HomeMy WebLinkAbout2.a. Former St. Joseph's FacilitiesAGENDA ITEM: Former St. Joseph's Facilities
AGENDA SECTION:
Discussion
PREPARED BY: Dan Schultz, Parks and Recreation
Director
AGENDA NO. 2.A.
ATTACHMENTS: None
APPROVED BY: VA
RECOMMENDED ACTION: Discussion only
4 ROSEMOUNT
CITY COUNCIL
City Council Work Session: August 13, 2008
EXECUTIVE SUMMARY
DISCUSSION
At the City Council work session on July 15, 2008, a topic of discussion was the former St. Joseph's
School and Church facilities. Staff shared with the Council a number of potential courses of action that
should be considered with preparing the buildings for future use. The potential courses of action included:
Make improvements to be compliant with handicapped accessibility requirements and use the church.
Make improvements to be compliant with handicapped accessibility requirements and use the church and
portions of school.
Hold referendum in the fall of 2008 and make all improvements to upgrade church as proposed in spring
2008 referendum.
Hold referendum in 2010 or later; make all improvements to upgrade church as proposed in spring 2008
referendum.
Hold referendum in 2010 or later, make all improvements to upgrade church and increase referendum
request to include improvements to school or demolition of school.
Work with private developer for development on a portion of the site, while maintaining the church for
public purpose.
Staff also shared with the Council that the deadline to have a question on the General Election ballot this
November was September 12.
The City Council directed staff to obtain preliminary numbers on what it would cost to make the gym,
cafeteria, kitchen and first floor classrooms accessible and available for public use. A request was also
made to break down the estimate for improvements to the Church by individual project rather than by
construction material, and to update the 2005 cost assumptions for the improvements to the entire schooL
Quinn Hutson from CNH Architects will be at the meeting to discuss any technical questions regarding
the possible improvements.
At the time of copying the packets the cost estimates were not yet complete. Staff expects the estimates to
be ready on August 11 or 12 Staff will forward the estimates to the City Council as soon as we receive
them.
AUGUST 1 3, 2008
FORMER ST. JOSEPH'S CHURCH AND
SCHOOL FACILITY
ROSEMOUNT, MN
COST ANALYSIS STUDY UPDATE
CHURCH BID PACKAGES
SCHOOL UPGRADES
7300 WEST 147TH STREET, SUITE #504 APPLE VALLEY, MN 55124-7580
PH: (952) 431-4433
Former St. Joseph's
Church Facility v\r ill
accomodate a vide
variety of community
functions including
performing arts. visual
arts, meeting space, fa-
cility rental and private
events.
The Former St. Joseph's Church Facility project renovates the former St. Joseph's Church and
School buildings with the primary goal to upgrade it to meet current building code requirements for
a general multi purpose assembly space. This study updates the previous reports provided in 2005
and 2007 with cost estimates updated to current construction cost levels. There are also breakouts
of the church remodeling into several different bid packages focusing on specific upgrade elements.
In addition, the study evaluates the minimum upgrades to the main floor of the school building
that would be required before a change in occupancy from school to an assembly use would be al-
lowed.
The description of code, accessibility and basic comfort described in the previous two reports may
be referenced to describe the work represented in this update. A new schematic design floor plan
for the school is attached at the end of this study.
AUGUST 1 3, 20 ❑8
Revised Schematic Design Budget Estimate for Former St. Joseph's Church Facility
The cost estimate below is the result of a detailed material and labor take-off done by our cost consultant,
Professional Project Management (PPM) and updated to a 2009 construction start. The cost estimate
includes a design contingency of 10% in order to cover the additional information and possible fine tun-
ing that will occur between these schematic design level drawings and the final construction plans and
specifications. The actual start date selected for the project may impact the inflation rate calculation, up
or down, and therefore the final construction cost.
I recommend providing for a construction contingency of 5% after the final bids are received as included
above to cover unknown conditions that might be encountered in remodeling of a building of this age.
CSI Division Description
02000 Sitework and Demolition
03000 Concrete
04000 Masonry
05000 Metals
06000 Wood Plastics
07000 Thermal
08000 Doors, Windows Glass
09000 Finishes
10000 Specialties
11000 Equipment
12000 Furnishings
13000 Special Construction
14000 Conveying Systems
15000 Mechanical
16000 Electrical
Subtotal Direct Cost
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
Alternates:
Alt. 1 Recarpet Assembly Hall
Alt. 2 Security System
Alt. 3 Public Address/Intercom
Alt. 4 Telephone and Data System
Alt. 5 Cable Television System
AUGUST 1 3, 2008
10%
6%
10%
6.75%
5%
CSI Division Subtotal
$70,134.11
$31,355.33
$75,014.08
$9,179.60
$9,684.16
$26,258.53
$22,609.80
$43,769.79
$10,197.20
$0.00
$0.00
$0.00
$0.00
$493,108.82
$91,039.98
$882,351.39
$88,235.14
$58,235.19
$1,028,821.72
$102,882.17
$76,320.00
$51441.09
$1,259,464.98
Total:
$18,982.36
$17,836.14
$16,152.70
$29,925.06
$4,666.80
Exterior Front Entry Bid Package 1
Bid Package 1 includes a new entry ramp, stairs and landing to meet accessibility requirements. At the
front entry doors, new handicap operators need to be installed to improve accessibility. New sidewalks
are needed to connect to the new accessible ramp and stairs.
Bid Package 1 Subtotal
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
Bid Package 2 Subtotal
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
AUGUST 1 3, 2008
12%
10%
15%
8%
5%
Interior Ramp Stage Extension Bid Package 2
To make the stage accessible, a new ramp and handrails need to be installed in the southwest corner of
the assembly space that will also provide a connection to the existing chapel. The existing stage needs
to be extended to connect to the new accessible ramp.
12%
10%
15%
8%
5%
$52,210.30
$6,265.24
$5,847.55
$64,323.09
$9,648.46
$5,917.72
$3,216.15
$83,105.43
$10,218.40
$1,226.21
$1,144.46
$12,589.07
$1,888.36
$1,158.19
$629.45
$16,265.08
Restroom Addition Bid Package 3
A new building addition to provide new multi- fixture men's and women's restrooms is needed to fulfill
code requirements. Remodeling of the sacristy is required to provide access to the new restrooms as well
as creating a new lobby outside of the new restrooms. The north assembly room needs a few upgrades
to allow access from the assembly room to the new restrooms.
Bid Package 3 Subtotal
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
Bid Package 4 Subtotal
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
AUGUST 13, 2006
12%
10%
15%
8%
5%
Additional Church HC Accessibility Bid Package 4
To improve accessibility, some doors will require widening and new hardware. Handicap drinking foun-
tains need to be installed as well as handicap signage. New handicap parking stalls are required to meet
code accessibility requirements.
12%
10%
15%
8%
5%
$89,385.40
$10,726.25
$10,011.16
$110,122.81
$16,518.42
$10,131.30
$5,506.14
$142,278.68
$12,698.80
$1,523.86
$1,422.27
$15,644.92
$2,346.74
$1,439.33
$782.25
$20,213.24
HVAC Mechanical Addition Bid Package 5
A new building addition to the west is required to house the new mechanical units. The existing boilers
will need to be replaced. A new make -up air and air conditioning unit will need to be installed as well
as supply and return ductwork.
Bid Package 5 Subtotal
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
Fire Suppression System Bid Package 6
A new sprinkler system needs to be installed throughout the existing building as well as water service
sized for the new sprinklers. A new fire alarm and smoke detection system needs to be installed.
Bid Package 6 Subtotal
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
AUGUST 13, 2008
12%
10%
15%
8%
5%
12%
10%
15%
8%
5%
$508,325.54
$60,999.07
$56,932.46
$626,257.07
$93,938.56
$57,615.65
$31,312.85
$809,124.13
$83,494.88
$10,019.39
$9,351.43
$102,865.69
$15,429.85
$9,463.64
$5,143.28
$132,902.47
Summary of Church Facility Bid Packages
The previous six bid packages cover most of the planned remodeling but a few miscellaneous items are
only included in the overall project cost estimate. These items include items such as new lighting in the
entry, patching and painting former water leaks and similar miscellaneous improvements identified with
the City staff on the previous study. As shown below these items represent $212,623.81 in additional
costs.
It is important also to point out that due to economies of scale and general conditions efficiencies, the
church facility remodeling will cost up to $157,000 more if done in separate packages. This additional
cost will likely be even more when calculating in inflation between the 2009 start date shown on the
updated costs and the actual date when the remodeling is undertaken. While breaking the project into
smaller steps provides flexibility, there are trade -offs to consider.
Total Project All 6 Bid Packages
Total Not Included Bid Packages
Total Project Cost
AUGUST 13, 2008
$1,203,889.02
$212,623.81
$1,416,512.84
Revised Schematic Design Budget Estimate for Former St. Joseph's School Facility
The following table is the updated costs to remodel the entire school building based on the 2005 build-
ing analysis work scopes but update for a 2009 construction start. These numbers represent preliminary
budget costs and unlike the church cost estimates, are not unit cost take -offs. Consequently, this estimate
is intended for ballpark comparisons only.
,School Building Overall Ouantity Unit Cost Total Cost
Exterior
Replace rusting steel lintels over windows 22 $1,823 $40,106
Tuckpoint and rebuild brick around NW
corner of building 1 $6,078 $6,078
Replace BUR roofs, flashings upgrade
insulation to meet code 13,500 $13.98 $188,730
Structure
(No work lintels noted above) 0 $0 $0
HVAC
New ventilation cooling system 1 $486,202 $486,202
Temperature control system 1 $42,543 $42,543
Boiler replacement (upgrade size of church
boiler to serve both) 1 $36,465 $36,465
Plumbing
Fire suppression system 21,600 $2.73 $58,968
(Bathrooms will be included below under
accessibility) 0 $0 $0
Electrical
Fire alarm, lighting, panel board upgrades 1 $182,326 $182,326
Interior Condition Codes
Replace corridor doors with fire rated openings 25 $1,823 $45,575
Enclose and fire rate stairwell 2 $9,724 $19,448
Fire rate corridor wall penetrations 1 $4,862 $4,862
Accessibility
Add three -stop elevator and enclosure 1 $109,396 $109,396
Add single -use HC restroom one per gender 2 $14,586 $29,172
Upgrade knob handles not already replaced
above 20 $608 $12,160
Miscellaneous HC upgrades 1 $6,078 $6,078
Subtotal $1,268,109
Contingency 15% $190,216
Softcosts Equipment
Design Fees (A/E) estimated 10% $145,832
FFE equipment Unknown
Minimum Total Church Gathering Area Upgrade $1,604,157
AUGUST 1 3, 2008
St. Joseph's School First Floor Upgrade
As an option instead of remodeling the entire school building, the main floor remodeling shown in this
option only addresses the minimum handicap accessibility and code updates necessitated by the change
in occupancy. This work is shown on the attached sheet SCO1 and provides upgrades to three class-
rooms, cafeteria, gymnasium and restrooms only. These upgrades include the following items:
Handicap access down to the cafeteria and gymnasium rooms
Replacement and widening of all room entrance doors smaller than 3' -0" wide
Addition of through -wall make -up air units in each occupied space
Addition of fire suppression system in first floor only
Upgrade of exit and emergency lighting systems
First Floor Subtotal
General Conditions
Overhead Profit
Total w/o Contingency
Design Contingency
A &E Fee
Construction Contingency
Total Project Cost
AUGUST 1 3, 2008
12%
10%
15%
8%
5%
$142,576.94
$17,109.23
$15,968.62
$175,654.79
$26,348.22
$16,160.24
$8,782.74
$226,945.99
I C
0
Z
JD lil
S...
a a
an
a
IF I
i
i
i
I.
5
i.
1
DI
I
h
a of
f
I
i1
r
¶i
V
Mt 1.1
6
If 110
fill
o f 1
it
i !hill 11
I
a. 1 i
51.731.0W HMO AD .11.10(J.00 0
4
g
u
�ooyog ydesor is
1.00S
z
0
°U
1-
N
z
Z
0
0
0
LL
0
z
4
T
T
N
7
129 -V
•1
i 11 a
4 I 1 e
aF i 1S
1
11 111 1 1 1
a
3A
1 9
1
l l f'
3 4 t
d A 1 1i
I
s
st
s
ti
a
Z.
ii
_s,
3 E}l
pie
Miff 2R V C#
iliiiill
n
ng
1
Eg i
1,
Ili =g
II
f
1.
gt
Pig
uu
O.
i
sa
f
i
1 I
p
i i
n n
II
1 1
N
1f -T 1' -012
ilial
11' -V
1e -1-
2T -11•
10-V
2d -10
C -1 12
e
189 -V
N
4 _1
Z
0
0
u 0
0
cn
Z
0 i
0
Z
E Wtevil 2009 Prcrystla \08021 Al -SI Joaepf,.giied- IryaciAmnm
Blll/20004D1',12 PM
SC
21
a
St. Joseph School
RosemouM,Minnesde
7300WEST11211181REET 8111E 6012FPUE VNIEY,MI0I24.7910 (BIm4314131
00:11 MF SVONARCHITECIS.INC.
i t Build It They Will Come!
Rosemount Area Arts Council's
Recommendations for
"Old St. Joseph's Campus"
8/»/2008
4 Recommendations (Part 2)
Begin programming as soon as possible
MAC is eager to help with programming
Build a ground -swell of demand for the
arts in Rosemount
Priming the Pump
Citizens will first see what is presented;
Then they will begin to have ideas of
what they would like to experience;
The arts community will hear about the
facility and come knocking to exhibit or
perform at our facility
G
-Proms
I4,20U
./4
Recommendations (Part 1)
Keep tab the church the school
Make necessary, but modest improvements
Church beginning in 2008 (lighting, sound, sealing, ADA
compliance, exhibit web)
School beginning in 2009 (To be determined)
consult with people who real, understand arts and theatre
facfities
Make all improvements yea high quality to attract
both patrons and artistsfperfonners
Recommendations (Part 3)
Wait for a referendum until:
citizens have experienced quality arts
programming;
citizens are demanding more;
A survey is done to show what people are
willing to contribute
Improvements in the economic news
4 Why an Arts Center?
The arts serve all ages:
Toddies
children
Teems
aaby- boomers
seniors
Those with disabilities
The arts bring people 1 across ages groups,
income bradcets, ethnic cultural badcgrounds
The arts are compatible with the library
Why an Arts Center?
The arts are compliment our schools
Compliments already robust arts programs
in K -12, Community Ed and DCTC
Provides access to cultural experiences that
may not otherwise be available to children
A number of teachers have already
expressed interest in becoming involved
4 Why an Arts Center?
Volunteerism civic pride
1 1 What Can Be: Theatre
Proscenium theatre
Black Box theatre
Dramas, musicals, dinner theatre,
orchestra, jazz, recitals, dance, poetry
slams, open mike comedy, rehearsal
space
Many groups are searching for a home
Why an Arts Center?
The arts are good for business:
Helps attract more "creative class" citizens
and knowledge, providing a better
employment pool for future employers
Helps attract more customers to the
downtown area for retailers and
restaurants
Builds a sense of place and community in
Rosemount; another source of civic pride
.111Why an Arts Center?
People
Schools
Business
4 What Can Be: Exhibit Arts
Painting, sculpture, photography,
needle arts, graphic arts, etc
Artists' studios
2
1 1 What Can Be: Film
Screenwriters workshops
Directors workshops
Short Film Festival
Possible tie to sister city in Ireland?
RAAC
Wants to provide programming
We believe that in 3 years, the
Rosemount Arts Center can be pretty
well booked each week
Possible service contract
Our relationship with the City?
To be determined
Message
his is the home of the arts in Rosemount.
Stop talking about it as a multi- purpose
center. Multi- purpose center sends no dear
message. People don't know what to
expect. They dont know whether it will be
good for them as individuals. No one can
"get behind" a multi purpose center.
What Can Be: Education
Classes in an array of arts
Children's Programming
Disability Programming
Senior's Programming
Writer's workshops
Dance studio
Leaving a Legacy
This center will be an organic, growing,
exciting place for generations to come
Please make this community a better,
more enjoyable place to live for many
years to come.
3