HomeMy WebLinkAbout6.n. Change Order #1 - Rosemount Village 2nd Addition Street & Utility Improvements, C.P. 378CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: October 5, 2004
AGENDA ITEM: Change Order #1- Rosewood Village 2 "
AGENDA SECTION:
Addition Street & Utilit Improvem City Project #378
Consent
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
*JTff'v5
N
ATTACHMENTS: Change Order #1
APPROVED BY:
RECOMMENDED ACTION: MOTION TO APPROVE CHANGE ORDER 4 IN THE
AMOUNT OF 46 ADDITIONAL DAYS ADDED TO THE CONTRACT FOR THE
ROSEWOOD VILLAGE ,2 ADDITION STREET AND UTILITY IMPROVEMENTS,
CITY PROJECT #378 AND AUTHORIZE THE NECESSARY SIGNATURES.
ACTION:
BACKGROUND:
Change Order #1, Rosewood Village 2 nd Addition Street and Utility Improvements, City
Project #378 includes an amendment to the contract completion date for the project.
The change in the contract completion date is due to project delays by the developer,
Progress Land Company.
SUMMARY:
Staff requests Council approval of Change Order #1.
t
ROSEWOOD VILLAGE 2ND ADDITION
STREET AND UTILITY CONSTRUCTION AND APPURTENANT WORK
CITY OF ROSEMOUNT, MN
CITY PROJECT NO. 378
OWNER
City of Rosemount
2875 145th Street West
Rosemount, MN 55068
CONTRA CTOR:
September 24, 2004
WSB PROJECT NO. 1562 -00
Erickson Construction, Inc.
13616 Pleasant Lane
Burnsville, MN 55337
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
THE ORIGINAL SUBSTANTIAL COMPLETION DATE OF OCTOBER 15, 2004 IS BEING CHANGED TO DECEMBER 1, 2004.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE,
OR FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
$443,123.59
ORIGINAL CONTRACT TIME:
10/15/2004
PREVIOUS CHANGE ORDERS: N/A
$0.00
. NET CHANGE FROM PREVIOUS CHANGE ORDERS:
N/A
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
$443,123.59
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
10/15/2004
NET INCREASE /DECREASE OF THIS CHANGE ORDER:
$0.00
NET INCREASE OF CHANGE ORDER:
46 Days
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$443,123.59
CONTRACT TIME WITH APPROVED CHANGE ORDERS
12/1/2004
RECOMMENDED BY:
ANTHON A. ADERHOLD, P.E.
WSB & ASSOCIATES, INC.
ENGINEER
APPROVED BY:
ERICKSON CONSTRUCTION, INC.
CONTRACTOR
APPROVED BY:
CITY ENGINEER
CITY ADMINISTRATOR
DATE OF COUNCIL ACTION
co -1co -1