HomeMy WebLinkAbout6.j. Change Order #4 - Akron Ave Trunk Utility & Railroad Improvements, City Project #4174014OSEMOUNT EXECUTIVE SUMMARY CITY COUNCIL City Council Meeting: October 5, 2010 AGENDA ITEM: Change Order #4 — Akron Avenue Trunk AGENDA SECTION: Utility & Railroad Improvements, City Consent Project #417 PREPARED BY: Andrew J. Brotzler, PE, Director of P AGENDA NO. �. Works /City Engineer ' ATTACHMENTS: Change Order #4; Map APPROVED BY: RECOMMENDED ACTION: Motion to Approve Change Order #4 for the Akron Avenue Trunk Utility & Railroad Improvements, City Project #417. BACKGROUND: Attached for Council consideration is Change Order #4 for the Akron Avenue Trunk Utility & Railroad Improvements, City Project #417. This change order represents the addition of work requested by the Metropolitan Council Environmental Services (MCES) to extend a maintenance ladder within the sanitary sewer diversion structure, No. 6004, installed as part of the project. This change results in a net increase of $2,271.54 to the contract for a revised contract amount of $3,172,651.57. Funding for Change Order No. 4 is to be 100% MCES. SUMMARY: Staff recommends Council approval of Change Order No. 4 for the Akron Avenue Trunk Utility & Railroad Improvements, City Project #417. G: \ENGPROJ \417 \20101005 CC ChangeOrder 4.doc WSB & Associates, Inc. Infrastructure ■ Engineering ■ Planning ■ Construction 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763 5414800 September 24, 2010 Mr. Andy Brotzler, PE City Engineer City of Rosemount 2875-145 th Street West Rosemount, MN 55068 Re: Change Order No. 4 Akron Avenue Trunk Utility and Railroad Improvements City of Rosemount Project No. 417 WSB Project No. 1668 -30 Dear Mr. Brotzler: Please find enclosed Change Order No. 4 (in triplicate) for the above - referenced project. The change order reflects a net increase to the contract in the amount of $2,271.54 for a revised contract total of $3,172,651.57. This change reflects additional work requested by the Metropolitan Council Environmental Services (MCES) to extend a maintenance ladder within the sanitary sewer diversion structure, No. 6004, installed as part of the project. Funding for Change Order No. 4 is to be 100% MCES. If the attached meets with your approval, please sign and process. If you have any questions or comments regarding the enclosed, please contact me at 763 - 287 -7173. Thank you. Sincerely, WSB & Associates, Inc. Mo an D , PE Projec ager Enclosures cc: Cindy Domiden, City of Rosemount Joseph LaTour, LaTour Construction, Inc. tsf Honorable Mayor and City Council October 28, 2008 Page 2 Minneapolis ■ St. Cloud Equal Opportunity Employer C:\Documents and Settings \pco\Local Settings \Temporary Internet Files \OLKD6\LTR CO 4 CTY -a brotzler- 091510.doc CHANGE ORDER NO.4 AKRON AVENUE TRUNK UTILITY AND 9/15/2010 RAILROAD IMPROVEMENTS CITY ROSEMOUNT PROJECT NO. 417 WSB PROJECT NO. 1668 -30 OWNER: CONTRACTOR: CITY OF ROSEMOUNT LATOUR CONSTRUCTION, INC. 2875 - 145TH STREET WEST 2134 CO. RD. 8 NW ROSEMOUNT, MN 55068 MAPLE LAKE, MN 55358 YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION: EXTENSION OF SANITARY SEWER MANHOLE LADDER IN MANHOLE NO. 6004 IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME: ORIGINAL CONTRACT PRICE: $3,102,181.66 ORIGINAL CONTRACT TIME: 9/1/2009 PREVIOUS CHANGE ORDERS: CHANGE ORDER 1 $22,448.37 NET CHANGE FROM PREVIOUS CHANGE ORDERS: NONE PREVIOUS CHANGE ORDERS: CHANGE ORDER 2 ($638,891.55) CONTRACT TIME PRIOR TO THIS CHANGE ORDER: 6/5/2010 PREVIOUS CHANGE ORDERS: CHANGE ORDER 3 $684,641.55 CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $3,170,380.03 NET INCREASE WITH CHANGE ORDER: 0 DAYS NET INCREASE OF THIS CHANGE ORDER: $2,271.54 CONTRACT TIME WITH APPROVED CHANGE ORDERS 6/5/2010 CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $3,172,651.57 RECOMMENDED BY: APPROVED BY: MORG DAWL Y, PE, P JECT M AGER CONTRACTOR SIGNATURE WSB &ASSOCIATES, INC. LATOUR CONSTRUCTION, INC. ENGINEER CONTRACTOR APPROVED BY: CITY ENGINEER CITY ADMINISTRATOR DATE OF COUNCIL ACTION K W1668- 301AdminlConstruction AdminlChange orderslChange Order #411668.30 Change Order 4CO-1 CHANGE ORDER NO. 4 DETAIL AKRON AVENUE TRUNK UTILITY AND RAILROAD IMPROVEMENTS CITY ROSEMOUNT PROJECT NO. 417 WSB PROJECT NO. 1668 -30 9/1512010 ADDED ITEMS ITEM EXTENDED NO. MAT. NO. DESCRIPTION NOTE QTY UNIT PRICE AMOUNT 304 2503.601 SANITARY SEWER MANHOLE LADDER EXTENSION 1 LUMP SUM $2,271.54 $2,271.54 TOTAL ADDITION TO ORIGINAL CONTRACT AMOUNT $2,271.54 K:101668- 301.AdminlConstruction AdminlChange orderslChange Order 0111668 -30 Change Order ICO1 Detail N 0 750 1,500 3,000 4,500 6,000 W�E Feet c December 200 T: /GIS /City /Maps/Departmental Maps/Engineedng/Chris/CR73 Utility Locate.mxd