EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: March 16, 2004
Attached please find a copy of the Feasibility Report for the Biscayne Pointe North Street and
Utility Improvements, City Project #370. This report addresses the construction of streets and
utilities within the Biscayne Pointe North Addition, along with the estimated cost and proposed
funding.
The developer,- Giles Properties, has deposited the required funds with the City. The proposed -
improvements will begin in the Spring of 2004 with substantial completion by Fall of 2004.
AGENDA ITEM: Receive Feasibility Report/Order
AGENDA SECTION:
Project/Authorize Plans & Specifications — Biscayne Pointe North
Consent
Street & Utility Improvements, City Project #370
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
A 0•
1 6 r,
ATTACHMENTS: Resolution
APPROVED BY:
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2004 -
A RESOLUTION RECEIVING THE FEASIBILITY REPORT, ORDERING
THE PROJECT AND AUTHORIZING THE PREPARATION OF PLANS AND
SPECIFICATIONS FOR BISCAYNE POINTE NORTH STREET AND UTILITY
IMPROVMENTS
CITY PROJECT #370
WHEREAS, pursuant to the resolutions of the Council adopted on February 3, 2004, a report has been
prepared by the City Engineer with reference to the improvement of Biscayne Pointe North Street and Utility
Improvements City Project #370, and this report was received by the Council on March 16, 2004, and
WHEREAS, the report provides information regarding whether the proposed project is necessary, cost-
effective, and feasible.
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF ROSEMOUNT,
MINNESOTA:
1. Such improvements are hereby ordered as proposed in the Feasibility Report for the project.
2. The City Engineer is hereby ordered to prepare plans and specifications for the making of such
improvements.
ADOPTED this 16th day of March, 2004.
William H. Droste, Mayor
ATTEST:
Linda Jentink, City Clerk
Motion by: Seconded by:
Voted in favor:
Voted against:
1
March 16, 2004
Biscayne Pointe North
Street and Utility Improvements
and Appurtenant Work
Prepared for:
City Project Number: 370
WSB Project No. 1577 -00
4150 Olson Memorial Highway, Suite 300
Minneapolis, MN 55422 (763) 541 -4800
FEASIBILITY REPORT
BISCAYNE POINTE NORTH
STREET AND UTILITY IMPROVEMENTS
AND APPURTENANT WORK
CITY PROJECT NO. 370
FOR THE
CITY OF ROSEMOUNT, MINNESOTA
March 16, 2004
Prepared By:
WSB & Associates, Inc.
4150 Olson Memorial Highway, Suite 300
Minneapolis, MN 55422
(763) 541 -4800
(763) 541 -1700 (Fax)
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
WSB Project No. 1577 -00
WS B
I & Associates, Inc.
I March 16, 2004
Honorable Mayor and City Council
City of Rosemount
'
2875 145 Street West
Rosemount, MN 55068 -4997
Re: Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
'
City Project No. 370
WSB Project No. 1577 -00
Dear Mayor and City Council Members:
Transmitted herewith is a feasibility report which addresses street and utility improvements
for the Biscayne Pointe North Addition.
■
We would be happy to discuss this report with you at your convenience. Please do not
hesitate to contact me at (763) 541 -4800 if you have any questions regarding this report.
'
Sincerely,
Y
WSB & Associates, Inc.
Mark A. Erichson, P.E.
Project Manager
'
Enclosure
js
'
4150 Olson'
Memorial Highway
' Suite 300
Minneapolis
Minnesota
55422
763.541.4800 r
' 763. 541.1700 FAX
Minneapolis • St. Cloud • Equal Opportunity Employer
CERTIFICATION
I hereby certify that this plan, specification or report was prepared by
me or under my direct supervision and that I am a duly Licensed
Professional Engineer under the laws of the State of Minnesota.
Mark A. Erichson, P.E.
Date: March 16, 2004 Lic. No. 40886
Date: March 16, 2004 Lic. No. 19133
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
WSB Project No. 1577 -00
Quality Control Review by:
TABLE OF CONTENTS
TITLE SHEET
LETTER OF TRANSMITTAL
CERTIFICATION SHEET
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY ......................................................................... ..............................1
2 INTRODUCTION ....................................................................................... ..............................2
2.1 Authorization .................................................................................... ..............................2
2.2
Scope ................................................................................................ ..............................2
' 2.3
Data Available .................................................................................. ..............................2
3 GENERAL
BACKGROUND .................................................................... ..............................3
' 3.1
Project Location (Figure 1) .............................................................. ..............................3
3.2
Existing Conditions .......................................................................... ..............................3
4. PROPOSED IMPROVEMENTS .............................................................. ..............................4
4.1
Street (Figure 3) ................................................................................ ..............................4
4.2
Storm Sewer (Figure 3) .................................................................... ..............................4
'
4.3
Watermain (Figure 2) ....................................................................... ..............................4
4.4
Sanitary Sewer (Figure 2) ................................................................. ..............................5
4.5
Sidewalk/Pathway (Figure 3) .....................................................5
'
4.6
Private Utilities / Streetlights ....................... ............................... ........ ............................ ..5
4.7
Permits /Approvals ............................................................................ ..............................5
4.8
Right -of -Way /Easements ................................................................. ..............................5
'
5 . FINANCING ............................................................................................... ..............................6
5.1
Estimated Costs ................................................................................ ..............................6
'
5.2
Funding ............................................................................................. ..............................6
6 . PROJECT SCHEDULE ............................................................................. ..............................6
7. FEASIBILITY AND RECOMMENDATION .......................................... ..............................7
' Appendix A
Figures
' Appendix B
Opinion of Probable Cost
' Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
WSB Project No. 1577 -00
1. EXECUTIVE SUMMARY
This report is written to address the proposed improvements, cost, and funding related to the
development of the new Biscayne Pointe development area known as the Biscayne Pointe North
Addition. A map showing the project location is shown on Figures 1 and 2.
The proposed improvements include the construction of city streets that include concrete curb
' and gutter and 5 -foot concrete sidewalks. The proposed City street construction includes the
extension of Birchwood Avenue from the north side of Biscayne Pointe 5 th Addition, north to
County Road 38 (135 Street West), a stub street to the west and a short cul -de -sac to the north
off of the stub street. Utility improvements include the construction of lateral sanitary sewer,
watermain, and storm sewer systems to serve 22 single family residential lots.
The estimated project cost for the street and utility improvements of the Biscayne Pointe North
Addition is $604,300. The estimate includes 10% contingency costs and 30% indirect costs.
The entire project cost will be financed by the developer, Giles Properties, Inc.
The majority of the public improvements for the Biscayne Pointe North Addition, including the
first lift of bituminous pavement and all restoration items, will be completed in 2004.
This project is feasible, necessary, and cost - effective from an engineering standpoint and should
be constructed as proposed herein.
'
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
WSB Project No. 1577 -00
Page 1
L
2. INTRODUCTION
2.1 Authorization
On February 3, 2004, the Rosemount City Council authorized the preparation of a Feasibility
Report to address development - related infrastructure costs attributed to the Biscayne Pointe
North Addition Street and Utility Construction project. The Biscayne Pointe North Addition has
been designated as City Project No. 370.
The Biscayne Pointe developer, Giles Properties, Inc, will be funding all costs.
2.2 Scope
This report addresses the construction of street and utility improvements necessary for the
development of the Biscayne Pointe North residential development located south of 135 Street
West (County Road 38), north of the Biscayne Pointe 5 th Addition, and between Bacardi Avenue
and Akron Avenue (County Road 73).
' The proposed improvements include construction of streets, lateral sanitary sewer, watermain,
and storm sewer systems. Site grading will be completed privately prior to construction of the
street and utility improvements.
' 2.3 Data Available
Information and materials used in the preparation of this report include the following:
• City of Rosemount Record Plans for adjoining properties.
• City of Rosemount Stormwater Management Plan.
• City of Rosemount Topography Maps for Adjoining Properties.
• City of Rosemount Water Supply and Distribution Plan.
• Preliminary Plat information for Biscayne Pointe North prepared by John Oliver &
Associates, Inc.
• Preliminary Grading Plans for Biscayne Pointe North prepared by John Oliver &
Associates, Inc.
• Construction Plan Set for Biscayne Pointe 5 th Addition prepared by WSB & Associates, Inc.
' Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
' Rosemount, Minnesota
WSB Project No. 1577 -00
Page 2
3. GENERAL BACKGROUND
3.1 Project Location (Figure 1)
The project is a proposed 22 lot single - family residential development to be located on a 10 acre
parcel. The tract is located on the south side of 135 Street West (County Road 38) between
where Bacardi Avenue meets 135th Street West from the north and Biscayne Avenue meets it
from the south. Biscayne Pointe 5 Addition adjoins the project area to the south.
3.2 Existing Conditions
An existing farmstead in the northwest corner will be removed by the developer during site
grading operations. The area around the farmstead is lightly wooded. Most of the tract is open
field, with some fence rows along the east and west sides of the tract. The proposed
development will save most of the existing trees.
Access to the tract is presently available from 135 Street West (County Road 38), which is a
gravel road and from Birchwood Avenue, at the north tract line of Biscayne Pointe 5 Addition.
The terrain in the project area is generally sloped to the north to County Road 38 (135 Street
West) where it drains to the northwest to Keegan Lake.
The project area is currently served by the Rosemount West Water System. An 8 -inch DIP
watermain was constructed in Birchwood Avenue during construction of the Biscayne Pointe 5th
Addition.
An 8 -inch PVC sanitary sewer main was constructed in Birchwood Avenue during construction
of the Biscayne Pointe 5 Addition. It is deep enough to provide gravity service to all twenty -
two proposed lots.
A Northern Natural Gas pipeline crosses the north end of the tract along County Road 38 (135
Street West).
There are private utilities located along 135 Street West (County Road 38) on the north side of
the tract and along Birchwood Avenue in the Biscayne Pointe 5 Addition, immediately south of
the tract.
'
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
'
WSB Project No. 1577 -00
Page 3
4. PROPOSED IMPROVEMENTS
' 4.1 Street (Figure 3)
' The City streets to be constructed as a part of the Biscayne Pointe North Addition are all local
streets. They include an extension of Birchwood Avenue north from the stub road in Biscayne
Pointe 5 th Addition to County Road 38; Birdsong Path from Birchwood Avenue west to the tract
' line; and Basswood Court, a short cul -de -sac street west Birchwood Avenue.
The local streets are proposed to be constructed to a width of 32 feet face -to -face with modified
`S' (surmountable) concrete curb and gutter.
A 5 -foot sidewalk will also be constructed along the east side of Birchwood Avenue and the
south side of Birdsong Path.
The pavement section for all streets will be designed to accommodate a 9 -ton axle load, and will
consist of approximately 4 inches of bituminous and 8 inches of Class 5 aggregate base. All
streets will be constructed over a sand base.
' 4.2 Storm Sewer (Figure 3)
' The proposed storm sewer improvements include the construction of lateral storm sewer to serve
the road rights -of -way. The site storm sewer system will be designed for a 10 -year rainfall
event.
Stormwater will be routed in a manner consistent with Rosemount's Comprehensive Storm
Water Management Plan (CSMP). The proposed improvements will route almost all of the site
stormwater to a new stormwater management pond in the northeast corner of the tract. A small
area in the northwest corner will drain directly off -site to County Road 38 (135 Street West).
The storm sewer system from the development flows northwest to City Regional Stormwater
Management Pond No. 1568, immediately north of County Road 38.
4.3 Watermain (Figure 2)
Water service will be extended from the existing Rosemount Water System. The proposed
improvements include the extension of the 8 -inch DIP watermain along Birchwood Avenue
north to County Road 38 (135 Street West), out Birdsong Path to the west tract line and north
up Basswood Court. The two 8 -inch stubs to the north and the west provide for future
development and for connections for looping, when new watermain is constructed. These
proposed improvements are in accordance with the Rosemount Water Supply and Distribution
Plan.
Fire hydrants will be installed along City streets in accordance with City Standards.
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
' Rosemount, Minnesota
WSB Project No. 1577 -00
Page 4
' 4.4 Sanitary Sewer (Figure 2)
Sanitary sewer service for the Biscayne Pointe North Addition development will be provided by
extending the existing 8 -inch PVC sanitary sewer main in Birchwood Avenue.
4.5 Sidewalk/Pathway (Figure 3)
' A 5 -foot wide concrete sidewalk will be constructed along the east side of Birchwood Avenue
and along the south side of Birdsong Path.
' 4.6 Private Utilities /Streetlights
Electrical service to the development area will be provided by Xcel Energy, phone service will
be provided by Frontier Communications, and gas service by Aquila.
' Streetlights for the development will be incorporated into the project and paid for by the
developer.
' 4.7 Permits /Approvals
' The anticipated permits and approvals that will be required and the respective regulatory
agencies are listed below:
• Minnesota Department of Health (MDH) ............................ ............................... Watermain
• Minnesota Pollution Control Agency ( MPCA) ............. ............................... Sanitary Sewer
' • Metropolitan Council Environmental Services (MCES) ............................. Sanitary Sewer
• Minnesota Pollution Control Agency (MPCA).. National Pollutant Discharge Elimination
System (NPDES) General Storm -water Permit for Construction Activity (MN R110000)
• Northern Natural Gas ..... ............................... .......................Pipeline Crossing Agreements
• Dakota County Highway Department .......... Street opening permit for Birchwood Avenue
The final PP
requires lat ires a roval by the Dakota County Plat Commission and Board of
P q
Commissioners.
4.8 Right-of-Way/Easements
' The proposed street rights -of -way for all public streets and all necessary easements across the
proposed Biscayne Pointe North development will be dedicated by the developer as part of the
' final plat.
' Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
WSW Project No. 1577 -00 Page 5
5. FINANCING
5.1 Estimated Costs
The detailed Opinion of Cost can be found in Appendix B of this report. The Opinion of Cost
incorporate anticipated 2004 construction costs and include a 10% contingency factor and all
related indirect costs. The indirect costs are estimated at 30% and include legal, engineering,
administrative, and financing items. The summary of the project costs is noted as follows:
Biscayne Pointe North - Cost Summary
Total
Subtotal Schedule A - Surface Improvements
$259,320.00
Subtotal Schedule B - Sanitary Sewer
$127,700.00
Subtotal Schedule C — Watermain
$77,760.00
Subtotal Schedule D - Storm Sewer
$117,790.00
Total
$582,600.00
5.2 Funding
The funding for all public improvements will be collected from the developer, Giles Properties,
Inc. There will be no City costs or oversizing costs related to this development. The cost per lot
for the 22 lots is approximately $26,482 per lot.
6. PROJECT SCHEDULE
The proposed project schedule is as follows:
Biscavne Pointe North Street and Utilitv Improvements and Appurtenant Work
Order Feasibility Report ............................................. ............................... February 3, 2004
Receive Feasibility Report / Order Plans and Specifications ...................... March 16, 2004
Approve Plans and Specifications /Order Ad for Bids .... ............................... April 20, 2004
ReceiveBids .................................................................... ............................... May 14, 2004
Award Contract ................................................................ ............................... May 18, 2004
Begin Construction .......................................................... ............................... May 24, 2004
Substantial Completion .......................................... ............................... September 15, 2004
Final Lift of Bituminous .............................................. ............................... August 15, 2005
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
WSB Project No. 1577 -00
Page 6
7. FEASIBILITY AND RECOMMENDATION
City Project No. 370 consists of the construction of street, sanitary sewer, watermain, storm
sewer, and appurtenant work as necessary to construct the Biscayne Pointe North Addition. The
' proposed public utility improvements are in accordance with the City of Rosemount's
Comprehensive Plans.
' It is the recommendation of WSB & Associates, Inc., that City Project No. 370, Biscayne Pointe
North, is feasible, necessary, and cost - effective from an engineering standpoint. We recommend
construction of the proposed improvements as detailed in this report.
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
' Rosemount, Minnesota
WSB Project No. 7577 -00
Page 7
P-1
1
APPENDIX A
Figures
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
'
WSB Project No. 1577 -00
APPENDIX A
Figures
132ND CT W -
U
132ND ST W m
90Nq R F o
qr N
0 of "ROJECT SITE
eONy R,c_ i�\
CONNEMARA TRL
LOWER 138TH ST W
138TH ST W
UPPER 138TH ST W
139TH ST W < Q
Q 3 a 3 i a E
O 0 o m
m m m m
140TH ST W y ,
Q�
0
145TH ST W
0 2000 4000
BIRCH ST W
BELFAST CT
j E
BEEF W
BELMONT CT
o
i BEECH ST W
v
145TH ST W
P £
�ryY9't'(4 mom? � Q BAYBERRY CIR �
145TH Sl W
6
m
P1
�
O
P
BISCAVNE
WSB Project No.01577 -00 March 2, 2004
4150 Olson Memorial Highway BISCAYNE POINTE NORTH
Suite422 Street & Utility Construction
WSB Minneapolis, MN 55422
763 - 541 -4800 and Appurtenant Work FIGURE NO.
k- FAX 763 -541 -1700
ROSEMOUNT, MINNESOTA 1
M' \01577- 00\FEAS \FIG_01.dwg, Layoutl
z 96B 99�
\ 0UN 1 I 1 CFA IY V.VD
136TH STREET W
FIFTH ADDITION
X HISCA�'NE F?OINTE � � I
LEGEND
—i— PROPOSED WATERMAIN SANITARY SEWER
f <— PROPOSED SANITARY SEWER
AND WATERMAIN
0 FT 50 100
WSB Project No.01577 -00 March 2, 2004
4150 OlsonMemodalHighway BISCAYNE POINTE NORTH
Suite 300 Street & Utility Construction
WSB Minneapolis, 763 - 541 - 4800 MN 55422
Q and Appurtenant Work FIGURE NO.
—
& Aciates, Inc. FAX 763- 541
sso -1700
ROSEMOUNT, MINNESOTA 2
MA01577- 00 \FEAS \FIG_02.dwg, Layoutl
-
4
--- - - - -I II
I
/ ► -- —�
��
l 5 %
I --------- -
� / I JO
I
- - - - -� L - - - - �
L
F- - - -7 F -- F— I
W 4
I I I II II I
I'a I
1 7 II II .
° J
I
N
10 3
L
5 24 23 22 21
J
3.17
1 —
1
� 1�
— --
,
z
F-
f
F- -3RDS0
—
gPaTK-
F — — — —
I
I
L
5
4
3
1
1 CO
ECT TO EXISTING
ATERMAIN
L _ I
L — — J
L CO
�E-C T O E
ITARY SEWER
I J
L J
FIFTH ADDITION
X HISCA�'NE F?OINTE � � I
LEGEND
—i— PROPOSED WATERMAIN SANITARY SEWER
f <— PROPOSED SANITARY SEWER
AND WATERMAIN
0 FT 50 100
WSB Project No.01577 -00 March 2, 2004
4150 OlsonMemodalHighway BISCAYNE POINTE NORTH
Suite 300 Street & Utility Construction
WSB Minneapolis, 763 - 541 - 4800 MN 55422
Q and Appurtenant Work FIGURE NO.
—
& Aciates, Inc. FAX 763- 541
sso -1700
ROSEMOUNT, MINNESOTA 2
MA01577- 00 \FEAS \FIG_02.dwg, Layoutl
/ x9689. 9�
136TH STREET W
WSB Project No.01577 -00 March 2, 2004
4150 Olson Memorial Highway BISCAYNE POINTE NORTH
WSB Suite 300 Street & Utility onstruction
Minneapolis, MN 55422 y
763 - 541 -4800 and Appurtenant Work FIGURE NO.
g A FAX 763 -541 -1700
ROSEMOUNT, MINNESOTA 3
M: \01577- 00 \FEAS \FIG_03.dwg, Layoutl
— -- 12
\\�
4
I
I
/ F - - - -�
12771" 5
1
s 2 1 - - --
I N
2
N I
1
1
\
p � 1 10
1
I I
L
L-- - - - �24
—
— — — --
15
FW
II II
I
'a
N
16"
21
2
ORBS 9-P F
I
.,
II
L - - -J
I
II
2 i
II II II
I
I
�
L-
JL —_J L–
I
15 "
–1 __J
MATCH EXISTING
STREET SECTION
11
—
X
I I
BISCA�YNE F? OINTE I FIF - IH
j ADDITION �
LEGEND
PROPOSED STORM SEWER
0 PROPOSED STREET CONSTRUCTION
STORM SEWER
36" ESTIMATED STORM SEWER PIPE SIZE
AND STREET
o Fr
so
100
WSB Project No.01577 -00 March 2, 2004
4150 Olson Memorial Highway BISCAYNE POINTE NORTH
WSB Suite 300 Street & Utility onstruction
Minneapolis, MN 55422 y
763 - 541 -4800 and Appurtenant Work FIGURE NO.
g A FAX 763 -541 -1700
ROSEMOUNT, MINNESOTA 3
M: \01577- 00 \FEAS \FIG_03.dwg, Layoutl
C
I I
APPENDIX B
Opinion of Probable Cost
' Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
' Rosemount, Minnesota
WSB Project No. 1577 -00
Biscayne Pointe North
Opinion of Probable Cost Summary
Schedule A Surface Improvements $181,340.00
Schedule B Sanitary Sewer $89,300.00
Schedule C Watermain $54,380.00
Schedule D Storm Sewer $82,370.00
SUBTOTAL $407,390.00
+10%
Contingencies
SUBTOTAL $448,129.00
+30%
Indirect Cost
Biscayne Pointe North Project Total $582,567.70
Feasibility Report
Biscayne Pointe North
Street and Utility Improvements and Appurtenant Work
City Project No. 370
Rosemount, Minnesota
WSB Project No. 1577 -00
u
Opinion of Probable Cost
„7777
WSB Project: Biscayne Pointe North Design By: JDH
Project Location: City of Rosemount Checked By:
City Project No.: 370
WSB Project No.: 1577 -00 Date: 3/16/2004
Item
No.
MN/DOT
I Specification No.
Description
I
Unit
Estimated
I Total Quantity
Unit Price
Estimated Total
Cost
A. SURFACE IMPROVEMENTS
1
2021.501
MOBILIZATION
LUMP SUM
1
$8,000.00
$8,000.00
2
2104.501
REMOVE CURB AND GUTTER
LIN FT
20
$5.00
$100.00
3
2104.501
REMOVE BITUMINOUS PAVEMENT
SQ YD
7
$2.50
$17.50
4
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
30
$3.50
$105.00
5
2105.501
COMMON EXCAVATION
CU YD
150
$5.00
$750.00
6
2105.522
SELECT GRANULAR BORROW (CV)(PLACEMENT)
CU YD
4,700
$2.50
$11,750.00
7
2105.525
TOPSOIL BORROW (LV)
CU YD
100
$10.00
$1,000.00
8
2112.501
SUBGRADE PREPARATION
ROAD STA
14.1
$200.00
$2,820.00
9
2211.501
AGGREGATE BASE, CLASS 5 (100% CRUSHED)
TON
4,260
$10.00
$42,600.00
10
2350.501
TYPE LV 3 WEARING COURSE (C)
TON
645
$36.00
$23,220.00
11
2350.502
TYPE LV 3 NON - WEARING COURSE (C)
TON
645
$35.00
$22,575.00
12
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
300
$2.00
$600.00
13
2502.541
4" PERF PVC PIPE DRAIN
LIN FT
50
$7.50
$375.00
14
2521.501
6" CONCRETE WALK
SQ FT
5,650
$3.50
$19,775.00
15
2521.604
2" BITUMINOUS PATH
SQ YD
570
$10.25
$5,842.50
16
2531.501
CONCRETE CURB & GUTTER, DESIGN MODIFIED S
LIN FT
2,700
$8.00
$21,600.00
17
2545.523'
4" NON - METALLIC CONDUIT
LIN FT
250
$6.00
$1,500.00
18
2563.601
TRAFFIC CONTROL
LUMP SUM
1
$2,500.00
$2,500.00
19
2564.531
F &I SIGN PANELS TYPE C
SQ FT
12.5
$25.00
$312.50
20
2564.602
F &I SIGN PANELS TYPE D
EACH
6
$250.00
$1,500.00
21
2573.501
BALE CHECK
EACH
40
$6.50
$260.00
22
2573.502
SILT FENCE, TYPE HEAVY DUTY
LIN FT
200
$2.50
$500.00
23
2573.602
INLET PROTECTION
EACH
14
$60.00
$840.00
24
2575.501
SEEDING (INCL TOPSOIL, FERT, MULCH, DISC ANCHOR)
ACRE
4
$1,000.00
$4,000.00
25
2575.505
SODDING TYPE LAWN (INCL. TOPSOIL & FERT.)
SQ YD
2,900
$3.00
$8,700.00
26
2575.523
EROSION CONTROL BLANKETS CATEGORY 3
SQ YD
50
$2.00
$100.00
SUBTOTAL SCHEDULE A - SURFACE IMPROVEMENTS $181,340.00
B. SANITARY SEWER
27
2451.602
GRANULAR FOUNDATION MATERIAL
TON
50
$3.00
$150.00
28
2503.603
CONNECT TO EXISTING SANITARY SEWER
EACH
1
$500.00
$500.00
29
2503.602
8"X 4" PVC TEE, C -900 PIPE
EACH
10
$285.00
$2,850.00
30
2503.602
8"X 4" PVC WYE
EACH
12
$65.00
$780.00
31
2503.603
TELEVISING SANITARY SEWER
LIN FT
1,225
$1.00
$1,225.00
32
2503.603
4" PVC PIPE SEWER SDR 26
LIN FT
1,100
$10.50
$11,550.00
33
2503.603
8" PVC PIPE SEWER SDR 26
LIN FT
385
$23.00
$8,855.00
34
2503.603
8" PVC PIPE SEWER DR 18
LIN FT
840
$51.00
$42,840.00
35
2506.516
CASTING ASSEMBLY
EACH
6
$400.00
$2,400.00
36
2506.603
CONST 48" DIA SAN SEWER MANHOLE
LIN FT
121
$150.00
$18,150.00
SUBTOTAL SCHEDULE B - SANITARY SEWER $89,300.00
I M: \01577- 00\FEAS \Opinion of Probable Cost 1 of 2
Opinion of Probable Cost
WSB Project: Biscayne Pointe North Design By: JDH
Project Location: City of Rosemount Checked By:
City Project No.: 370
WSB Project No.: 1577 -00 Date: 3/16/2004
Item
No.
MN/DOT
I Specification No.
Description
I
Unit
Estimated
Total Quantity
Unit Price
Estimated Total
Cost
C. WATERMAIN
33
2104.523
SALVAGE HYDRANT AND VALVE
EACH
1
$500.00
$500.00
34
2504.602
INSTALL HYDRANT AND VALVE
EACH
1
$500.00
$500.00
35
2504.602
HYDRANT
EACH
4
$1,850.00
$7,400.00
36
2504.602
1" CORPORATION STOP
EACH
22
$50.00
$1,100.00
37
2504.602
6" GATE VALVE AND BOX
EACH
3
$550.00
$1,650.00
38
2504.602
8" GATE VALVE AND BOX
EACH
6
$750.00
$4,500.00
39
2504.602
1" CURB STOP & BOX
EACH
22
$115.00
$2,530.00
40
2504.602
CONNECT TO EXISTING WATERMAIN (8 ")
EACH
1
$500.00
$500.00
41
2504.603
1" TYPE K COPPER PIPE
LIN FT
1,100
$9.00
$9,900.00
42
2504.603
6" WATER MAIN -DUCT IRON CL 52
LIN FT
50
$20.00
$1,000.00
43
2504.603
8" WATER MAIN-DUCT IRON CL 52
LIN FT
1,410
$20.00
$28,200.00
44
2504.604
4" POLYSTYRENE INSULATION
SQ YD
100
$20.00
$2,000.00
45
2504.604
DUCTILE IRON FITTINGS
POUND
1,500
$2.00
$3,000.00
SUBTOTAL SCHEDULE C - WATERMAIN $54,380.00
D. STORM SEWER
46
2451.602
GRANULAR FOUNDATION MATERIAL
TON
50
$3.00
$150.00
47
2501.515
15" RC PIPE APRON
EACH
1
$425.00
$425.00
48
2501.515
18" RC PIPE APRON
EACH
1
$450.00
$450.00
49
2501.515
21" RC PIPE APRON
EACH
1
$475.00
$475.00
50
2501.515
27" RC PIPE APRON
EACH
1
$525.00
$525.00
51
2501.602
TRASH GRATE FOR 15" RC PIPE APRON
EACH
1
$250.00
$250.00
52
2501.602
TRASH GRATE FOR 18" RC PIPE APRON
EACH
1
$325.00
$325.00
53
2501.602
TRASH GRATE FOR 21" RC PIPE APRON
EACH
1
$425.00
$425.00
54
2501.602
TRASH GRATE FOR 27" RC PIPE APRON
EACH
1
$610.00
$610.00
55
2503.541
15" RC PIPE SEWER DESIGN 3006 CL V
LIN FT
510
$22.50
$11,475.00
56
2503.541
18" RC PIPE SEWER DESIGN 3006 CL III
LIN FT
250
$24.00
$6,000.00
57
2503.541
21" RC PIPE SEWER DESIGN 3006 CL III
LIN FT
210
$26.00
$5,460.00
58
2503.541
24" RC PIPE SEWER DESIGN 3006 CL III
LIN FT
300
$28.00
$8,400.00
59
2503.541
27" RC PIPE SEWER DESIGN 3006 CL III
LIN FT
200
$30.00
$6,000.00
60
2506.501
CONSTRUCT DRAINAGE STRUCTURE DES 48 -4020
LIN FT
65
$150.00
$9,750.00
61
2506.501
CONSTRUCT DRAINAGE STRUCTURE DES 60 -4020
LIN FT
50
$225.00
$11,250.00
62
2506.502
CONSTRUCT DRAINAGE STRUCTURE DES G
EACH
2
$975.00
$1,950.00
63
2506.502
CONSTRUCT DRAINAGE STRUCTURE DES SPECIAL 1 (2'x3' CB ) ,
EACH
5
$1,200.00
$6,000.00
64
2506.502
CONSTRUCT DRAINAGE STRUCTURE DES SPECIAL 2
EACH
I
$6,000.00
$6,000.00
65
2506.516
CASTING ASSEMBLY
EACH
10
$450.00
$4,500.00
66
2511.501
RANDOM RIPRAP, CLASS IV
CU YD
21
$85.00
$1,785.00
67
2511.515
GEOTEXTILE FILTER, TYPE IV
SQ YD
32.0
1 $5.00
1 $160.00
SUBTOTAL SCHEDULE D - STORM SEWER $82,370.00
Project Subtotal $407,390.00
+ 10% Contingencies $40,740.00
Subtotal $448,130.00
+ 30% Indirect Cost $134
Biscayne Pointe North - Project Total $582,600.00
1 M \01577- 00 \FEAS \Opinion of Probable Cost 2 of 2