HomeMy WebLinkAbout6.d. Change Order #1, 2 & 3 - Connemara Tower Painting, City Project #411 4ROSEt vLOLINJf EXECUTIVE SUMMARY
CITY COUNCIL
City Council Meeting: January 15, 2008
AGENDA ITEM: Change Order #1, 2 3- Connemara AGENDA SECTION:
Tower Painting, City Project #411 Consent
PREPARED BY: Andrew J. Brotzler, PE, City Engineer AGENDA NO. 4/4.
ATTACHMENTS: Change Order #1, 2 3; KLM APPROVED BY:
Engineering Letter of Recommendation
RECOMMENDED ACTION: Motion to Approve Change Order #1, 2 3 forth
Connemara Tower Painting, City Project #411.
ISSUE:
KLM Engineering is recommending three change orders to this project for a net reduction in contract
price from $494,500 to $487,157.12.
BACKGROUND:
The following summarizes the proposed contract changes:
Change Order 1: This change order was originally approved by Council on May 15, 2007. The original
change order added $3,000 to the contract to allow additional venting to be installed during blasting and
painting operations. The work covered by this change order was never completed. Therefore, Change
Order 1 should be reversed.
Change Order 2: This change order is a deduction of $7,842.88 for three electric bills paid by the City.
Change Order 3: This change order is to replace the damaged pipe -style safety climb device with a more
common cable -style safety device. This change order is an increase of $3,500.
SUMMARY:
Staff recommends that Council approves Change Order #1, 2 3 for the Connemara Tower Painting,
City Project #411.
G: ENGPROJ 411 \ChangeOrder 1 -2 -3CC 1- 15-08. doc
KLM ..ENCINEERIN INC.
P.O. Box 897.3394 Lake Elmo Ave. N. Lake Elmo, MN 55042
(651) 773 -5111 Fax (651) 773 -5222
December 26, 2007
Mr. Andrew Brotzler
City of Rosemount
2875 145 Street West
Rosemount, MN 55068
RE: Detailed Explanation of the Change Orders No. 1, 2, 3 for the Connemara
Tower Located in Rosemount, Minnesota.
City Project No. 411
KLM Project No. MN1829
Dear Mr. Brotzler:
Change Order No 1: This $3,500.00 change order was to install two (2) additional roof
ventilation manways to provide additional ventilation during blasting, painting,
and curing of the tower during reconditioning.
By the time the change order was approved, OPC had completed the interior wet
painting and had removed the rigging needed to weld, blast, and paint the interior
wet portions of the manways. Therefore, change order no. 1 for $3,500.00 was
never completed.
Change Order No. 2: This change order is a deduction from the contract amount by
$7,842.88 for three (3) electric bills paid by the city.
1 Master Electric Co. replaced water damaged Tight switches, three (3)
globes (interior lights), and two (2) circuit breakers and photo cells for
$675.65.
2 The city's electrician installed two (2) outlets on the tower for
$4,625.39.
3 Sieman's Water Technologies replaced the Micrologix 1200 PLC
damaged by dust and water. The cost was $2,541.84.
The total cost for change order no. 2 was a deduction of $7,842.88.
Change Order No. 3: This change order was a recommendation from KLM to change
the damaged pipe style safety climb device to a DBI /SALA ladder safety system
cable style safety device commonly installed on water towers. Total cost for
labor and materials was $3,500.00.
If you have any questions please call me at 651.773.5111.
Sincerely,
KLM Engineering, Inc.
.3(4‘.
Kelly C. Mu Ihtrfn
Project Supervisor
KCM /ms
CC: MN 1829 Office File
C:Ms\Kelly\MN 1829RosemountChangeOrderExplanationConnemaral2- 26- 07.doc
CITY OF ROSEMOUNT, MN
CONTRACT CHANGE ORDER NO. 1
Revision 11 -28 -07
Project: Connemara Tower (KLM Project No. MN1829)
(City) Project No: 411
Change Order No.: 1
Date: May 3, 2007
Contractor: Odland Protective Coatings
The additional authorized work performed by the contractor, contained herein, shall be made in
full to the Contract Documents for the project.
Connemara Tower. To install 1 or 2 additional roof ventilations to provide adequate
ventilation during blasting, painting, curing, and for Confined Space Entry.
Total Amount of Change Order No. 1 $3,000.00 (2 additional roof ventilations)
Per Odland Protective Coatings Change Order No. 1 is to be DELETED work not done.
CHANGE ORDER NO. 1 SUMMARY
ORIGINAL CONTRACT AMOUNT $491,500.00
CONTRACT CHANGE ORDER NO. 1
AMENDED CONTRACT $491,500.00
APPROVALS:
ACCEPTED BY: Odland Protective Coatings, Inc.
By: l 1 0 itle: T f e 3 i L Date: 1 °1
RECOMMENDED BY: KLM Engineering, Inc.
D S ;h 7
By: z rf (Title: t Date: 1 L.
APPROVED BY:
By: Title: Date:
C:\ls\2007 projects\MN1829 Rosemount \Change Order No. 1 revised 11- 28- 07.doc
CITY OF ROSEMOUNT, MN
CONTRACT CHANGE ORDER NO. 2
Project: Connemara Tower (KLM Project No. MN1829)
(City) Project No: 411
Change Order No.: 2
Date: November 28, 2007
Contractor: Odland Protective Coatings
The additional authorized work performed by the contractor, contained herein, shall be made in
full to the Contract Documents for the project.
Connemara Tower. Reduce contract amount by $7,842.88 total of three (3) electrical
contractor invoices paid by the City of Rosemount.
CHANGE ORDER NO. 2 SUMMARY
ORIGINAL CONTRACT AMOUNT $491,500.00
CONTRACT CHANGE ORDER NO. 1
CONTRACT CHANGE ORDER NO. 2 7,842.88)
AMENDED CONTRACT $483,657.12
APPROVALS:
ACCEPTED BY: Odland Protective Coatings, Inc.
By f/Y2 T itle: /e5, Date: f) -0 v 7
RECOMMENDED BY: KLM Engineering, Inc.
B i '-(_Title: 1 J t'C Date: I d d 7
Y
APPROVED BY:
By: Title: Date:
C:\1s\2007 projects\MN1829 Rosemount \Change Order No. 2 11- 28- 07.doc
CITY OF ROSEMOUNT, MN
CONTRACT CHANGE ORDER NO. 3
Project: Connemara Tower (KLM Project No. MN1829)
(City) Project No: 411
Change Order No.: 3
Date: November 28, 2007
Contractor: Odland Protective Coatings
The additional authorized work performed by the contractor, contained herein, shall be made in
full to the Contract Documents for the project.
Connemara Tower. Provide all equipment and labor to install a DBUSALA ladder safety
system (flexible cable type) $3,500.00
CHANGE ORDER NO. 3 SUMMARY
ORIGINAL CONTRACT AMOUNT $491,500.00
CONTRACT CHANGE ORDER NO. 1
CONTRACT CHANGE ORDER NO. 2 7,842.88)
CONTRACT CHANGE ORDER NO. 3 3,500.00
AMENDED CONTRACT $487,157.12
APPROVALS:
ACCEPTED BY: Odland Protective Coatings, Inc.
By: t_.c',.� Title: ®'"z6'..1: Date:
RECOMMENDED BY: KLM Engineering, Inc.
'f title:
By Gs- ,c��� 1 t� Date: d c
APPROVED BY:
By: Title: Date: