HomeMy WebLinkAbout6.n. Change Order #2, Bloomfield Vinyards, City Project # 368F
CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: December 2, 2003
Change Order #2, Bloomfield Vineyards Improvements includes an amendment to the contract for adding the
items shown in the Change Order No. 2 detail. The amount of Change Order #2 is $6,500.00 for a revised
contract price of $521,120.79. There is no change in the contract schedule as part of this change order.
Staff requests Council approval of this item.
AGENDA ITEM: Change Order #2 - Bloomfield Vineyards
Improvements, City Project #368
AGENDA SECTION:
Consent
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
AGENDM "6 N
ATTACHMENTS: Change Order #2
APPROVED BY:
1 _
� W `
es, Inc.
November 24, 2003
I Honorable Mayor and City Council
City of Rosemount
2875 145' Street West
Rosemount, MN 55068
Re: Change Order No. 2
Bloomfield Vineyards
�. City of Rosemount Project No. 368
WSB Project No. 20,12 -70 ,
Dear Mayor and Council Members:
Please find enclosed Change Order No. 2 for the above- referenced project. Change Order
No. 2 is necessary because Centex Homes, the developer for this project, did not own the
' "Mina Property" as soon as they expected. Subsequently, our contractor was not able to
complete their work that entailed jacking utilities from this project under the railroad tracks and
into the "Mines Property." Erickson Construction was required to re- mobilize their crews after
Centex closed on the property. This re- mobilization is the only item indicated on this chan ge
order. We recommend approval of this change order as detailed.
Please contact me at 763 -287- 7163 if you have any questions.
Sincerely,
WSB'& Associates, Inc.
Mark A. Erichson, P.E.
Project Manager
Enclosure
cc: Don Erickson, Erickson Construction Co.
Andy Brotzler, City of Rosemount
Chad Onsgard, Centex Homes
lh
4� e
f,
P: I WPWIM2012- 701112403- hmcc.doc
Minneapolis • St. Cloud • Equal Opportunity Employer
BLOOMFIELD VINEYARDS NOVEMBER 24, 2003
STREET AND UTILITY CONSTRUCTION AND APPURTENANT WORK
CITY OF ROSEMOUNT PROJECT NO. 368
WSB PROJECT NO..2012 -70
OWNER: CONTRACTOR:
CITY OF ROSEMOUNT ERICKSON CONSTRUCTION, INC.
2875 - 145TH STREET WEST 13616 PLEASANT LANE
ROSEMOUNT, MN 55068 BURNSVILLE, MN 55337
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
Remobilization for construction north of the railroad tracks is required due to the developer not closing on the property as soon
as they Originally intended.
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS
AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE,
OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE: $477,102.21
ORIGINAL CONTRACT TIME (SUBSTANTIAL):
10/3112003
PREVIOUS CHANGE ORDERS: NO. 1 $37,518.58
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
NONE
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $514,620.79
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
10/31/2003
NET INCREASE OF THIS CHANGE ORDER: $6,500.00
NET INCREASE OF CHANGE ORDER:
NONE
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $521,120.79
CONTRACT TIME WITH APPROVED CHANGE ORDERS:
10131/2003
RECOMMENDED BY:
APPROVED BY:
MARK A. ERICHSON, P.E., PROJECT:MANAGER
WSB & ASSOCIATES, INC.
ERICKSON CONSTRUCTION, INC.
ENGINEER
CONTRACTOR
APPROVED BY:
CITY ENGINEER
CITY ADMINISTRATOR