HomeMy WebLinkAbout6.o. Change Order #4 - Truck Highway 3 Improvements, City Project #318CITY OF ROSEMOUNT EXECUTIVE SUMMARY. FOR ACTION CITY COUNCIL MEETING DATE: December 2, 2003 Change Order #4, Trunk Highway #3 Improvements includes an amendment to the contract for adding the items shown in the Change Order No.4 detail. These additional items represent miscellaneous work completed by the contractor for project clean-up. The amount of Change Order #4 is $35,352.55 for a revised contract price of $2,194,360.16. There is no change in the contract schedule as part of this change order. Staff requests Council approval of this item. AGENDA ITEM: Change Order #4 —Trunk Highw #3 ay Improvements, City Project #318 AGENDA SECTION: Consent PREPARED BY: Andrew J. Brotzler, P.E., City Engineer AMN gn. ATTACHMENTS: Change Order #4 APPROVED BY: RECOMMENDED ACTION: MOTION TO APPROVE CHANGE ORDER #4 TO TRUNK HIGHWAY #3 IMPROVEMENTS, CITY PROJECT #318 AND AUTHORIZE THE NECESSARY SIGNATURES. COUNCIL ACTION: 8 mil, >I NOVEMBER 12, 2003 TRUNK HIGHWAY 3 STREET AND UTILITY CONSTRUCTION AND APPURTENANT WORK B.P. NO. 1921-73 AND CITY OF ROSEMOUNT PROJECT NO. 318 - WSB PROJECT NO. 1191 -21 OWNER: CONTRACTOR: CITY OF ROSEMOUNT VALLEY PAVING, INC. 2875.145TH STREET WEST 8800 -13TH AVENUE EAST ROSEMOUNT, MN 55068 SHAKOPEE, MN 55379 YOU ARE DIRECTED TO MAKE THE FOLLOWING MODIFICATIONS IN THE CONTRACT DOCUMENT DESCRIPTION; THE FOLLOWING MODIFICATIONS TO THE PROJECT ARE REQUESTED: 189. ADDING 3" MINUS FOR SOFT SPOTS IN BASE ON 10/28/02 AND 10/29/02 190. ADD 295 SQ FT OF BITUMINOUS SIDEWALK FOR WINTER 191. INSTALL SPLIT RAIL FENCE 192. MILL TAPERS THAT WERE INSTALLED PROR TO WINTER AS A TEMPORARY MEASURE 193. REVISE DRIVEWAY AND PARKING LOT ADJACENT TO MASTER TRANSMISSION 194. MODIFY PARKING LOT AND BOULEVARDS ADJACENT TO GENZ -RYAN 195. ADD ROCK BY RETAINING WALL 196. REMOVE POOR SOILS UNDER SOFT SPOTS IN ROAD 197., ADDITIONAL PAVEMENT REMOVAL ON 145TH AND 146TH FOR LOOPS AND OTHER SMALL PATCH AREAS 198. STORM SEWER CASTING FOR ADDITIONAL DRAIN FOR THE GENZ -RYAN PROPERTY 199. TEMPORARY TRAFFIC CONTROL OVER THE WINTER CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL. IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME: ORIGINAL CONTRACT PRICE: $2,128,583.16 ORIGINAL CONTRACT TIME: 11/30/2002 PREVIOUS CHANGE ORDERS: NOS. 1, 2, AND 3 $30,424.45 NET CHANGE FROM PREVIOUS CHANGE ORDERS: N/A CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $2,159,007.61 CONTRACT TIME PRIOR TO THIS CHANGE ORDER: 6/15/2003 NET INCREASE OF THIS CHANGE ORDER: $35,352.55 NET INCREASE OF CHANGE ORDER: N/A CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $2,194,360.16 CONTRACT TIME WITH APPROVED CHANGE ORDERS 6/15/2003 RECOMMENDED BY: APPROVED BY:' DAVID E. HUTTON, P.E, PROJECT MANAGER CONTRACTOR SIGNATURE WSB & ASSOCIATES, INC. VALLEY PAVING; INC. ENGINEER CONTRACTOR APPROVED BY: CITY ENGINEER MAYOR CITY ADMINISTRATOR DATE F: IWPWIN11191- 211ExceACO- 4.xIsiCO -4 K, SEUM NOVEMBER 12, 2003 TRUNK HIGHWAY 3 STREET AND UTILITY CONSTRUCTION AND APPURTENANT WORK S.P. NO. 1921 -73 AND CITY OF ROSEMOUNT PROJECT NO. 318 WSB PROJECT N0: 1191 -21 MODIFIED QUANTITIES ITEM NO. DESCRIPTION QTY UNIT PRICE TOTAL ADDING 3" MINUS FOR SOFT SPOTS IN BASE ON 189 1.00 LUMP SUM $5,890.66 $5,890.66 10/28/02 AND 10/29/02 ADD 295 SQ FT OF BITUMINOUS SIDEWALK FOR 190 1.00 LUMP SUM $1,237.08 $1,237.08 WINTER 191 INSTALL SPLIT RAIL FENCE 1.00 LUMP SUM $1,071.11 $1,071.11 192 MILL TAPERS THAT WERE INSTALLED PRIOR TO 1,533.00 SQ YD $3.50 $5,365.50 WINTER AS A TEMPORARY MEASURE REVISE DRIVEWAY AND PARKING LOT ADJACENT TO 193 1.00 LUMP SUM $6,744.88 $6,744.88 MASTER TRANSMISSION MODIFY PARKING LOT AND BOULEVARDS ADJACENT 1 1.00 LUMP SUM $8,063.78 $8,063.78 TO GENZ -RYAN 195 ADD ROCK BY RETAINING WALL 1.00 LUMP SUM $1,355.83 $1,355.83 196 REMOVE POOR SOILS UNDER SOFT SPOTS IN 1.00 LUMP SUM $1,000.00 $1,000.00 ADDITIONAL PAVEMENT REMOVAL ON 145TH AND 197 1.00 LUMP SUM $3,000.00 $3,000.00 146TH FOR LOOPS AND OTHER SMALL PATCH AREAS STORM SEWER CASTING FOR ADDITIONAL DRAIN FOR 198 1.00 LUMP SUM $123.71 $123.71 THE GENZ -RYAN PROPERTY 199 TEMPORARY TRAFFIC CONTROL OVER THE WINTER 1.00 LUMP SUM $1,500.00 $1,500.00 TOTAL MODIFIED QUANTITIES $35,352.55 NET TOTAL CHANGE ORDER NO. 4 $35,352.55 F :IWPMM1191- 211ExceACO- 4.xisIC04 Detail