HomeMy WebLinkAbout6.j. Receive Bids/Award Contract for Connemara Trail Overpass, City Project #379CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
City Council Meeting Date: December 7, 2004
AGENDA ITEM: Receive Bids /Award Contract for
AGENDA SECTION:
Connemara Trail Overpass,
Consent
C Project #379
PREPARED BY: Andrew J. Brotzler, P.E.
City Engineer Wz
AGEN
06
J
ATTACHMENTS: None 7 APPROVED
BY:
RECOMMENDED ACTION: Motion to adopt a resolution receiving bids and awarding
contract for the Connemara Trail Overpass, City Project #379
ACTION:
BACKGROUND:
On Friday, December 3, 2004, bids for the referenced project were received and read aloud
publicly. The bids are being reviewed for accuracy before a recommendation can be made.
This project includes the construction of a bridge spanning over the UP rail system,
connecting Connemara Trail, located in the Meadows of Bloomfield Development on the
north side of the railroad, to Connemara Trail located in the Bloomfield 7 Addition
development on the south side of the railroad. All costs associated with the project will be
funded by the advancement of state aid monies.
SUMMARY:
The tabulation of.bidders, resolution and letter of recommendation to award will be provided
at the Council meeting.
6 , J�
Honorable Mayor and City Council
City of Rosemount
2875 145 Street West
Rosemount. MN 55068
Re: Connemara Trail Bridge (STA. 72 +00.00 to STA. 76 +50.00)
Street and Bridge Construction and Appurtenant Work
City of Rosemount Project No. 379
S.A.P. No. 208 - 104 -04
Bridge No. 19557
WSB Project No. 1561 -00
Dear Mayor and Council Members:
Bids were received for the above - referenced project on Friday, December 3, 2004, and were
opened and read aloud. A total of 6 bids were received. The bids were checked for mathematical
accuracy and tabulated. The Engineer's Estimate was $1,581,408.60. Please find enclosed the
bid tabulation indicating the low bidder as Lunda Construction Co., Black River Falls, WI, in the
amount of $1,491,272.45.
r We recommend that the City Council consider these bids and award a contract to Lunda
RIZI Construction Co., based on the results of the bids received.
Sincerely,
WSB & Associates, Inc.
Anthony A. Aderhold, P.E.
Project Manager
4150 Olson,;
Memorial H,g my Lunda Construction Co.
Suite 300 Cindy Dorniden, City of Rosemount
763•�4I h�� FAX
C.-Documents and SettingslaaalLocal Settings) Temporary Ini —t FilesDLKMRecommendation LTR.doc
Minneapolis • St. Cloud Equal Opportunity Employer
PROJECT:
Connemara Trail Bridge (STA. 72 +00.00 to STA. 76 +50.00)
Street and Bridge Construction and Appurtenant Work
City of Rosemount Project No. 379
S.A.P. No. 208 - 104 -04
Bridge No. 19557
LOCATION:
Rosemount, MN
WSB PROJECT NO.:
1561 -00
Bids Opened: December 3, 2004 at 10:00 a.m.
Engineer's Opinion of Cost
$1,581,408.60
I hereby certify that this is a true and correct tabulation of the bids as received on December 3, 2004.
Anthony A. Aderhold, P
, Project Manager
BID TAB SUMMARY
Contractor
Addendum Rec'd.
Bid Security
Total Bid
1
Lunda Construction Co. (Black River Falls, WI)
n/a
X
$1,491,272.45
2
Minnowa Construction, Inc.
n/a
X
$1,493,357.00
3
Robert R. Schroeder Construction, Inc.
n/a
X
$1,537,907.20
4
Redstone Construction Co., Inc.
n/a
X
$1,583,801.52
5
Edward Kraemer & Sons, Inc.
n/a
X
$1,592,678.20
6
Ames Construction, Inc.
n/a
X
$1,662,204.60
Engineer's Opinion of Cost
$1,581,408.60
I hereby certify that this is a true and correct tabulation of the bids as received on December 3, 2004.
Anthony A. Aderhold, P
, Project Manager
BID TAB SUMMARY
WSB
& .4ssaciatea. Inc.
Project Name: RSMT - Connemara Trail Bridge
Client: City of Rosemount
Bid Opening: 12/3/2004 10:00
WSB
Bid Tabulation
Contract No.:
Project No.: 01561 -00
Owner: Minneapolis
12/6/2004
Item No.
Item
Units
Quantity
Unit. Price Total Price
Unit Price Total Price
Unil Price Total Price
Unit Price Total Price
Project: 01561 00 - RSMT - Connemara Trail Bridge
Engineers Material Table
L unda Construction Co.
Minnowa Construction, Inc.
Robert R. Schroeder Constr., ,
Inc.
SCHEDULE A
1
2021.501
MOBILIZATION
LUMP SUM
1
$60,000.00
$60,000.00
$65,000.00
$65,000.00
$45,000.00
$45,000.00
$129,265.00
$129,265.00
2
2104.501
REMOVE CURB AND GUTTER
LIN FT
20
$6.50
$130.00
$2.00
$40.00
$10.00
$200.00
$10.00
$200.00
3
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
19
$5.00
$95.00
$2.00
$38.00
$5.00
$95.00
$10.00
$190.00
4
2104.511
SAWING CONCRETE PAVEMENT (FULL DEPTH)
LIN FT
9
$7.00
$63.00
$3.00
$27.00
$10.00
$90.00
$5.00
$45.00
5
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
84
$4.00
$336.00
$3.00
$252.00
$5.00
$420.00
$5.00
$420.00
6
2105.501
COMMON EXCAVATION (P)
CU YD
1100
$3.50
$3,850.00
$4.00
$4,400.00
$2.00
$2,200.00
$5.00
$5,500.00
7
2105.522
SELECT GRANULAR BORROW (CV)
CU YD
1100
$11.00
$12,100.00
$9.00
$9,900.001
$8.00
$8,800.00
$12.00
$13,200.00
8
2105.523
COMMON BORROW (CV)
CU YD
20400
$6.50
$132,600.00
$7.50
$153,000.001
$6.00
$122,400.00
$7.15
$145,860.00
9
2211.501
AGGREGATE BASE CLASS 5
TON
770
$12.00
$9,240.00
$15.00
$11,550.00
$15.00
$11,550.00
$15.00
$11,550.00
10
2301.553
BRIDGE APPROACH PANELS
SQ YD
302.22
$110.00
$33,244.20
$60.00
$18,133.20
$100.00
$30,222.00
$65.00
$19,644.30
11
2350.501
TYPE MV 3 WEARING COURSE MIXTURE (C)
TON
131
$42.00
$5,502.00
$53.00
$6,943.00
$53.00
$6,943.00
$54.00
$7,074.00
12
2350.502
TYPE MV 3 NON WEARING COURSE MIXTURE (C)
TON
262
$38.00
$9,956.00
$49.00
$12,838.00
$49.00
$12,838.00
$47.00
$12,314.00
13
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
60
$2.50
$150.00
$5.00
$300.00
$5.00
$300.00
$5.00
$300.00
14
2401.501
STRUCTURAL CONCRETE (1A43)
CU YD
83
$225.00
$18,675.00
$310.00
$25,730.00
$350.001
$29,050.00
$220.00
$18,260.00
15
2401.501
STRUCTURAL CONCRETE (3Y43)
CU YD
447
$300.00
$134,100.00
$345.00
$154,215.00
$400,001
$178,800.00
$285.00
$127,395.00
16
2401.512
BRIDGE SLAB CONCRETE (3Y36)
SQ FT
14700
$17.00
$249,900.00
$8.00
$117,600.00
$9.00
$132,300.00
$9.00
$132,300.00
17
2401.513
TYPE P -1 RAILING CONCRETE (3Y46)
LIN FT
462
$60.00
$27,720.00
$38.00
$17,556.00
$45.00
$20,790.00
$54.00
$24,948.00
18
2401.515
SIDEWALK CONCRETE (3Y46)
SQ FT
4170
$10.25
$42,742.50
$5.00
$20,850.00
$7.00
$29,190.00
$9.00
$37,530.00
19
2401.541
REINFORCEMENT BARS
POUND
5013
$0.70
$3,509.10
$0.85
$4,261.05
$1.00
$5,013.00
$1.00
$5,013.00
20
2401.541
REINFORCEMENT BARS (EPDXY COATED)
POUND
134312
$0.90
$120,880.80
$0.85
$114,165.20
$1.00
$134,312.00
$1.00
$134,312.00
21
2401.601
STRUCTURE EXCAVATION
LUMP SUM
1
$18,000.00
$18,000.00
$12,000.00
$12,000.00
$12,000.001
$12,000.00
$12,000.00
$12,000.00
22
2401.601
SLOPE PREPARATION
LUMP SUM
1
$7,500.00
$7,500.00
$2,500.00
$2,500.00
$3,000.001
$3,000.00
$3,500.00
$3,500.00
23
2402.59
ELASTOMERIC BEARING PAD TYPE 1
EACH
18
$200.00
$3,600.00
$85.00
$1,530.00
$70.001
$1,260.00
$400.00
$7,200.00
24
2402.595
BEARING ASSEMBLY
EACH
36
$680.00
$24,480.00
$750.00
$27,000.00
$500.00
$18,000.00
$400.00
$14,400.00
25
2402.603
STRUCTURAL TUBE RAILING WITH FENCE DES T -3
LIN FT
460
$120.00
$55,200.00
$95.001
$43,700.00
$140.00
$64,400.00
$80.00
$36,800.00
26
2404.501
CONCRETE WEARING COURSE (3U17A)
SQ FT
13000
$2.00
$26,000.00
$2.00
$26,000.00
$3.35
$43,550.00
$3.85
$50,050.00
27
2405.502
PRESTRESSED CONCRETE BEAMS 36 "MOD
LIN FT
1882
$120.00
$225,840.00
$140.00
$263,480.00
$140.00
$263,480.00
$148.00
$278,536.00
28
2405.511
DIAPHRAGMS FOR TYPE 36 "MOD PRESTRESSED BEAMS
LIN FT
448
$55.00
$24,640.00
$80.00
$35,840.00
$40.00
$17,920.00
$46.00
$20,608.00
29
2452.507
C -I -P CONCRETE PILING DELIVERED 12"
LIN FT
3960
$19.50
$77,220.00
$24.00
$95,040.00
$24.00
$95,040.00
$19.00
$75,240.00
30
2452.508
C -I -P CONCRETE PILING DRIVEN 12"
LIN FT
3960
$3.10
$12,276.00
$1.00
$3,960.00
$2.00
$7,920.00
$4.00
$15,840.00
31
2452.519
C -1 -P CONCRETE TEST PILE 70 FT LONG 12"
EACH
8
$6,500.00
$52,000.00
$8,500.00
$68,000.00
$5,000.00
$40,000.00
$4,000.00
$32,000.00
32
2452.602
PILE POINTS 12"
EACH
74
$50.00
$3,700.00
$250.00
$18,500.00
$150.00
$11,100.00
$125.00
$9,250.00
Page 1 of 4
Item No.
Item
Units
Quantity
JUnit Price JTotal Price
Unil Pr ce Total Price
Unit Price Total Price
Unit Price Total Price
Project: 01561 -00 - RSMT - Connemara Trail Bridge
Engineers Material Table
Lunda Construction Co.
Minnowa Construction, Inc.
Robert R. Schroeder Constr.,
Inc.
33
2514.501 CONCRETE SLOPE PAVING
SQ YD
971
$95.00 $92,245.00
$60.00 $58,260.00
$45.00 $43,695.00
$54.00 $52,434.00
34
2521.501 4" CONCRETE WALK
SQ FT
11401
$3.50 $3,990.00
$3.45 $3,933.00.
$4.50 $5,130.00
$2.40 $2,736.00
35
2521.604
2" BITUMINOUS PATH
SQ YD
187
$13.00
$2,431.00
$12.50
$2,337.50
$22.00
$4,114.00
$6.00
$1,122.00
36
2531.501
CONCRETE CURB & GUTTER DESIGN 8618
LIN FT
410
$11.50
$4,715.00
$13.45
$5,514.50
$14.00
$5,740.001
$16.00
$6,560.00
37
2545.501
ELECTRIC LIGHT SYSTEM
LUMP SUM
1
$15,000.00
$15,000.00
$15,230.00
$15,230.00
$16,000.00
$16,000.001
$12,000.00
$12,000.00
38
2545.509
CONDUIT SYSTEM 2" (LIGHTING)
LUMP SUM
1
$4,500.00
$4,500.00
$4,836.00
$4,836.00
$5,000.00
$5,000.001
$12,000.00
$12,000.00
39
2545.509
CONDUIT SYSTEM 1 -112" (FUTURE)
LUMP SUM
1
$4,200.00
$4,200.00
$3,922.00
$3,922.00
$4,000.00
$4,000.00
$7,000.00
$7,000.00
40
2554.501
ITRAFFIC BARRIER DESIGN SPECIAL
LIN FT
50
$30.00
$1,500.00
$37.95
$1,897.50
$38.00
$1,900.00
$38.00
$1,900.00
41
2554.521
ANCHORAGE ASSEMBLY -PLATE BEAM
EACH
4
$260.00
$1,040.00
$250.00
$1,000.00
$250.00
$1,000.00
$250.00
$1,000.00
42
2554.523
END TREATMENT - ENERGY ABSORBING TERMINAL
EACH
2
$2,750.00
$5,500.00
$2,165.00
$4,330.00
$2,165.00
$4,330.00
$2,250.00
$4,500.00
43
2557.501
WIRE FENCE DESIGN 6OV -9322
LIN FT
300
$32.00
$9,600.00
$19.65
$5,895.00
$23.00
$6,900.00
$23.00
$6,900.00
44
2563.601
TRAFFIC CONTROL
LUMP SUM
1
$1,500.00
$1,500.00
$2,000.00
$2,000.00
$2,500.00
$2,500.00
$5,000.00
$5,000.00
45
2563.61
FLAG PERSON
HOUR
250
$35.00
$8,750.00
$85.00
$21,250.00
$75.00
$18,750.00
$60.00
$15,000.00
46
2564.603
4" SOLID LINE WHITE -PAINT
LIN FT
900
$0.15
$135.00
$0.68
$612.00
$0.28
$252.00
$0.25
$225.00
4 7
2564.603
4" DOUBLE SOLID LINE YELLOW -PAINT
LIN FT
450
$0.30
$135.00
$0.84
$378.00
$0.56
$252.00
$0.50
$225.00
48
2564.603
4" SOLID LINE WHITE -EPDXY
LIN FT
1100
$0.25
$275.00
$1.20
$1,320.00
$1.20
$1,320.00
$0.50
$550.00
49
2564.603
4" DOUBLE SOLID LINE YELLOW -EPDXY
LIN FT
550
$0.60
$330.00
$2.40
$1,320.00
$2.40
$1,320.00
$1.00
$550.00
50
2572.501
TEMPORARY FENCE
LIN FT
500
$2.85
$1,425.00
$1.60
$800.00
$1.60
$800.00
$7.50
$3,750.00
51
2573.502
SILT FENCE, TYPE MACHINE SLICED
LIN FT
1500
$2.85
$4,275.00
$1.50
$2,250.00
$1.50
$2,250.00
$1.80
$2,700.00
52
2575.501
SEEDING
ACRE
13
$1,150.00
$3,795.00
$200.00
$660.00
$200.00
$660.00
$295.00
$973.50
53
2575.502
SEED MIXTURE 25B
POUND
165
$7.10
$1,171.50
$24.50
$4,042.501
$25.00
$4,125.00
$20.00
$3,300.00
54
2575.505
SODDING TYPE SALT RESISTANT
SQ YD
900
$3.50
$3,150.00
$3.50
$3,150.00
$3.50
$3,150.00
$4.00
$3,600.00
55
2575.511
MULCH MATERIAL TYPE 1
TON
2.92
$110.00
$321.20
$200.00
$584.00
$200.00
$584.00
$295.00
$861.40
56
2575.519
DISK ANCHORING
ACRE
1.46
$80.00
$116.80
$250.00
$365.00
$250.00
$365.00
$100.00
$146.00
57
2575.523
EROSION CONTROL BLANKETS CATEGORY 3
SQ YD
8950
$1.75
$15,662.50
$1.20
$10,740.00
$1.20
$10,740.00
$1.30
$11,635.00
58
1 2575.532 ICOMMERCIAL
FERTILIZER ANALYSIS 22 -5 -10 IPOUND
990
$0.40
$396.00
$0.30
$297.00
$0.30
$297.00
$0.50
$495.00
Total SCHEDULE
A:
$1,581,408.60
$1,491,272.45
$1,493,357.00
$1,537,907.20
Total SCHEDULE A: $1,581,408.60 1 $1,491,272.45 $1,493,357.00 $1,537,907.20
Totals for Project 01561 -00
$1,581,408.60
$1,491,272.45
$1,493,357.00
$1,537,907.20
of Estimate for Project 01561 -00
-5.70 %
-5.57%1
2.75%
Page 2 of 4
Item No. I Item Units Quantity Unit Price Total Price
I Unit Price ITotal Price
jUnit Price Total Price jUnit Price ITotal Price
Project: 01561 -00 - RSMT - Connemara Trail Bridge I Engineers Material Table
lRedstone Construction
Edward Kraemer & Sons, Inc. I Ames Construction
SCHEDULE A
1 -
2
2021.501
MOBILIZATION
LUMP SUM
1
$60,000.00
$60,000.00
$69,899.11
$69,899.11
$77,200.00
$77,200.00
$84,000.00
$84,000.00
2104.501
REMOVE CURB AND GUTTER
LIN FT
20
$6.50
$130.00
$5.00
$100.00
$10.00
$200.00
$30.00
$600.00
3
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
19
$5.00
$95.00
$10.00
$190.00
$10.001
$190.00
$25.00
$475.00
4
2104.511
SAWING CONCRETE PAVEMENT (FULL DEPTH)
LIN FT
9
$7.00
$63.00
$10.00
$90.00
$10.00
$90.00
$40.00
5
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
84
$4.00
$336.00
$5.00
$420.00
$5.00
$420.00
$360.00
6
2105.501
COMMON EXCAVATION (P)
CU YD
1100
$3.50
$3,850.00
$5.50
$6,050.00
$5.00
$5,500.00
$6.00
$12.00
$504.00
$13,200.00
7
2105.522
SELECT GRANULAR BORROW (CV)
CU YD
1100
$11.00
$12,100,001
$17.00
$18,700.00
$12.00
$13,200.00
$15.00
$16,500.00
8
2105.523
COMMON BORROW (CV)
CU YD
20400
$650
$132,600.00
$6.50
$132,600.00
$7.15
$145,860.00
$5.75
$117,300.00
9
2211.501
AGGREGATE BASE CLASS 5
TON
770
$12.00
$9,240.00
$15.75
$12,127.50
$15.00
$11,550.00
$15.00
$11,550.00
10
2301.553
BRIDGE APPROACH PANELS
SQ YD
302.22
$110.00
$33,244.20
$98.86
$29,877.47
$110.00
$33,244.20
$105.00
$31,73110
11
2350.501
TYPE MV 3 WEARING COURSE MIXTURE (C)
TON
131
$42.00
$5,502.00
$54.25
$7,106.75
$53.00
$6,943.00
$56.00
$7,336.00
12
2350.502
TYPE MV 3 NON WEARING COURSE MIXTURE (C)
TON
262
$38.00
$9,956.00
$47.25
$12,379.50
$49.00
$12,838.00
$52.00
13
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
60
$2.50
$150.00
$5.00
$300.00
$5.00
$300.00
$10.00
$13,624.00
14
2401.501
STRUCTURAL CONCRETE (tA43)
CU YD
83
$225.00
$18,675.00
$319.16
$26,490.28
$425.00
$35,275.00
$425.00
$600.00
$35,275.00
16
2401.501
STRUCTURAL CONCRETE (3Y43)
CU YD
447
$300.00
$134,100.00
$398.79
$178,259.13
$450.00
$201,150.00
$525.00
$234,675.00
16
2401.512
BRIDGE SLAB CONCRETE (3Y36)
SQ FT
14700
$17.00
$249,900.00
$9.68
$142,296.00
$8.75
$128,625.00
$10.00
$147,000.00
17
2401.513
TYPE P -1 RAILING CONCRETE (3Y46)
LIN FT
462
$60.00
$27,720.00
$62.42
$28,838.04
$39.15
$18,087.30
$56.00
$25,872.00
18
2401.515
SIDEWALK CONCRETE (3Y46)
SQ FT
4170
$10.25
$42,742.50
$9.87
$41,157.90
$6.00
$25,020.00
$6.25
$26,062.50
1 9
2401.541
REINFORCEMENT BARS
POUND
5013
$0.70
$3,509.10
$0.88
$4,411.44
$0.90
$4,511.70
$1.00
$5,013.00
20
2401.541
REINFORCEMENT BARS (EPDXY COATED)
POUND
134312
$0.90
$120,880.80
$0.90
$120,880.80
$1.00
$134,312.00
$1.00
$134,312.00
21
22
2401.601
STRUCTURE EXCAVATION
LUMP SUM
1
$18,000.00
$18,000.00
$11,688.79
$11,688.79
$12,150.00
$12,150.00
$25,000.00
$25,000.00
23
2401.601
SLOPE PREPARATION
LUMP SUM
1
$7,500.00
$7,500.00
$6,937.36
$6,937.36
$1,250.00
$1,250.00
$5,000.00
$5,000.00
2402.59
ELASTOMERIC BEARING PAD TYPE 1
EACH
18
$200.00
$3,600.00
$43.19
$777.42
$100.00
$1,800.00
$60.00
$1,080.00
24
25
2402.595
BEARING ASSEMBLY
EACH
36
$680.00
$24,480.00
$452.52
$16,290.72
$550.00
$19,800.00
$455.00
$16,380.00
2402.603
STRUCTURAL TUBE RAILING WITH FENCE DES T -3
LIN FT
460
$120.00
$55,200.00
$128.53
$59,123.80
$125.00
$57,500.00
$130.00
$59,800.00
26
2404.501
CONCRETE WEARING COURSE (3U17A)
SQ FT
13000
$2.00
$26,000.00
$3.44
$44,720.00
$3.35
$43,550.00
$3.50
$45,500.00
27
2405.502
PRESTRESSED CONCRETE BEAMS 36 "MOD
LIN FT
1882
$120.00
$225,840.001
$128.34
$241,535.88
$131.50
$247,483.00
$130.00
$244,660.00
28
2405.511
DIAPHRAGMS FOR TYPE 36 "MOD PRESTRESSED BEAMS
LIN FT
448
$55.00
$24,640.00
$28.41
$12,727.68
$30.00
$13,440.00
$32.00
29
2452.507
C -I -P CONCRETE PILING DELIVERED 12
LIN FT
3960
$19.50
$77,220.00
$21.73
$86,050.80
$32.00
$126,720.00
$25.00
$14,336.00
30
2452.508
C-I-P CONCRETE PILING DRIVEN 12"
LIN FT
3960
$3.10
$12,276.00
$1.12
$4,435.20
$1.00
$3,960.00
$1.00
$99,000.00
31
2452.519
C -I -P CONCRETE TEST PILE 70 FT LONG 12"
EACH
8
$6,500.00
$52,000.00
$7,030.77
$56,246.16
$5,000.00
$40,000.00
$5,500.00
$3,960.00
$44,000.00
32
2452.602
PILE POINTS 12 "
EACH
74
$50.00
$3,700.00
$143.77
$10,638.98
$170.00
$12,580.00
$300.00
$22,200.00
33
2514.501
CONCRETE SLOPE PAVING
SQ YO
971
$95.00
$92,245.00
$89.86
$87,254.06
$70.00
$67,970.00
$67.00
$65,057.00
34
2521.501
4" CONCRETE WALK
SQ FT
1140
$3.50
$3,990.00
$4.45
$5,073.00
$3.85
$438900
$3.85
$4,389.00
35
2521.604
2" BITUMINOUS PATH
SQ YD
187
$13.00
$2,431.00
$19.75
$3,693.25
$18.00
, .$3,366.00
$12.50
$2,337.50
36
2531.501
CONCRETE CURB & GUTTER DESIGN 8618
LIN FT
410
$11.50
$4,715.00
$14.25
$5,842.50
$16.00
$6,560.00
$20.00
$8,200.00
37
2545.501
ELECTRIC LIGHT SYSTEM
LUMP SUM
1
$15,000.00
$15,000.00
$16,595.00
$16,595.00
$15,230.00
$15,230.00
$15,500.00
$15,500.00
38
2545.509
CONDUIT SYSTEM 2" (LIGHTING)
LUMP SUM
1
$4,500.00
$4,500.00
$9,250.00
$9,250.00
$4,836.00
$4,836.00
$5,000.00
$5,000.00
39
2545.509
CONDUIT SYSTEM 1 -1/2" (FUTURE)
LUMP SUM
1
$4,200.00
$4,200.00
$7,100.00
$7,100.00
$3,922.00
$3,922.00
$4,000.00
$4,000.00
40
2554.501
TRAFFIC BARRIER DESIGN SPECIAL
LIN FT
50
$30.00
$1,500.00
$37.95
$1,897.50
$37.95
$1,897.50
$40.00
41
2554.521
ANCHORAGE ASSEMBLY -PLATE BEAM
EACH
4
$260.00
$1,040.00
$250.00
$1,000.00
$250.00
$1,000.00
$250.00
$2,000.00
42
2554.523
END TREATMENT - ENERGY ABSORBING TERMINAL
EACH
2
$2,750.00
$5,500.00
$2,165.00
$4,330.00
$2,165.00
$4,330.00
$2,200.00
$1,000.00
$4,400.00
43
2557.501
WIRE FENCE DESIGN 60V -9322
LIN FT
300
$32.00
$9,600.00
$23.00
$6,900.00
$19.65
$5,895.00
$25.00
$7,500.00
Page 3 of 4
Ilem No.
Item
Project: 01561 -00 - RSMT - Connemara Trail Bridge
Units
Quanti
44
2563.601
TRAFFIC CONTROL
45
2563.61
FLAG PERSON
LUMP SUM
46
2564.603
4" SOLID LINE WHITE -PAINT
HOUR
;
47
2564.603
4" DOUBLE SOLID LINE YELLOW -PAINT
LIN FT
48
2564.603
4" SOLID LINE WHITE -EPDXY
LIN FT
C
49
2564.603
4" DOUBLE SOLID LINE YELLOW -EPDXY
LIN FT
11
50
2572.501
TEMPORARY FENCE
LIN FT
51
2573.502
SILT FENCE, TYPE MACHINE SLICED
LIN FT
5
52
2575.501
SEEDING
LIN FT
15
53
2575.502
SEED MIXTURE 25B
ACRE
54
2575.505
SODDING TYPE SALT RESISTANT
POUND
1
55
2575.511
MULCH MATERIAL TYPE 1
SCI YD
9
56
2575.519
DISK ANCHORING
TON
2.
57
2575.523
EROSION CONTROL BLANKETS CATEGORY 3
ACRE
1.
58
2575.532
COMMERCIAL FERTILIZER ANALYSIS 22 -5
SQ YD
89
-10
POUND
9'
Total SCHEDULE
Total SCHEDULE A:
Totals for Project 01561 -00
of Estimate for Project 01561 -00
I hereby certify that this is an exact reproduction of bids received
Certified By: = / Registration No.
Date:
Unit Price ITotal Price Unit Price Total Price Unit Price Total Price Unil Price Total Price
Engineers Material Table Redstone Construction
$1,500.00 Edward Kraemer &Sons, Inc.
Ames Construction
$1,500.00 $1.00 $1.00 $1.00 $1.00 $10,000.00 $10,000.00
$35.00 $8,750.00 $100.00 $25,000.00 $50.00 $12,500.00 $51.00 $12,750.00
$0.15 $135.00 $0.68 $612.00 $0.28 $252.00 $2.00
$0.30 $135.00 $1,800.Oc
$0.84 $378.00 $0.56 $252.00 $2.00
$0.25 $275.00 $1.20 $1,320.00 $1.20 $900.00
$1,320.00
$0.60 $330.00 $2.40 $2,200.00
$1,320.00 $2.40 $1,320.00 $3.00 $1,650.00
$1 0
$2.85 $1,425.00 $1.60 $800.00 $1.60 $800.00 $2,pp
$2.85 $4,275.00 $1,000.00
.5 $2,250.00 $1.50 $2,250.00 $2.00
$1,150.00 $3,795.00 $200.00 $660.00 $3,000.00 $200.00 $660.00 $200.00
$7.10 $ 660 . 00
$1,171.50 $24.50 $4,042.50 $24.50 $4,042.50 $25.00 $4,125.00
$3.50 $3,150.00 $3.50 $3,150.00 $3.50 $3,150.00
$110.00 $321.20 $200.00 $5.00 $4,500.00
$584.00 $200.00 $584.00 $200.00 $584.00'
$80.00 $116.80 $250.00 $365.00 $250.00 $365.00
$250.00 $365.00
$1.75 $15,662.50 $1.20 $10,740.00 $1.20 $10,740.00 $1.35 $12,082.50
$0.40 $396.00 $0.30 $297.00 $0.30 $297.00 $0.30
$1,581,408.60 $297.00
$1,583,801.52 $1,592,678.20 $1,662,204.60
$1,581,408.60 $1,592,678.20
$1,662,204.60
$1,583,801.52
$1,581,408.60 $1,583,801.52 $1,592,678.20
$1,662,204.60
0.71
5.11
Page 4 of 4
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2004 —
A RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT
FOR THE CONNEMARA TRAIL OVERPASS
CITY PROJECT NO. 379
BE IT FURTHER RESOLVED, by the City Council of the City of Rosemount, Minnesota, as follows:
1. All bids on construction of the Connemara Trail Overpass have been received and
tabulated.
2. The bid of Lunda Construction Company in the amount of $1,491,272.45 for the
construction of said improvements is in accordance with the plans and specifications and
advertisement for bids and is the lowest responsible bid and shall be and hereby is
accepted.
3. The Mayor and Clerk are hereby authorized and directed to enter into a contract with said
bidder for the construction of said improvements for and on behalf of the City of
Rosemount.
4. The City Clerk is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposit of all successful bidder and the next
two lowest bidders shall be retained until a contract has been executed.
5. Award of the bid is contingent on the determination by the City Administrator that all
necessary rights -of -entry or easements by deed or dedication have been secured for
construction of the improvements.
ADOPTED this 7 th day of December, 2004.
William H. Droste, Mayor
ATTEST:
Linda Jentink, City Clerk
Motion by: Seconded by:
Voted in favor:
Voted against: