HomeMy WebLinkAbout6.h. Change Order #1 - Keegan Lake Outlet, City Project #343CITY OF ROSEMOUNT
r EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: May 18, 2004
AGENDA ITEM:
Change Order #1, Keegan Lake Outlet, City
AGENDA SECTION:
Project #343
Consent
PREPARED BY:
Andrew J. Brotzler, P.E., City Engineer F►"
D
ATTACHMENTS:
Change Order #1
APPROVED BY
RECOMMENDED
ACTION: MOTION TO APPROVE CHANGE ORDER #1 FOR
KEEGAN LAKE OUTLET, CITY PROJECT #343, AND AUTHORIZE THE NECESSARY
SIGNATURES.
ACTION:
ISSUE:.
The Change Order reflects additional traffic control required by Dakota County on
County Road 38 and for the removal and replacement of a barb wire fence.
BACKGROUND:
Keegan Lake Outlet, City Project #343, when completed will provide an outlet for
Keegan Lake to ultimately provide a stabilized normal water level and prevent flooding
of adjacent properties.
SUMMARY:
Staff is recommending that the Council make a motion to approve Change Order #1 in
the amount of $12,063 for the Keegan Lake Outlet, City Project #343.
I
KEEGAN LAKE OUTLET STORM SEWER CONSTRUCTION
May 12, 2004
CITY OF ROSEMOUNT
CITY PROJECT NO. 343A
WSB PROJECT NO. 1498 -00
OWNER:
CONTRACTOR:
S. M. Hentges & Sons, Inc.
City of Rosemount
650 Quaker Avenue, Suite 200
2875145th Street West
P.O. Box 69
Rosemount, MN 55068
Jordan, MN 55352
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY,
SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE: $292,194.89
ORIGINAL CONTRACT TIME:
5/30/2004
PREVIOUS CHANGE ORDERS: N/A $0.00
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
NIA
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $292,194.89
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
5/30/2004
NET INCREASE OF THIS CHANGE ORDER: $12,063.00
NET INCREASE OF CHANGE ORDER:
N/A
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $304,257.89
CONTRACT TIME WITH APPROVED CHANGE ORDERS
5/30/2004
RECOMMENDED BY:
APPROVED BY:
MARK A. ERICHSON, P.E., PROJECT MANAGER
WSB & ASSOCIATES, INC. S. M. HENTGES & SONS, INC.
ENGINEER CONTRACTOR
APPROVED BY:
CITY ENGINEER CITY ADMINISTRATOR
DATE OF COUNCIL ACTION
C:IDocuments and SettingslcadV-ocal SettingslTemporary Internet Filesl0LK7DiC0- 1.xIsC0-1
KEEGAN LAKE OUTLET STORM SEWER CONSTRUCTION
May 12, 2004
CITY OF ROSEMOUNT
CITY PROJECT NO. 343A
ADDITIONAL QUANTITIES
Extended
Item No. Description
Qty
Unit
Price
Amount
38 2104.501 REMOVE BARB WIRE FENCE
960
LIN FT
$2.00
$1,920.00
39 2557.52 TEMPORARY FENCE
875
LIN FT
$6.00
$5,250.00
40 2557.603 BARB WIRE FENCE
955
LIN FT
$4.00
$3,820.00
41 25634.6 ADDITIONAL TRAFFIC CONTROL
1
LUMP SUM
$1,073.00
$1,073.00
TOTAL ADDITIONAL QUANTITIES
$12,063.00
TOTAL INCREASE CHANGE ORDER NO. 1
$12,063.00