HomeMy WebLinkAbout6.p. Payment #3 and Final - Trunk Highway 3 (143rd to 145th) Street and Signal Improvements, City Project 4214DA(C)ISEMOLINT EXECUTIVE SUMMARY
CITY COUNCIL
City Council Meeting: December 21, 2010
AGENDA ITEM: Payment #3 and Final — Trunk Highway 3
(143rd to145th) Street and Signal AGENDA SECTION:
Improvements, City Project #421 Consent
PREPARED BY: Andrew J Brotzler, PE, Director of P AGENDA NO.
Works /City Engineer
ATTACHMENTS: Final Pay Voucher, Map APPROVED BY:
RECOMMENDED ACTION: Motion to Approve Payment # 3 and Final for the Trunk
Highway 3 (143�d to145th) Street and Signal Improvements, City Project #421, to Max
Steininger, Inc. and Accepting it for Perpetual Maintenance
BACKGROUND:
This item is on the agenda to request Payment #3 and Final to Max Steininger, Inc. for the Trunk
Highway 3 (143`d to 145th) Street and Signal Improvements, City Project #421.
This pay voucher includes three change orders for additional minor extra work identified as necessary
during construction. Change Order No. 1 includes the removal of an existing conduit bank in conflict
with the new storm sewer. Change Order No. 2 includes the placement of additional topsoil necessary to
facilitate drainage within the boulevard at 143`d Street. Change Order No. 3 includes salvaging and
reinstalling three no parking signs to complete sidewalk replacement on 145' Street. These changes result
in a net increase of $4,589.79 for a revised contract amount of $334,721.82. Funding for the change orders
included within Construction Pay Voucher No. 3 are eligible for Municipal State Aid Funding.
The final construction amount of $325,760.69 is 2.7% below the revised contract amount of $334,721.82.
SUMMARY:
Staff recommends that Council approve Payment #3 and final for the project, and accept the project for
perpetual maintenance subject to the following conditions.
1. Satisfactorily showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year maintenance bond.
G: \ENGPROJ \421 \20101221 CC FinalPayment 3.doc
WSB
- Engineering ❑ Planning _- Environmental F1 Construction 701 Xenia Avenue South
& Associates. Inc. Suite 300
Minneapolis, MN 55416
Tel: 763 -541 -4800
December 16, 2010 Fax: 763 - 541 -1700
Honorable Mayor and City Council
City of Rosemount
2875 — 145`h Street West
Rosemount, MN 55068
Attn: Cindy Dorniden, City of Rosemount
Re: Construction Pay Voucher No. 3 (Final)
TH 3, 143`d to 145d` Street
Signal Improvement and Right -Turn Lane
City of Rosemount Project No. 421
SP 1921 -89 & SAP 208 - 010 -007
WSB Project No. 1668 -85
Dear Mayor and Council Members:
Please find enclosed the final Construction Pay Voucher No. 3 for the above - referenced project in the amount of
$27,844.25.
Also enclosed are the following documents required for processing final payment for the above - referenced
project:
1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes 290.92
requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the contract have
been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year Maintenance Bond (warranty start date to coincide with the date Council approves final
payment).
We recommend that you make final payment in the amount of $27,844.25 for Max Steininger, Inc. at your earliest
convenience. Please contact me at 651- 322 -2015 if you have any questions or comments regarding the enclosed
information. Thank you.
Sincerely,
WSB & Associates, Inc.
Phi Olson, PE
Project Manager
Enclosures
cc: Cindy Dorniden, City of Rosemount
Andy Brotzler, City of Rosemount
Bobby Kathuria, Max Steininger, Inc.
Minneapolis C St. Cloud
Equal Opportunity Employer
Pay Voucher
Owner: City of Rosemount Date: 9/30/2010
2875 145th Street West
Rosemount, MN 55068 -4941
H�S_B For Period: 711/2010 to 9/30/2010 Request No.: 3 & FINAL
Contractor: Max Steininger, Inc.
3080 Lexington Avenue South
& Associates, Inc. Eagan, MN 55121
Pay Voucher
RSMT - TH 3 143rd -145th Street Signal Improvements and Right -Turn Lane
Client Contract No.:
Project No.: 01668 -85
Client Project No.: CP 421
Project
Summary
1
Original Contract Amount
$330,132.03
2
Contract Changes - Addition
$4,589.79
3
Contract Changes - Deduction
$0.00
4
Revised Contract Amount
$334,721.82
5
lValue Completed to Date
$325,760.69
6
1 Material on Hand
$0.00
7
Amount Earned
$325,760.69
8
Less Retainage
$0.00
9
Subtotal
$325,760.69
10
Less Amount Paid Previously
$297,916.44
11
Liquidated Damages
$0.00
12
JAMOUNT DUE THIS PAY VOUCHER NO. 3 & FINAL
$27,844.25
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT THE
CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL VOUCHER
HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE WITH, AND
PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER.
Recommended for Approval by: Construction Observer:
WSB & Associates, Inc.
Approved by Contractor:
Max Steininger, Inc.
Approved by Owner:
City of Rosemount
Specified Contract Completion Date: Date:
7/16/2010
Comment:
Page 1 of 4
Pay Voucher
Project Material Status
Item
No.
I Item
Description
Units
Unit Price
Contract
Quantity
IQuantityto
Date
Current
Quantity
Amount to
Date
BASE BID
1
2021.501
MOBILIZATION
LUMP SUM
$8,330.24
1
1
0
$8,330.24
2
2102.502
PAVEMENT MARKING REMOVAL
LIN FT
$0.54
4001
976
320
$527.04
3
2104.501
REMOVE WATER MAIN
LIN FT
$5.49
25
22
0
$120.78
4
2104.501
REMOVE SEWER PIPE (STORM)
LIN FT
$5.49
31
31
0
$170.19
5
2104.501
REMOVE CURB AND GUTTER
LIN FT
$2.32
460
550
0
$1,276.00
6
2104.503
REMOVE CONCRETE WALK
SQ FT
$0.61
4400
4327
0
$2,639.47
7
2104.505
REMOVE BITUMINOUS SIDEWALK
SQ YD
1 $6.14
125
300
0
$1,842.00
8
2104.505
REMOVE CONCRETE DRIVEWAY PAVEMENT
SQ YD
$6.14
701
67
0
$411.38
9
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
$3.48
9801
775
0
$2,697.00
10
2104.509
REMOVE STAIRS
EACH
$220.97
1
1.5
0
$331.46
11
2104.509
REMOVE DRAINAGE STRUCTURE
EACH
$219.58
1
1
0
$219.58
12
12104.509,
REMOVE SIGN TYPE C
EACH
$53.51
1
3
2
$160.53
13
2104.511
SAWING CONCRETE PAVEMENT (FULL DEPTH)
LIN FT
$3.34
100
119
0
$397.46
14
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
$1.20
1030
966
0
$1,159.20
15
2104.603
ABANDON WATER MAIN
LIN FT
$8.78
118
103
0
$904.34
16
2105.501
COMMON EXCAVATION (P)
CU YD
$14.32
515
515
0
$7,374.80
17
2105.507
SUBGRADE EXCAVATION (P)
CU YD
$15.80
790
790
0
$12,482.00
18
2105.522
SELECT GRANULAR BORROW (CV)
CU YD
$9.09
790
790
0
$7,181.10
19
2211.501
AGGREGATE BASE CLASS 5
TON
$19.81
50
60.17
0
$1,191.97
20
2211.503
AGGREGATE BASE (CV) CLASS 5 (P)
CU YD
$30.17
250
250
0
$7,542.50
21
2231.501
BITUMINOUS PATCHING MIXTURE
TON
$96.44
16
19.89
0
$1,918.19
22
2232.501
MILL BITUMINOUS SURFACE (1.5)
SQ YD
$3.86
1200
1257
97
$4,852.02
23
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (4,E)
TON
$82.79
5101
390.47
0
$32,327.01
24
12411.5071
CONCRETE STAIRWAY
EACH
$2,647.48
1
1.5
0
$3,971.22
25
2503.541
15" RC PIPE SEWER DESIGN 3006 CLASS V
LIN FT
$23.05
488
488
0
$11,248.40
26
2503.602
CONSTRUCT BULKHEAD
EACH
$329.37
1
1
0
$329.37
27
2504.602
CONNECT TO EXISTING WATER MAIN
EACH
$878.33
4
6
2
$5,269.98
28
2504.602
ADJUST GATE VALVE
EACH
$109.79
2
3
0
$329.37
29
2504.603
12" WATER MAIN -DUCT IRON CL 52
LIN FT
$76.85
145
145
16
$11,143.25
30
2504.604
4" POLYSTYRENE INSULATION
SQ YD
$38.42
15
8.9
0
$341.94
31
2504.608
DUCTILE IRON FITTINGS
POUND
$2.20
1965
2580
860
$5,676.00
32
2506.501
CONSTRUCT DRAINAGE STRUCTURE DESIGN 48 -4020
LIN FT
$318.39
33.2
32.06
0
$10,207.58
33
2506.516
CASTING ASSEMBLY
EACH
$439.16
6
6
0
$2,634.96
34
2506.522
ADJUST FRAME & RING CASTING
EACH
$170.17
21
2
0
$340.34
35
2506.602
CONNECT INTO EXISTING DRAINAGE STRUCTURE
EACH
$329.37
1
1
0
$329.37
36
12521.50114"
CONCRETE WALK (HE)
SQ FT
$2.98
3950
2942
0
$8,767.16
37
2521.501
6" CONCRETE WALK (HE)
SQ FT
$5.03
410
808
0
$4,064.24
38
2521.511
2.5' BITUMINOUS WALK
SQ FT
$2.00
2630
2621
0
$5,242.00
39
2531.501
CONCRETE CURB & GUTTER DESIGN B618 HE
LIN FT
$14.63
60
28
0
$409.64
40
2531.501
CONCRETE CURB & GUTTER DESIGN 8624 (HE)
LIN FT
$14.63
630
758
0
$11,089.54
41
2531.502
CONCRETE CURB DESIGN V8 (HE)
LIN FT
$20.70
85
90
0
$1,863.00
42
2531.507
6" CONCRETE DRIVEWAY PAVEMENT HE
SQ YD
$40.67
70
76
0
$3,090.92
43
2531.618
TRUNCATED DOMES
SQ FT
$31.39
240
186
0
$5,838.54
44
2533.507
PORTABLE PRECAST CONCRETE BARRIER DESIGN 8337
LIN FT
$12.84
574
577.35
1.35
$7,413.17
45
2554.615
IMPACT ATTENUATOR
ASSEMBLY
$1,498.38
2
2
0
$2,996.76
46
2563.601
TRAFFIC CONTROL
LUMP SUM
$4,281.11
1
1
0
$4,281.11
47
2564.531
SIGN PANELS TYPE C
SQ FT
1 $34.78
6.3
17.1
10.8
$594.74
48
2565.511
TRAFFIC CONTROL SIGNAL SYSTEM
SIG SYS
$96,259.78
1
1
0
$96,259.78
49
12565.6011
EMERGENCY VEHICLE PREEMPTION SYSTEM
LUMP SUM
$6,125.62
1
1
0
$6,125.62
50
12573.5021
SILT FENCE, TYPE PREASSEMBLED
LIN FT
$1.281
5001
410
0
$524.80
Page 2 of 4
Pay Voucher
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
51
2573.530
STORM DRAIN INLET PROTECTION
EACH
$176.43
7
11
0
$1,940.73
52
2575.505
SODDING TYPE LAWN
SQ YD
$3.21
1250
1185
237
$3,803.85
53
2580.603
INTERIM PAVEMENT MARKINGS
LIN FT
$1.34
1200
3337
663
$4,471.58
54
2582.501
PAVEMENT MESSAGE (LEFT ARROW) PAINT
EACH
$64.21
5
8
0
$513.68
55
2582.501
PAVEMENT MESSAGE (RIGHT ARROW) PAINT
EACH
$64.21
1
2
0
$128.42
56
2582.501
PAVEMENT MESSAGE (RIGHT -THRU ARROW) PAINT
EACH
$85.63
4
5
0
$428.15
57
2582.501
PAVEMENT MESSAGE (RIGHT -THRU ARROW) EPDXY
EACH
$160.54
4
0
0
$0.00
58
2582.501
PAVEMENT MESSAGE (LT ARROW) EPDXY
EACH
$123.08
8
2
0
$246.16
59
2582.501
PAVEMENT MESSAGE (RT ARROW) EPDXY
EACH
$123.08
2
2
0
$246.16
60
12582.50214"
SOLID LINE YELLOW -PAINT
LIN FT
$0.28
1150
0
0
$0.00
61
2582.502
4" BROKEN LINE YELLOW -PAINT
LIN FT
$0.28
290
0
0
$0.00
62
2582.502
4" DOUBLE SOLID LINE YELLOW -PAINT
LIN FT
$0.56
1450
809
0
$453.04
63
2582.502
4" SOLID LINE WHITE -EPDXY
LIN FT
$1.04
1400
367
0
$381.68
64
2582.502
4" SOLID LINE YELLOW -EPDXY
LIN FT
$1.04
1150
0
0
$0.00
65
2582.502
4" BROKEN LINE YELLOW -EPDXY
LIN FT
$1.04
290
0
0
$0.00
66
12582.50214"
DOUBLE SOLID LINE YELLOW -EPDXY
LIN FT
$2.09
400
120
0
$250.80
67
12582.50214"
SOLID LINE WHITE -PAINT
LIN FT
$0.27
34001
1167
0
$315.09
68
12582.5031
CROSSWALK MARKING -EPDXY
SQ FT
$3.751
9001
414
0
$1,552.50
Totals For Section BASE BID:
$321,170.90
Change Order 1
69 12104.601 1 REMOVE DUCT BANK ILUMPSLIMI $531.301 11 11 1
$531.30
Totals For Change Order 1:
$531.30
Change Order 2
70 12105.6011 TOPSOIL PLACEMENT I LUMP SUM 1 $3,386.49 11 1 1
$3,386.49
Totals For Change Order 2:
$3,386.49
Change Order 3
71
12563.6131
FLASHER TYPE A (LOW INTENSITY)
JUNITDAY
1 $0.501
1921
1921
192
$96.00
72
12564.6021
SALVAGE AND REINSTALL SIGN
I EACH
1 $192.001
31
31
3
$576.00
Totals For Change Order 3:
$672.00
Project Totals:
$325,760.69
Page 3 of 4
Pay Voucher
Project Payment Status
Owner: City of Rosemount
Client Project No.: CP 421
Client Contract No.:
Project No.: 01668 -85
Contractor: Max Steininger, Inc.
Contract Chanaes
No.
Type
Date
Description
Amount
C01
Change Order
9/2/2010
Remove conduit at 143rd Street.
$531.30
CO2
Change Order
9/2/2010
Topsoil placement.
$3,386.49
CO3
Change Order
9/23/2010
Salvage and reinstall three signs at 145th Street.
$672.00
Change Order Totals: 1
$4,589.79
Pavment Summary
No.
From
Date
To Date
Payment
Total
Payment
Retainage
Per
Payment
Total
Retainage
Total
Payment +
Retainage
Work
Certified Per
Payment
Total Work
Certified
1
5/17/2010
5/31/2010
$137,033.78
$137,033.78
$7,212.30
$7,212.30
$144,246.08
$144,246.08
$144,246.08
2
6/1/2010
6/30/2010
$160,882.66
$297,916.44
$8,467.51
$15,679.81
$313,596.25
$169,350.17
$313,596.25
3 &
FINAL
7/1/2010
9/30/2010
$27,844.25
$325,760.69
($15,679.81)
$0.00
$325,760.69
$12,164.44
$325,760.69
Payment Totals:
$325,760.69
$0.00
$325,760.69
$325,760.69
Project Summary
Material On Hand:
Total Payment to Date:
Total Retainage:
Total Amount Earned:
Page 4 of 4
$0.00
$325,760.69 Original Contract:
$0.00 Contract Changes:
$325,760.69 Revised Contract:
$330,132.03
$4,589.79
$334,721.82