EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: October 7, 2003
Change Order #1, Eastside Watermain, Phase 2, includes the addition of concrete rail posts for protection of
hydrants and fiberoptic markers to protect the future SCADA fiberoptic boxes. Another addition is 10.5 -foot
hydrants instead of 7,5 -foot hydrants to allow for a clean-out hydrant installation that enables air to be released
from the watermain in low points. The final addition was a water service for the Weiderhold property located
along CSAH 42. This service was installed at the homeowners request and they were notified by letter that cost
for this installation of the water service would be added to their permit to hook -up when it is applied for.
Staff requests Council approval of this item. .
RECOMMENDED ACTION: MOTION TO APPROVE CHANGE ORDER #1 FOR EASTSIDE
WATERMAIN, PHASE 2, CITY PROJECT #345 AND AUTHORIZE NECESSARY SIGNATURES.
COUNCIL ACTION:
AGENDA ITEM: Change Order #1— Eastside Watermain, Phase 2,
AGENDA SECTION:
City Project #345
Consent
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
AGEN
b
ATTACHMENTS: 'Change Order #1
APPROVED BY:
13
r
cxi erg a r° l ,'
CHANGEI QRDER.NO 1
EASTSIDE WATERMAIN PHASE II SEPTEMBER 25, 2003
AND APPURTENANT WORK
CITY OF ROSEMOUNT PROJECT NO. 345
WSB PROJECT NO. 1402 -00
OWNER:
CITY OF ROSEMOUNT
2875 - 145TH STREET WEST
ROSEMOUNT, MN 55068
CONTRACTOR:
THREE RIVERS CONSTRUCTION, INC.
15001 HUDSON ROAD, P.O. BOX 206
LAKELAND, MN 55043
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
$1,022,089.80
ORIGINAL CONTRACT TIME:
11/11/2003
PREVIOUS CHANGE ORDERS: N/A
$0.00
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
NONE
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
$1,022,089.80
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
11/11/2003
NET INCREASE OF THIS CHANGE ORDER:
$17,622.00
NET INCREASE OF CHANGE ORDER:
NONE
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$1,039,711.80
CONTRACT TIME WITH APPROVED CHANGE ORDERS
11/11/2003
RECOMMENDED BY: APPROVED BY:
KEVIN B. KAWLEWSKI, P.E., PROJECT MANAGER
WSB & ASSOCIATES, INC. THREE RIVERS CONSTRUCTION, INC.
ENGINEER CONTRACTOR
APPROVED BY:
CITY ENGINEER CITY ADMINISTRATOR
DATE OF COUNCIL ACTION
Page 1 F. 00TxceAC0 ICO -r
EASTSIDE WATERMAIN PHASE II
September 25, 2003
AND APPURTENANT WORK
CITY OF ROSEMOUNT PROJECT NO. 345
WSB PROJECT NO. 1402 -00
ADDED ITEMS
Item No. Description
Qty
Unit
Price
Extended Amount
76 CONCRETE RAIL POST
69
EACH
$175.00
$12,075.00
77 HYDRANT
6
EACH
$300.00
$1,800.00
78 CHANGEABLE MESSAGE SIGN DES FIBER OPTIC
40
EACH
$75.80
$3,032.00
79 SERVICE INSTALLATION
1
EACH
$715.00
$715.00
TOTAL INCREASE CHANGE ORDER NO. 1
ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT..
$17,622.00
$17,622.00