HomeMy WebLinkAbout6.j. Receive Bids/Award Contract - Glendalough 4th Addition Street & Utility Improvements, City Project #43598ROSEMOUNT SUMMARY
CITY COUNCIL
City Council Meeting: June 7, 2011
AGENDA ITEM: Receive Bids /Award Contract -
AGENDA SECTION:
Glendalough 4th Addition Street and
Consent
Utility Improvements, City Project #435
PREPARED BY: Andrew J. Brotzler, PE, Dire o Public
Works / City Engineer
AGENDA NO... -
ATTACHMENTS: Resolution; Bid Tab; Letter of
APPROVED BY:
Recommendation; Map
RECOMMENDED ACTION: Motion to Adopt a Resolution Receiving Bids and Awarding
the Contract for the Glendalough 4 t " Addition Street and Utility Improvements, City Project
#435.
ISSUE:
Receive bids and award contract for the Glendalough 4th Addition Street and Utility Improvements, City
Project #435.
BACKGROUND:
On Friday, May 27, 2011, bids for this project were received and read aloud publicly. After verification of
bids received, the low bidder is BCM Construction, Inc. in the amount of $434,878.10.
The Glendalough 4`'' Addition is comprised of 25 single - family residential units. The proposed
improvements will complete Carlingford Lane to the north of 134`" Street West (the attached location map
illustrates the project area). The proposed surface improvements include the construction of a 28 -foot
wide city street that includes concrete curb & gutter and 5 -foot concrete sidewalks along both sides. There
will also be a trail connection to the existing bituminous trail along the north property line of the
Glendalough developments. The proposed utility improvements include the construction of water main,
sanitary sewer, and storm sewer.
It is anticipated that the public improvements for the Glendalough 4`' Addition will be fully completed,
including all restoration items (except the bituminous wear course) by the end of the 2011 construction
season.
SUMMARY:
Staff recommends that Council adopt the attached resolution receiving the bids and awarding the contract
for the Glendalough 4th Street and Utility Improvements, City Project #435.
G:AENGPROJ \435 \20110607 CC RecBid- AwardCoiltract.docx
CITY OF ROSEMOUNT
DAKOTA.COUNTY, MINNESOTA
RESOLUTION 2011 —
A RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT
FOR THE GLENDALOUGH 4TH
STREET AND UTILITY IMPROVEMENTS
CITY PROJECT #435
WHEREAS, the City Council authorized the City Engineer to advertise for bids.
BE IT RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows:
All bids on construction of Glendalough 4th Street and Utility Improvements have been received and
tabulated.
1. The bid of BCM Construction, Inc. from Faribault, Minnesota, in the amount of
$434,878.10 for the construction of said improvements is in accordance with the plans and
specifications and advertisement for bids, and is the lowest responsible bid and shall be
and hereby is accepted.
2. The Mayor and Clerk are hereby authorized and directed to enter into a contract with said
bidder for the construction of said improvements for and on behalf of the City of
Rosemount conditioned upon receipt of an executed easement from the property owner in
a form approved by the City Attorney.
3. The City Clerk is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposit of the successful bidder and the next
two lowest bidders shall be retained until a contract has been executed.
ADOPTED this 7` day of June, 2011.
ATTEST:
William H. Droste, Mayor
Amy Domeier, City Clerk
A
Honorable Mayor and City Council
City of Rosemount
2875-145 th Street West
Rosemount, MN 55068
Attn: Cindy Dorniden
Re: Glendalough 4 Addition y
- Street and Utility Construction
City of Rosemount Project No. 435
WSB Project No. 1916 -33
Dear Mayor and Council Members:
} Bids were received for the above - referenced project on Friday, May 27, 2011, and were opened and read
aloud. A total of nine bids were received. The bids were checked for mathematical accuracy and
tabulated... Please find enclosed the bid tabulation indicating the low bidder for the Base Bid (Schedule
A -D) and Alternate 1 as BCM Construction, Inc., Faribault, Minnesota, in the amount of $434,878.10.
Base Bid +
Bidder Base Bid Alternate 1 Alternates
BCM Construction, Inc. 427,343.10 $7,535.00 $434,878.10
Engineer's Estimate $477,133.50 $4,775.00 $481,908.50
We recommend that the City Council consider these bids and award a contract to BCM Construction,
Inc., based on the results of the bids received.
Sincerely,
WSB & Associates, Inc.
Q a 4 o"� — '
Phil Olson, PE
Project Manager
Enclosures
cc: Dan Behrens, BCM Construction, Inc.
Andy Brotzler, City of Rosemount
Cindy Dorniden, City of Rosemount
tsf
,. Minneapolis ❑ St. Cloud
Equal Opportunity Employer
KA01916- 3301Admin \Construction Admin \LTR RECMMDTN- hmcc-052720112.doc
��
Yi S
� Engineering ❑ Planning ❑ Environmental ❑ Construction
701 Xenia Avenue South
& Associates. Inc..
Suite 300
Minneapolis, MN 55416
Tel: 763 - 541 -4800
Fax: 763 - 541 -1700
May 31, 2011
Honorable Mayor and City Council
City of Rosemount
2875-145 th Street West
Rosemount, MN 55068
Attn: Cindy Dorniden
Re: Glendalough 4 Addition y
- Street and Utility Construction
City of Rosemount Project No. 435
WSB Project No. 1916 -33
Dear Mayor and Council Members:
} Bids were received for the above - referenced project on Friday, May 27, 2011, and were opened and read
aloud. A total of nine bids were received. The bids were checked for mathematical accuracy and
tabulated... Please find enclosed the bid tabulation indicating the low bidder for the Base Bid (Schedule
A -D) and Alternate 1 as BCM Construction, Inc., Faribault, Minnesota, in the amount of $434,878.10.
Base Bid +
Bidder Base Bid Alternate 1 Alternates
BCM Construction, Inc. 427,343.10 $7,535.00 $434,878.10
Engineer's Estimate $477,133.50 $4,775.00 $481,908.50
We recommend that the City Council consider these bids and award a contract to BCM Construction,
Inc., based on the results of the bids received.
Sincerely,
WSB & Associates, Inc.
Q a 4 o"� — '
Phil Olson, PE
Project Manager
Enclosures
cc: Dan Behrens, BCM Construction, Inc.
Andy Brotzler, City of Rosemount
Cindy Dorniden, City of Rosemount
tsf
,. Minneapolis ❑ St. Cloud
Equal Opportunity Employer
KA01916- 3301Admin \Construction Admin \LTR RECMMDTN- hmcc-052720112.doc
I IBID TABULATION SUMMARY
PROJECT:
Glendalough 4th Addition
Street and Utility Construction
LOCATION:
City of Rosemount Project No. 435
WSB PROJECT NO.:
1916 -33
Bids Opened: Friday, May 27, 2011 at 10:00 a.m.
Engineer's Opinion of Cost $481,908.50
I hereby certify that this is a true an .correct t yj of the bids as received on May 27, 2011.
Phil Olson, PE
Denotes corrected figure
4
K:101916- 3301AdminlConstruction Admin11916 -33 Bid Tab Summary
Bid Security
Addendum
Base Bid
Contractor
(5 %)
No. 1
Schedules A -D
Alternate 1
Grand Total Bid
1
BCM Construction, Inc.
X
X
$427,343.10
$7,535.00
$434,878.10
2
Ryan Contracting, Co.
X
X
$435,619.10
$6,699.00
$442,318.10
3
Nodland Construction Co., Inc.
X
X
$449,520.23
$7,886.50
$457,406.73
4
Minnesota Dirt Works, Inc.
X
X
$456,290.30
$7,213.50
$463,503.80
5
Burschville Construction, Inc.
X
X
$460,428.60
$8,715.00
$469,143.60
6
Geislinger and Sons, Inc.
X
X
$493,201.75
$7,860.00
$501;061.75
7
Miller Excavating, Inc.
X
X
$496,965.33
$7,824.50
$504,789.83
8
Northdale Construction Co., Inc.
X
X
$498,375.66
$8,477.75
$506,853.41
9
Redstone Construction Co., Inc.
X
X
$530,443.35
$9,074.90
$539,518.25
Engineer's Opinion of Cost $481,908.50
I hereby certify that this is a true an .correct t yj of the bids as received on May 27, 2011.
Phil Olson, PE
Denotes corrected figure
4
K:101916- 3301AdminlConstruction Admin11916 -33 Bid Tab Summary