HomeMy WebLinkAbout6.j. Receive Bids/Award Contract - Glendalough 4th Addition Street & Utility Improvements, City Project #43598ROSEMOUNT SUMMARY CITY COUNCIL City Council Meeting: June 7, 2011 AGENDA ITEM: Receive Bids /Award Contract - AGENDA SECTION: Glendalough 4th Addition Street and Consent Utility Improvements, City Project #435 PREPARED BY: Andrew J. Brotzler, PE, Dire o Public Works / City Engineer AGENDA NO... - ATTACHMENTS: Resolution; Bid Tab; Letter of APPROVED BY: Recommendation; Map RECOMMENDED ACTION: Motion to Adopt a Resolution Receiving Bids and Awarding the Contract for the Glendalough 4 t " Addition Street and Utility Improvements, City Project #435. ISSUE: Receive bids and award contract for the Glendalough 4th Addition Street and Utility Improvements, City Project #435. BACKGROUND: On Friday, May 27, 2011, bids for this project were received and read aloud publicly. After verification of bids received, the low bidder is BCM Construction, Inc. in the amount of $434,878.10. The Glendalough 4`'' Addition is comprised of 25 single - family residential units. The proposed improvements will complete Carlingford Lane to the north of 134`" Street West (the attached location map illustrates the project area). The proposed surface improvements include the construction of a 28 -foot wide city street that includes concrete curb & gutter and 5 -foot concrete sidewalks along both sides. There will also be a trail connection to the existing bituminous trail along the north property line of the Glendalough developments. The proposed utility improvements include the construction of water main, sanitary sewer, and storm sewer. It is anticipated that the public improvements for the Glendalough 4`' Addition will be fully completed, including all restoration items (except the bituminous wear course) by the end of the 2011 construction season. SUMMARY: Staff recommends that Council adopt the attached resolution receiving the bids and awarding the contract for the Glendalough 4th Street and Utility Improvements, City Project #435. G:AENGPROJ \435 \20110607 CC RecBid- AwardCoiltract.docx CITY OF ROSEMOUNT DAKOTA.COUNTY, MINNESOTA RESOLUTION 2011 — A RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT FOR THE GLENDALOUGH 4TH STREET AND UTILITY IMPROVEMENTS CITY PROJECT #435 WHEREAS, the City Council authorized the City Engineer to advertise for bids. BE IT RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows: All bids on construction of Glendalough 4th Street and Utility Improvements have been received and tabulated. 1. The bid of BCM Construction, Inc. from Faribault, Minnesota, in the amount of $434,878.10 for the construction of said improvements is in accordance with the plans and specifications and advertisement for bids, and is the lowest responsible bid and shall be and hereby is accepted. 2. The Mayor and Clerk are hereby authorized and directed to enter into a contract with said bidder for the construction of said improvements for and on behalf of the City of Rosemount conditioned upon receipt of an executed easement from the property owner in a form approved by the City Attorney. 3. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits made with their bids, except that the deposit of the successful bidder and the next two lowest bidders shall be retained until a contract has been executed. ADOPTED this 7` day of June, 2011. ATTEST: William H. Droste, Mayor Amy Domeier, City Clerk A Honorable Mayor and City Council City of Rosemount 2875-145 th Street West Rosemount, MN 55068 Attn: Cindy Dorniden Re: Glendalough 4 Addition y - Street and Utility Construction City of Rosemount Project No. 435 WSB Project No. 1916 -33 Dear Mayor and Council Members: } Bids were received for the above - referenced project on Friday, May 27, 2011, and were opened and read aloud. A total of nine bids were received. The bids were checked for mathematical accuracy and tabulated... Please find enclosed the bid tabulation indicating the low bidder for the Base Bid (Schedule A -D) and Alternate 1 as BCM Construction, Inc., Faribault, Minnesota, in the amount of $434,878.10. Base Bid + Bidder Base Bid Alternate 1 Alternates BCM Construction, Inc. 427,343.10 $7,535.00 $434,878.10 Engineer's Estimate $477,133.50 $4,775.00 $481,908.50 We recommend that the City Council consider these bids and award a contract to BCM Construction, Inc., based on the results of the bids received. Sincerely, WSB & Associates, Inc. Q a 4 o"� — ' Phil Olson, PE Project Manager Enclosures cc: Dan Behrens, BCM Construction, Inc. Andy Brotzler, City of Rosemount Cindy Dorniden, City of Rosemount tsf ,. Minneapolis ❑ St. Cloud Equal Opportunity Employer KA01916- 3301Admin \Construction Admin \LTR RECMMDTN- hmcc-052720112.doc �� Yi S � Engineering ❑ Planning ❑ Environmental ❑ Construction 701 Xenia Avenue South & Associates. Inc.. Suite 300 Minneapolis, MN 55416 Tel: 763 - 541 -4800 Fax: 763 - 541 -1700 May 31, 2011 Honorable Mayor and City Council City of Rosemount 2875-145 th Street West Rosemount, MN 55068 Attn: Cindy Dorniden Re: Glendalough 4 Addition y - Street and Utility Construction City of Rosemount Project No. 435 WSB Project No. 1916 -33 Dear Mayor and Council Members: } Bids were received for the above - referenced project on Friday, May 27, 2011, and were opened and read aloud. A total of nine bids were received. The bids were checked for mathematical accuracy and tabulated... Please find enclosed the bid tabulation indicating the low bidder for the Base Bid (Schedule A -D) and Alternate 1 as BCM Construction, Inc., Faribault, Minnesota, in the amount of $434,878.10. Base Bid + Bidder Base Bid Alternate 1 Alternates BCM Construction, Inc. 427,343.10 $7,535.00 $434,878.10 Engineer's Estimate $477,133.50 $4,775.00 $481,908.50 We recommend that the City Council consider these bids and award a contract to BCM Construction, Inc., based on the results of the bids received. Sincerely, WSB & Associates, Inc. Q a 4 o"� — ' Phil Olson, PE Project Manager Enclosures cc: Dan Behrens, BCM Construction, Inc. Andy Brotzler, City of Rosemount Cindy Dorniden, City of Rosemount tsf ,. Minneapolis ❑ St. Cloud Equal Opportunity Employer KA01916- 3301Admin \Construction Admin \LTR RECMMDTN- hmcc-052720112.doc I IBID TABULATION SUMMARY PROJECT: Glendalough 4th Addition Street and Utility Construction LOCATION: City of Rosemount Project No. 435 WSB PROJECT NO.: 1916 -33 Bids Opened: Friday, May 27, 2011 at 10:00 a.m. Engineer's Opinion of Cost $481,908.50 I hereby certify that this is a true an .correct t yj of the bids as received on May 27, 2011. Phil Olson, PE Denotes corrected figure 4 K:101916- 3301AdminlConstruction Admin11916 -33 Bid Tab Summary Bid Security Addendum Base Bid Contractor (5 %) No. 1 Schedules A -D Alternate 1 Grand Total Bid 1 BCM Construction, Inc. X X $427,343.10 $7,535.00 $434,878.10 2 Ryan Contracting, Co. X X $435,619.10 $6,699.00 $442,318.10 3 Nodland Construction Co., Inc. X X $449,520.23 $7,886.50 $457,406.73 4 Minnesota Dirt Works, Inc. X X $456,290.30 $7,213.50 $463,503.80 5 Burschville Construction, Inc. X X $460,428.60 $8,715.00 $469,143.60 6 Geislinger and Sons, Inc. X X $493,201.75 $7,860.00 $501;061.75 7 Miller Excavating, Inc. X X $496,965.33 $7,824.50 $504,789.83 8 Northdale Construction Co., Inc. X X $498,375.66 $8,477.75 $506,853.41 9 Redstone Construction Co., Inc. X X $530,443.35 $9,074.90 $539,518.25 Engineer's Opinion of Cost $481,908.50 I hereby certify that this is a true an .correct t yj of the bids as received on May 27, 2011. Phil Olson, PE Denotes corrected figure 4 K:101916- 3301AdminlConstruction Admin11916 -33 Bid Tab Summary