HomeMy WebLinkAbout6.c. Change Order #1 - Chippendale Tower Improvements, City Project #374CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: March 16, 2004
AGENDA ITEM: Change Order #1- Chippendale Tower
AGENDA SECTION:
Improvements, City Project #374
Consent
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
AG V
1
i�
ATTACHMENTS: Change Order #1
APPROVED BY
Please find attached for your review and consideration Change Order #1 for the Chippendale
Tower Project, City Project #374. As noted, this change order includes the addition of security
lighting to the tower structure that will be motion operated. The total amount of Change Order
#1 is $2,940.00 for revised total contract amount of $290,405.00.
Staff recommends Council approval of this item.
KLM ENGI EERIN INC.
P.O. Box 897 • 3394 Lake Elmo Ave. N. • Lake Elmo, MN 55042
March 4, 2004 (651) 773- 5111• Fax (651) 773 -5222
John Newkirk
Project Manager
Classic Protective Coatings, Inc.
N 7670 State Highway 25
Menomonie, WI 54751
RE: Change Order No. I — Installation of Security Light during Reconditioning of
Chippendale Tower in Rosemount, MN
KLM Project MN 1830
KIM Engineering, Inc. recommends approval of the following change order to the specifications
and contract for the above referenced project. Final approval by the City Council is required for
this Change Order to be included in the scope of work. Approval by the City Council is indicated
by the City Administrator's signature on this form.
Receipt of a completed copy of this letter authorizes Classic Protective Coatings to proceed with
this work listed on this Change Order in conjunction with the project.:
1. Furnish and install all items necessary for an exterior security light on the support _
column adjacent to the ladder,, including light, motion sensor electrical and conduit.
The fixture(s) shall use one (1) 300 watt or two (2) 150 watt bulbs. Lights shall be
controlled by a motion sensor set to detect motion on-the ladder, with .a minimum 180
degree field of detection. The light and motion sensor shall have watertight
construction and fittings. The light and motion detector shall have options for
daylight shutoff, sensitivity and position adjustment, manual override, and shall allow
for adjustment to the length of time the light will stay on after motion is detected.
2. Light system shall be tied directly into existing power supply, on a separate circuit if
available.
3. Light and sensor shall be permanently attached to the support column or strut, as
directed by the Engineer.
Con r agrees to perform the above items for a price of $2,940.00.
J ck Kollmer, KLM Engineering, Inc. Date
assic Protective Coatings, Inc. Date
Jamie Verbrugge, City Administrator Date