
CONST 48" DIA SAN SEWER MANHOLE
LIN FT
5162 00
73 8
74 03
0
$11,992 86
Totals For Section SCHEDULE B SANITARY SEWER IMPROVEMENTS
$36,25606
SCHEDULE C WATER MAIN IMPROVEMENTS
34
2104 523
SALVAGE HYDRANT VALVE
EACH
$190 00
1
1
0
$190 00
35
2504 602
HYDRANT
EACH
$1,658 00
1
1
0
$1,65800
36
2504 602
INSTALL HYDRANT AND VALVE
EACH
$438 00
1
1
0
5438 00
37
2504 602
1" CORPORATION STOP
EACH
52900
17
17
0
$49300
38
2504 602
6" GATE VALVE AND BOX
EACH
5590.00
1
1
0
$590 OD
39
2504 602
B" GATE VALVE AND BOX
EACH
$80500
2
2
0
$1,610 00
40
2504 602
1" CURB STOP BOX
EACH
574,00
17
17
0
$1,25800
41
2504 602
CONNECT TO EXISTING WATERMAIN (8")
EACH
565300
3
3
0
51,959 00
42
2504 603
1' TYPE K COPPER PIPE
LIN FT
512 00
750
749
0
58,988 00
43
2504 603
6" WATER MAIN-DUCT IRON CL 52
LIN FT
$27 00
20
15
0
S405 00
44
2504 603
8" WATER MAIN -DUCT IRON GL 52
LIN FT
524 00
908
915
0
$21,96000
45
2504 604
4" POLYSTYRENE INSULATION
SO YO
$17 00
22
0
0
5000
46
2504 608
DUCTILE IRON FITTINGS
POUND
$2 00
865
930
0
$1,860 00
01556 -16 Pay Vouchers 9
Project Material Status
Thursday, February 02, 2006
2 of 4
Item
No
Item
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
Totals For Section SCHEDULE C WATERMAIN IMPROVEMENTS
541,409 00
SCHEDULE D STORM SEWER IMPROVEMENTS
47
2503 541
15" RC PIPE SEWER DESIGN 3006 CLASS V
LIN FT
$23 00
529
537
0
$12,351 00
48
2503 602
CONNECT TO EXISTING STORM SEWER
EACH
$722 00
1
1
0
$722 00
49
2506 501
CONSTRUCT DRAINAGE STRUCTURE DESIGN 48 -4020
LIN FT
$166 00
18 1
18 85
0
S3 12910
50
2506 502
CONSTRUCT DRAINAGE STRUCTURE DESIGN G
EACH
$1,202 00
1
1
0
51,202 00
51
2506 502
CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 1
EACH
$815 00
2
2
0
$1 630 00
52
2506 516
CASTING ASSEMBLY
EACH
$538 00
5
5
0
$2,690 00
Totals For SCHEDULE D STORM SEWER IMPROVEMENTS
$21,72410
Project Totals
$225,320 79
01556 -16 Pay Vouchers 9
ass
Thursday, February 02, 2006-
3 of 4
No.
From Date
To Date
Payment
Total Payment
Retainage Per Payment
Total Retainage
Completed
1
8/5/2004
8/31/2004
$83,123 54
$83,123 54
$4,374 92
$4,374 92
$87,498 46
2
9/1/2004
9/30/2004
$64,526 42
$147,649.96
$3,396 13
$7,771 05
$155,421.01
3
10/1/2004
10/31/2004
$7,637.27
$155,287.23
$401 96
$8,173.01
$163,460.24
4
11/112004
11/30/2004
$3,477.00
$158,764.23
$183.00
$8,356 01
$167,120.24
5
12/1/2004
1/31/2005
$9,81516
$168,579 39
$51659
$8,872 60
$177,45199
6
2/1/2005
5/31/2005
$1,377.03
$169,956 42
$72 48
$8,945 08
$178,901.50
7
6/1/2005
6/30/2005
$19,205.92
$189,162 34
$1,010.83
$9,955 91
$199,118 25
8
7/1/2005
9/30/2005
$14,193 13
$203,355 47
$747 01
$10,702.92
$214,058 39
9 FINAL
10/1/2005
2/1/2006
$21,965 32
$225,320.79
($10,702 92)
$0.00
$225,320.79
Payment Totals
$225,320.79
$0 00
$225,320.79
No
Type
(Date
Description
Amount
Change Order Totals.
$0.00
131556 16 Pay Vouchers 9
Contract Chan es
Project Payment Status
Owner City of Rosemount
Client Project No.
Client Contract No.:
Project No.: 01556 -16
Contractor. Three Rivers Construction
Thursday, February 02, 2006
Project Summary
Material On Hand:
Total Payment to Date:
Total Retainage:
Total Amount Earned:
$0.00
$225,320.79
50.00
$225,320.79
Original Contract:
Contract Changes:
Revised Contract:
$217,246.76
$0.00
$217,246.76
4 of 4