HomeMy WebLinkAbout6.r. Payment #2 & Final - 128th Street Drainage Improvements, City Project #356f CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: October 7, 2003
This item is on the agenda to request Payment No. 2 and final to Heselton Construction in the amount of
$6,474.95 for the 128TH Street Drainage Improvements, City Project #356.
Staff recommends that Council approve Payment #2 and final for the project and accept the project for perpetual
maintenance.
RECOMMENDED ACTION: MOTION TO APPROVE PAYMENT #2 AND FINAL TO HESELTON
CONSTRUCTION THE AMOUNT OF $6,474.95 FOR THE 128 STREET DRAINAGE
IMPROVEMENTS, CITY PROJECT #356 AND ACCEPT FOR PERPETUAL MAINTENANCE.
COUNCIL ACTION:
AGENDA ITEM: Payment #2 & Final -128 ' Street Drainage
Improvements, City Project #356
AGENDA SECTION:
Consent
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
AGEND
-
u6 o
ATTACHMENTS: Payment #2 & Final
APPROVED BY:
?Y""'
Please make payment in this amount to Heselton Construction, LLC at your earliest
convenience.
WS B
& Associates, Inc.
September 23, 2003
Honorable Mayor and City Council
City of Rosemount
ir
2875 —145 Street West
Rosemount, MN 55068
Attn: Cindy Dorniden, City of Rosemount
Re: Construction Pay Voucher No. 2 (Final)
128 Street Drainage Improvements and Appurtenant Work
City of Rosemount Project No. 356
WSB Project No. 1005 -56
Dear Mayor and Council Members:
Please find enclosed the final Construction Pay Voucher No. 2 for the above - referenced
project in the amount of $6,474.95. We recommend final payment subject to receipt of the
following items:
1. Satisfactory showing that the contractor has complied with the provisions of
Minnesota Statutes 290.92 requiring withholding state income tax.
2. Evidence in the form of an affidavit that all claims against the contractor by reasons
of the contract have been fully paid or satisfactorily secured.
3. Consent of Surety to Final Payment certification from the contractor's surety.
4. Two -year maintenance bond.
Please make payment in this amount to Heselton Construction, LLC at your earliest
convenience.
W SB
B
k AJSPLINGS. /nc.
)wner: City of Rosemount Date: September 23, 200:
or Period: 8/1/2003 to 8/31/2003 Request No: 2 AND FINAL
:ontractor. Heselton Construction, LLC
PAY VOUCHER
128TH STREET DRAINAGE IMPROVEMENTS AND APPURTENANT WORK
CITY OF ROSEMOUNT PROJECT NO. 356
WSB PROJECT NO. 1005 -56
SUMMARY
1 Original Contract Amount
2 Change Order - Addition
3 Change Order - Deduction
4 Revised Contract Amount
5 Value Completed to Date
6 Material on Hand
7 Amount Earned
8 Less Retainage 0%
9 Subtotal
10 Less Amount Paid Previously
11 AMOUNT DUE THIS PAY VOUCHER NO
Recommended for Approval by:
WSB & Associates, Inc.
Project Manager /Engineer
$ 45,844.00
$ 0.00
$ 0.00
$
45,844.00
$
44,616.50
$
0.00
$
44,616.50
$
0.00
$
44,616.50
$
38,141.55
$
6,474.95
Con ruction Obs er
Approved by Contractor: Approv d by Owner.
HESELTON CONST�N, CITY EMOUNT
Specified Contract Completion Date:
August 15, 2003
P.S. 1 of 3
Date:
F.%WPW1M 700.5561E -1; 7005 -56 PeyV —d.,2 AND FNL RVSD 092303