HomeMy WebLinkAbout6.h. Payment #5 & Final - Glendalough and Glendalough 2nd Street and Utility Improvements, City Project #4274ROSEMOUNTEXECUTIVE SUMMARY
CITY COUNCIL
City Council Meeting: August 4, 2010
AGENDA ITEM: Payment #5 & Final — Glendalough and
AGENDA SECTION:
Glendalough 2nd Street and Utility
Consent
Improvements, City Project #427
PREPARED BY: Andrew J. Brotzler, PE, Director of P lic
AGENDA NO.
Works / City Engineer
ATTACHMENTS: Payment Voucher, Map
APPROVED BY:
RECOMMENDED ACTION: Motion to Approve Payment #5 and Final for the Glendalough
and Glendalough 2nd Street and Utility Improvements, City Project #427, to McNamara
Contracting, Inc. and Accepting it for Perpetual Maintenance.
BACKGROUND:
This item is on the agenda to request Payment #5 and Final to McNamara Contracting, Inc. for the
Glendalough and Glendalough 2nd Addition, City Project #427. This project included the construction of
storm sewer, streets, and sidewalks within the Glendalough and Glendalough 2nd Addition.
The final construction amount of $216,834.01 is 8.1% below the contract amount of $235,923.75.
SUMMARY:
Staff recommends that Council approve Payment #5 and final for the project and accept the project for
perpetual maintenance subject to the following conditions.
1. Satisfactorily showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year maintenance bond.
G: \ENGPROJ \427 \20100804 CC Payment 5 &Final.doc
WSB
� Engineering Planning
& Associates, kie.
July 13, 2010
Environmental Construction
Honorable Mayor and City Council
City of Rosemount
2875 145th Street West
Rosemount, MN 55068
ATTN: Cindy Dorniden
Re: Construction Pay Voucher No. 5 (Final)
2009 Glendalough and Glendalough 2nd Additions
City of Rosemount Project No. 427
WSB Project No. 1668 -91
Dear Mayor and Council Members:
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 - 541 -4800
Fax: 763- 541 -1700
Please find enclosed the final Construction Pay Voucher No. 5 (Final) for the above - referenced project
in the amount of $18,884.97. We recommend final payment subject to receipt of the following items:
1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year maintenance bond.
Please make payment in this amount to McNamara Contracting, Inc. at your earliest convenience.
Sincerely,
WSB & Associates, Inc.
Morg Da 1 , PE
Projec ger
Enclosures
cc: Cindy Dorniden, City of Rosemount
Kevin McNamara, McNamara Contracting, Inc.
tsf
Minneapolis St. Cloud
Equal Opportunity Employer
Owner: City of Rosemount
2875 145th Street West
Rosemount, MN 55068 -4941
For Period: 6/9/2010 to 6/30/2010
Contractor: McNamara Contracting, Inc.
16700 Chippendale Avenue
Rosemount, MN 55068
Pay Voucher
RSMT - Glendalough 2009 Addns
Client Contract No.:
Project No.: 01668 -91
Client Project No.: 427
Date: 7/7/2010
Request No.: 5 & FINAL
Project Summary
1
Original Contract Amount
$235,923.75
2
Contract Changes - Addition
$0.00
3
Contract Changes - Deduction
$0.00
4
Revised Contract Amount
$235,923.75
5
Value Completed to Date
$216,834.01
6
Imaterial on Hand
$0.00
7
Amount Earned
$216,834.01
8
Less Retainage
$0.00
9
Subtotal
$216,834.01
10
Less Amount Paid Previously
$197,949.04
11
Liquidated Damages
$0.00
12
AMOUNT DUE THIS PAY VOUCHER NO. 5 & FINAL
$18,884.97
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT
THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL
VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE WITH,
AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER.
Recommended for Approval by:
Specified Contract Completion Date:
12/31/2010
Comment:
Cons n Observer:
Approved by Owner:
City of Rosemount
Date:
Project Material Status
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity I
Amount to
Date
SCHEDULE A- SURFACE IMPROVEMENTS
1
2021.501
MOBILIZATION (5% MAXIMUM)
LUMP SUM
$11,780.00
1
1
0.25
$11,780.00
2
2104.501
REMOVE CURB AND GUTTER
LIN FT
$5.00
60
80
0
$400.00
3
2104.501
REMOVE SILT FENCE
LIN FT
$1.00
400
240
0
$240.00
4
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
$2.50
60
62
0
$155.00
5
2104.511
SAWING CONCRETE PAVEMENT (FULL DEPTH)
LIN FT
$5.00
30
0
0
$0.00
6
2104.5131
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
$3.00
70
56
0
$168.00
7
2104.523
SALVAGE SIGN
EACH
$1.00
4
6
0
$6.00
8
2105.501
COMMON EXCAVATION (P)
CU YD
$11.40
3350
3350
0
$38,190.00
9
2105.507
SUBGRADE EXCAVATION
CU YD
$1.00
100
3032
0
$3,032.00
10
2105.522
SELECT GRANULAR BORROW (CV)
CU YD
$1.00
3300
2638
0
$2,638.00
11
2112.501
SUBGRADE PREPARATION
ROAD STA
$500.00
11.5
11.5
0
$5,750.00
12
2211.501
AGGREGATE BASE CLASS 5
TON
$4.50
1680
1789.57
0
$8,053.07
13
2350.501
TYPE LV 3 WEARING COURSE MIXTURE (C)
TON
$29.00
465
441.51
95.21
$12,803.79
14
2350.502
TYPE LV 3 NON WEARING COURSE MIXTURE (C)
TON
$29.00
465
481.35
95.2
$13,959.15
15
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
$2.50
210
175
0
$437.50
16
2504.602
ADJUST GATE VALVE AND BOX
EACH
$250.00
4
4.55
0
$1,137.50
17
2506.522
ADJUST FRAME & RING CASTING ( SANITARY)
EACH
$350.00
8
8
0
$2,800.00
18
2521.501
6" CONCRETE WALK
SQ FT
$5.35
11400
10395
0
$55,613.25
19
2531.501
CONCRETE CURB & GUTTER, DESIGN MODIFIED S
LIN FT
$12.15
2100
2160
0
$26,244.00
20
2535.501
BITUMINOUS CURB
LIN FT
$2.00
295
291
0
$582.00
21
2545.523
4" NON - METALLIC CONDUIT
LIN FT
$3.00
180
160
0
$480.00
22
2563.601
jTRAFFIC CONTROL
LUMP SUM
$3,300.00
1
1
0
$3,300.00
23
2564.5311
F &I SIGN PANELS TYPE C
SQ FT
$35.00
6.25
6.25
0
$218.75
24
2564.602
INSTALL SALVAGED SIGN
EACH
$155.00
2
21
0
$310.00
25
2573.502
SILT FENCE, TYPE MACHINE SLICED
LIN FT
$2.00
825
605
0
$1,210.00
26
2573.602
TEMPORARY ROCK CONSTRUCTION ENTRANCE
EACH
$100.00
2
1
0
$100.00
27
2573.602
INLET PROTECTION
EACH
$75.00
14
14
0
$1,050.00
28
2575.501
SEEDING (INCL TOPSOIL, FERT, MULCH, DISC ANCHOR)
ACRE
$1,025.00
1
1.6
0
$1,640.00
29
2575.502
SEED MIXTURE 250
POUND
$4.20
75
0
0
$0.00
30
2575.505
SODDING, TYPE LAWN (INCL. TOPSOIL & FERT.)
SQ YD
$6.00
4910
2175
0
$13,050.00
31
2564.603
12" SOLID LINE WHITE -PAINT
LIN FT
$35.00
12
161
0
$560.00
Totals For Section SCHEDULE A - SURFACE IMPROVEMENTS:
$205,908.01
SCHEDULE B - STORM SEWER IMPROVEMENTS
32
2104.5231
SALVAGE CASTING
EACH
$1.00
1
11
0
$1.00
33
2503.541
15" RC PIPE SEWER DESIGN 3006 CLASS V
LIN FT
$25.00
96
95
0
$2,375.00
34
2503.602
CONNECT TO EXISTING MANHOLE (STORM)
EACH
$500.00
3
3
0
$1,500.00
35
2506.516
CASTING ASSEMBLY
EACH
$750.00
1
1
0
$750.00
36
2506.522
ADJUST FRAME & RING CASTING ( STORM)
EACH
$200.00
10
9
0
$1,800.00
37
2506.602
CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 1
I EACH
1 $1,500.001
3
3
0
$4,500.00
Totals For SCHEDULE B - STORM SEWER IMPROVEMENTS:
$10,926.00
Project Totals:
$216,834.01
Project Payment Status
Owner: City of Rosemount
Client Project No.: 427
Client Contract No.:
Project No.: 01668 -91
Contractor: McNamara Contracting, Inc.
Contract Chances
No. Type
Date
Description
JAmount
Change Order Totals:
1 $0.00
avmentSummarf
a
No.
From Date
To Date
Payment
Total
Payment
Retainage
Per
Payment
Total
Retainage
Total
Payment +
Retainage
Work
Certified
Per
Payment
Total Work
Certified
1
9/1/2009
9/30/2009
$56,809.97
$56,809.97
$2,990.00
$2,990.00
$59,799.97
$59,799.97
$59,799.97
2
10/1/2009
10/30/2009
$41,262.92
$98,072.89
$2,171.73
$5,161.73
$103,234.62
$43,434.65
$103,234.62
3
11/1/2009
11/30/2009
$34,646.06
$132,718.95
$1,823.48
$6,985.21
$139,704.16
$36,469.54
$139,704.16
4
12/31/2009
6/8/2010
$65,230.09
$197,949.04
$3,433.16
$10,418.371$208,367.41
$68,663.25.$208,367.41
5 &
FINAL
6/9/2010
6/30/2010
$18,884.97
$216,834.01
($10,418.37)
$0.00
$216,834.01
$8,466.60
$216,834.01
Payment Totals:
1$216,834.011
$0.00
$216,834.011
$216,834.01
Proiect Summary
Material On Hand:
Total Payment to Date:
Total Retainage:
Total Amount Earned:
$0.00
$216,834.01 Original Contract:
$0.00 Contract Changes:
$216,834.01 Revised Contract:
$235,923.75
$0.00
$235,923.75
UFFE
ZOCT C
CROLLY
CT
r
7-
G
�
j Park
�
SH /gym
r
= L
CR GGS
O
D
CRp`NFO�R
Shannol�p
ST W
_._ Park 0
CC) R
�sQ U3 ,
.C.HARLSTON WAY
c
Glendalough n7ko**O
132ND
ST W
Q
W
COUCHTOWN.o GpRRgCy �J czzi
TH RI
ftS !WA op '9 q`F o
O
SLOUGH TEL ° v aN
� yCT i �
°F- . ,.. O
zO
a W y F JG���b a v POpZO�P vO
JPt H w_ A` O TH S T W
VO PAT COLES REFI; H O OLISS TRL x j d
b
/
"oa
41�r
- N \
137TH STJ
------------ o
s R'?, o
OWN Scj Glendalough
D
E '
-3pa
\ i „ eFhwarz Pond Patin
142ND
0 480 960 1,920 2,880
T: /GIS/City /Maps/Departmental Maps /Enginee ing/Chds/Glendalough 2009 Locate
W
� Feet
11
ROSEMO
01 �,'—
132F=— D C
—
133RD S 133�� gT O A
CL
X
~ m;
Qe
� cy
W off- Z
N 134TH SL, r
z :.
o_
M z5 � 1361
"
Brockway W
PKWY
rtl
j Park
Carrolls
CONNEMARA
Woods
ST W
Park
p , 51, 138TH
8 U. 138TH ST W
�
�
W'
-------------------------------------------------- --- W
Q
3
143R I ST W r
Q
Q
Ui
W
a
UPPER
143RD
H
v
�z
144_
ST W
V
142ND
0 480 960 1,920 2,880
T: /GIS/City /Maps/Departmental Maps /Enginee ing/Chds/Glendalough 2009 Locate
W
� Feet
11
ROSEMO
01 �,'—
132F=— D C
—
133RD S 133�� gT O A
CL
X
~ m;
Qe
� cy
W off- Z
N 134TH SL, r
z :.
o_
M z5 � 1361
"
Brockway W
PKWY
rtl
j Park
CONNEMARA
w
Q L i 138TH ST W
ST W
p , 51, 138TH
8 U. 138TH ST W
�
�
139TH STIN ���,
�
m W W W
4 !
W.
w.
2 W
m a z
z.
140TH ST W' == o -= m-
ff
Erickson
Park
Central
Park.
lu.
a
1
130TH
FCEE��G
BIRDSON
B LMONT
T
�F
B LF T
C
a
Z
a
BEECH ST W
July 2009