HomeMy WebLinkAbout2.e. Ratify Default on 2007 Street Improvements Project, Project #410�tROSEMO EXECUTIVE SUMMARY
CITY COUNCIL
City Council Meeting: July 20, 2010
AGENDA ITEM: Ratify Default on 2007 Street
AGENDA SECTION:
Improvements Project, City Project #410
Consent
PREPARED BY: Andrew J. Brotzler, PE, Director f ublic
AGENDA NO.
Works /City Engineer
'
ATTACHMENTS: Project Punch List, Notice of Interif Letter
to Declare Default to United Fire &
Casualty and Sammon Parker
APPROVED BY:
Construction, Letter from United Fire
Group
RECOMMENDED ACTION: Motion to ratify default and termination of contract to Sammon
Parker Construction and United Fire and Casualty Company on the 2007 Street
Improvements Project, City Project #410.
BACKGROUND:
The two year warranty period for the 2007 Street Improvements Project is scheduled to expire August 4,
2010. The contractor, Sammon Parker Construction, has failed to complete the project punch list (see
attached) itemizing the required warranty work. The estimated cost to complete the work is $11,720.
On June 28, 2010, the City sent a letter by certified mail for the Notice of Intent to Declare Default to
Sammon Parker Construction and the Surety Company (United Fire and Casualty Company). The letter
notified the two companies that Sammon Parker Construction was in default of the contract for not
completing the work as required by the two year warranty period. A meeting was scheduled with the
contractor for July 2, 2010; however the contractor did not attend or contact the City to reschedule.
The City attorney is currently drafting a letter declaring that Sammon Parker Construction is in default of
the contract and that the City is terminating their contract. The letter is scheduled to be mailed out July 19,
2010 to Sammon Parker Construction and the Surety Company. The City attorney is also drafting a letter
to the Surety Company to demand that they promptly make arrangements to perform the warranty work
as itemized on the project punch list and notify the City of their plan. An additional notice of default
would be required for the Surety Company if they do not respond with a plan to complete the work.
SUMMARY:
Upon recommendation from the City attorney's office, Staff is recommending that Council ratify default
and termination of contract.
G: \ENGPROJ \410 \20100720 CC Ratify Default.doc
2007 Street Improvement Project - Warranty Punchlist
WSB Project #: 1556 -89
Rosemount Project #: 410
Date:6 /21/10
Please Contact Joe Koscielak at 612 - 360 -1287 prior to beginning work.
Item #
Description
Location
Date
Accepted
1
Remove and Replace Cracked Curb and
Gutter (10')
SW Corner 145th Street /Biscayne Way
2
ISaw and Seal Curb and Gutter
NW Corner 145th Street /Biscayne Way
3
Saw and Seal Curb and Gutter
14575 Biscayne Way
4
Saw and Seal Curb and Gutter
Between 14605 Biscayne Way and 14615
Biscayne Way
5
Remove and Replace Curb and Gutter (3')
14655 Biscayne Way (no mark)
6
Remove and Replace Curb and Gutter (3')
14665 Biscayne Way (no mark)
7
Remove and Replace Curb and Gutter (9')
14685 Biscayne Way
8
Saw and Seal Curb and Gutter
14590 Biscayne Way
9
Remove and Replace Cracked Driveway
Panel
14640 Biscayne Way
10
Remove and Replace Cracked Pedestrian
Ramp (2 Panels)
Next to Lower 147th and Cambrian Intersect
Sign
11
Remove and Replace Cracked Pedestrian
Ramp Sidewalk (1 Panel)
Next to Lower 147th and Cambrian Intersect
Sign
12
Remove and Replace Driveway Wing
14790 Cambrian Avenue
13
Replace Dead Spruce Tree
Patch of Planted Trees Across from Rudy's Red
Eye Grill
14
Replace or overlay settled areas of
bituminous path
Between Cambrian Avenue and Camero Ln
15
Saw and Seal Curb and Gutter
14825 Camero Lane
16
Remove and Replaced Cracked Driveway
Panel
14805 Camero Lane
17
Remove and Replace Cracked Driveway
Win
House Across from 14720 CambrianAvenue
18
Saw and Seal Curb and Gutter
House Across from 14720 Cambrian Avenue
19
Remove and Replace Driveway Panels
14820 Camero Lane
20
Saw and Seal Curb and Gutter
14755 Cambrian Avenue
21
Saw and Seal Curb and Gutter
14755 Cambrian Avenue
22
Saw and Seal Curb and Gutter
14755 Cambrian Avenue near Stop Sign
23
Remove and Replace DWY Panel
14800 Camero Lane
4ROSEMOUNT
PUBLIC WORKS DEPARTMENT
June 28, 2010
VIA CERTIFIED MAIL
United Fire & Casualty Company
PO Box 73909
Cedar Rapids, IA 52407 -3909
Sammon Parker Construction, Inc.
16810 Bagley Avenue
Faribault, MN 55021
Re: Bond No. 54- 166460
2007 Street Improvement Project
City Project No. 410
NOTICE OF INTENT TO DECLARE DEFAULT
Dear Sir or Madam:
Please take notice that the City intends to declare Sammon Parker Construction, Inc. ( "Contractor's in
default of the Contract for the above - referenced project if satisfactory plans are not made to complete the
warranty work as itemized on the attached punch list.
The Contractor, under the terms of the Contract, warranted its work, equipment, and materials for a period
of two years from the date of final payment. As Surety, United Fire & Casualty Company issued the above -
referenced bond, thereby binding itself to the City for the Contractor's performance of the warranty work.
The warranty work must be completed as itemized on the attached punch list.
We are holding a meeting at the office of the City Engineer, in Rosemount City Hall, on July 2, 2010 at 9:00
a.m. to review the Contractor's arrangements to perform the warranty work. Promptly advise the City
Engineer at 651 - 322 -2025 if you are not available and propose alternate dates for the meeting. The meeting
must be held within fifteen (15) days of your receipt of this letter. If you do not intend to perform the work,
promptly advise.
If the Contractor does not present satisfactory arrangements to perform the warranty work, the City will
declare the Contractor in default and terminate its right to complete the work.
Thank you for your prompt attention to this matter.
Sincerely,
Andrew J. Brotzler, PE
City Engineer
Enclosure
cc: Dean Sammon: dsammon @myclearwave.net
Charlie L. LeFevere, Esq.
G: \ENGPROJ \410 \06282010 Notice of intent to declare default - 370906v1.docx
SPIRIT OF PRIDE AND PROGRESS
2875 145th Street West • Rosemount, MN 55068 -4997 •651- 423 -4411 • TDD/TTY 651- 423 -6219 - Fax 651 - 322 -2694
www.ci.rosemount.mmus
Un
UNITED FIRE GROUP
Surety Department
July 1, 2010
City of Rosemount
2875 - 145th Street West
Rosemount, MN. 55068 -4997
ATTENTION: Andrew J. Brotzler, PE
RE: PRINCIPAL: Sammon Parker Construction, Inc.
BOND NO.: 54- 166460
Dear Mr. Brotzler:
We are in receipt of your letter dated June 28, 2010.
United Fire & Casualty Company
United Life Insurance Company
Addison Insurance Company
Lafayette Insurance Company
United Fire & Indemnity Company
United Fire Lloyds
Texas General Indemnity Company
United Fire & Casualty Company, as Surety, is presently conducting an
investigation into your claim. Neither this letter, or any investigation undertaken
by Surety, should be construed to be a waiver of any of our rights under the
bond.
We will be back in contact with you upon completion of the investigation.
Sincerely,
UNITED FIRE & CASUALTY COMPANY
Steven C. Watters
Senior Surety Claims Representative
SCW:mld
cc: Sammon Parker Construction, Inc. (Mr. Dean Sammon)
Klein Agnecy, Inc. 20 -3414
HOME OFFICE: 118 Second Ave. SE, PO Box 73909, Cedar Rapids, IA 52407 -3909 Phone: 319 - 399 -5700 FAX: 319 - 286 -2520 www.unitedfiregroup.com