Loading...
HomeMy WebLinkAbout6.k. Final Payment #5, Crosscroft 2nd Street and Utility Improvements, City Project #388AGENDA ITEM: Final Payment #5, Crosscroft 2n Street and Utility Improvements, City Project #388 AGENDA SECTION: Consent PREPARED BY: Andrew J. Brotzler, PE, City Engineer AGENDA NO. ATTACHMENTS: Payment Voucher, Map APPROVED BY: RECOMMENDED ACTION: Motion to Approve Payment #5 and Final for the Crosscroft 2nd Street and Utility Improvements, City Project #388, to Ryan Contracting and Accepting it for Perpetual Maintenance. 4 ROSEMOUNT CITY COUNCIL City Council Meeting November 7, 2006 BACKGROUND: SUMMARY: Packet page 124 of 177 EXECUTIVE SUMMARY This item is on the agenda to request Payment #5 and Final to Ryan Contracting for the Crosscroft 2 Addition, City Project #388 This project included the construction of streets, sanitary sewer, water main, storm sewer and sidewalks within the Crosscroft 2' Addition. The final construction amount of $219,304 25 is 3.2% above the contract amount of $212,423.00. Items contnbuung to the increase in the overall construction cost include greater quantities of subgrade excavation, concrete walk, and silt fence installation than ongtnally estimated necessary to complete the project All project costs are the responsibihty of the developer, D.R Horton Staff recommends that Council approve Payment #5 and final for the project and accept the project for perpetual maintenance subject to the following conditions 1. Satisfactorily showing that the contractor has complied with the provisions of Minnesota Statutes 290 92 requiring withholding state income tax. 2 Evidence in the form of an affidavit that all claims against the contractor by reasons of the contract have been fully paid or satisfactorily secured. 3. Consent of Surety to Final Payment certification from the contractor's surety. 4 Two -year maintenance bond. 1 \Engtneenng Cound November 7, 2006 \CP388 -Finai PaymentCCii -7 -06 doc WSB Assocwrrs, Inc Infrastructure 1 Engineering 1 Planning 1 Construction 701 Xenia Avenue South Suite 300 October 25, 2006 Minneapolis, MN 55416 Tel. 753- 541 -4800 Honorable Mayor and City Council Fax 763 -541 -1700 City of Rosemount 2875 145 Street West Rosemount, MN 55068 Attn: Cindy Dorniden, City of Rosemount Re: Construction Pay Voucher No. 5 (Final) Crosscroft 2n Addition Street and Utility Construction City of Rosemount Project No. 3S8 WSB Project No. 1556 -15 Dear Mayor and Council Members: Please find enclosed the final Construction Pay Voucher No. 5 (Final) for the above- referenced project in the amount of S13,380.60. We recommend final payment subject to receipt of the following items: Morgan Project tsf 1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes 290.92 requiring withholding state income tax. 2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the contract have been fully paid or satisfactorily secured. 3. Consent of Surety to Final Payment certification from the contractor's surety. 4. Two -year maintenance bond. Please make payment in this amount to Ryan Contracting Co. at your earliest convenience. Sincerely, WSB Assnciat's, Inc. Enclosures cc: Andy Brotzler, City of Rosemount Ryan Contracting Co. Packet page 125 of 177 Minneapolis 1 St. Cloud Equal Opportunity Employer a1LNTPROMflL f IV f FM CItAe /OMOOda Project Summary 1 Original Contract Amount $212,423 00 2 Contract Changes Addition $0 00 3 Contract Changes Deduction $0 00 4 Revised Contract Amount 5212,423 00 5 Value Completed to Date 5219,304 25 6 Material on Hand $0 00 7 Amount Earned 3219,304 25 8 Less Retainage 50 00 9 Subtotal 5219,304 25 10 Less Amount Paid Previously 5205,923 65 11 Liquidated Damages $0 00 12 AMOUNT DUE THIS PAY VOUCHER NO 5 FINAL $13,380 60 01556 -15 Pay Voucher 5 WSB R Anoctates, Inc. I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER. Recommended for Ap.roval by: WS: Associates, I 4 A...ve.: )114 ontra Specified Contract Completion Date 7/21/2005 Comment Packet page 126 of 177 Owner: City of Rosemount 2875 145th Street West Rosemount, MN 55068-4941 For Period: 10/1/2005 to 10/15/2006 Contractor: Ryan Contracting Co. 8700 13th Avenue East Shakopee, MN 55379 Pay Voucher RSMT Crosscroft 2nd Addition Client Contract No Protect No 01556 -15 Client Project No 388 Request No.: 5 FINAL Construction Observer Approved by Owner City of Rosemount Date. Tuesday, October 24, 2006 Date: 10/24/2006 1 of 4 a C 4 N 133RD CT W7/ t3- )0 yaliC7 o &7 0AH5I Q CROSS ACT 71rr GROSSLOUGHF 717 Z LL O W o w cn. rn 0 ct DELLWOOD HSTW I V icr J O P 255 510 it vz GONt:_y �epl" w v J Q 4 a �J ∎Cz 4 C OPPER POND I'm XI CROCUS 2 1,020 1 530 2,040 [Feet LAKE FILE /KaNtSYR311Ldl tigthy4^H4ds/0epartmental Maps /Engmeenng /Chns 2nd Lccate mad \V C K�'01R coo c oo-P,1/4 cY CCUC}i -TOW -G )n P TH T Iw 31 a 1 z a 136THSTW 7 a o C OLESHIRE P,y c/ RJ u li w CORLISS TRL 137THSTIaa Q o EC Lt U U RO SCH WAR POND 4 MINNESOTJ October 2006