HomeMy WebLinkAbout6.e. Change Order #1- Biscayne Pointe 5th Addition Street & Utility Improvements, City Project 367_ t
CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: October 19, 2003
AGENDA ITEM: Change Order #1 — Biscayne Pointe 5
AGENDA SECTION:
Addition Street & Utility Improvements, City Project #367
Consent
PREPARED BY: Andrew J. Brotzler, P.E., Pity Engineer
T MT6
ATTACHMENTS: Change Order #1
APPROVED BY:
RECOMMENDED ACTION: MOTION TO APPROVE CHANGE ORDER # FOR
BISCAYNE POINTE 5 th ADDITION STREET AND UTILITY IMPROVEMENTS, CITY
PROJECT #367 AND AUTHORIZE NECESSARY SIGNATURES.
COUNCIL ACTION:
BACKGROUND:
Change Order #1, Biscayne Pointe 5 th Addition Street & Utility Improvements, includes
the addition of '$24,940.50 to the original contract amount of $533,919.88 for a new
total of $558,860.38. The additional work included under Change Order #1 was
grading work of the boulevards for small utilities and regrading of the streets. All work
done was at the request of the developer, Heritage Development.
`SUMMARY:
Staff requests - Council approval of this item.
BISCAYNE POINTE 5TH ADDITION
OCTOBER 7, 2004
STREET AND UTILITY CONSTRUCTION AND APPURTENANT WORK
7/15/2004
CITY OF ROSEMOUNT, MN
$0.00
CITY PROJECT NO. 367
WSB PROJECT NO. 1514 -00
OWNER:
CONTRACTOR:
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
City of Rosemount
Contractors Edge, Inc.
2875145th Street West
16511 - 563 Avenue
Rosemount, MN 55068
Good Thunder, MN 56037
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
ITEM 66 - ADDITIONAL GRADING IN BOULEVARDS FOR SMALL UTILITIES
ITEM 67 - REGRADE SITEWORK IN STREETS AND PILE EXCESS
ITEM 68 - REMOBILIZATION
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE
OR FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
$533,919.88
ORIGINAL CONTRACT TIME:
7/15/2004
PREVIOUS CHANGE ORDERS: N/A
$0.00
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
N/A
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
$533,919.88
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
7/1512004
NET INCREASE OF THIS CHANGE ORDER:
$24,940.50
NET INCREASE OF CHANGE ORDER:
N/A
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$558,860.38
CONTRACT TIME WITH APPROVED CHANGE ORDERS 7/15/2004
RECOMMENDED BY: APPROVED BY:
ANTHONY A. ADERHOLD, P.E.
WSB & ASSOCIATES, INC. CONTRACTORS EDGE, INC.
ENGINEER CONTRACTOR
APPROVED BY:
CITY ENGINEER
CITY ADMINISTRATOR
DATE OF COUNCIL ACTION
ca1ca1
CO -1CO1 Detafl
a
BISCAYNE POINTE 5TH ADDITION
STREET AND UTILITY CONSTRUCTION AND APPURTENANT WORK
CITY OF ROSEMOUNT, MN
CITY PROJECT NO. 367
ADDITIONAL QUANTITIES
Extended
Item No. Description
Unit
Quantity
Price
Amount
66 NEW ADDITIONAL GRADING WORK
LUMP SUM
1
$10,785.50
$10,785.50
67 NEW REGRADE SITEWORK AND PILE EXCESS
LUMP SUM
1
$11,460.00
$11,460.00
68 2021.601 REMOBILIZATION
LUMP SUM
1
$2,695.00
$2,695.00
TOTAL ADDITIONAL QUANTITIES
$24,940.50
TOTAL INCREASE CHANGE ORDER NO. 1
$24, 940.50