HomeMy WebLinkAbout8. Chippendale Avenue/CSAH 42 Street & Utility Improvements, City Project #344CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: April 17, 2003
AGENDA ITEM: Chippendale Avenue /CSAH 42 Street and Utility
AGENDA SECTION:
Improvements, City Project 4344
Public Hearing
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
AGENDA NO:
0.
ATTACHMENTS: Resolution
APPROVED BY-
At the March 20, 2003 Council meeting, Council received a revised Feasibility Report for the Chippendale
Avenue /CSAH 42 Street and Utility Improvements, City Project #344. The original feasibility report for this
project was completed in 2002 with the project being delayed until 2003 to address access issues on
Chippendale Avenue. With the delay of the original project, which consists of the reconstruction of
Chippendale Avenue south of CSAH 42 and improvements to the Chippendale Avenue /CSAH 42 intersection,
the original report was revised to add the reconstruction of Chippendale Avenue from 145 Street to Upper 149 "
Street to the proposed improvements. The reconstruction of this additional segment of Chippendale Avenue is
included in the City's 2004 CIP. However, as funding is available to finance the project in 2003, it is proposed
to advance the project schedule to facilitate the completion of work as one project rather than two separate
projects to minimize disruption to the area.
As noted, the project includes the reconstruction of Chippendale Avenue from 145`'' Street to 15 Pt Street along
with improvements to the Chippendale Avenue /CSAH 42 intersection. As part of the intersection
improvements, a new signal system is proposed to be installed. The other item to be addressed with this project
is the proposed closure and/or reduction of access from Chippendale Avenue to the Holiday Gas Station.
The total estimated project cost is $1,892,480. Funding for the project will consist of special assessments to
adjacent properties, Municipal State Aid (MSA) funds, Dakota County funds, Street CIP funds and City Core
funds
As part of the process, Staff conducted a Public Informational Meeting on April 9, 2003. Comments and
concerns received at the Public Informational Meeting will be presented to Council.
Attached for Council consideration is a resolution approving the project and ordering the preparation of plans
and specifications.
RECOMMENDED ACTION: MOTION TO ADOPT A RESOLUTION APPROVING THE PROJECT
AND ORDERING THE PLANS AND SPECIFICATIONS FOR THE CHIPPENDALE AVENUE /CSAH 42
STREET AND UTILITY IMPROVEMENTS, CITY PROJECT #344.
COUNCIL ACTION:
2
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOLUTION 2003 —
A RESOLUTION APPROVING THE PROJECT AND ORDERING THE
PREPARATION OF PLANS AND SPECIFICATIONS FOR
CHIPPENDALE AVENUE /CSAH 42 STREET AND UTILITY IMPROVEMENTS
CITY PROJECT 4344
WHEREAS, the City Council of the City of Rosemount ordered a feasibility report for
Chippendale Avenue /CSAH 42 Street and Utility Improvements, City Project #344; and
WHEREAS, the City Council of the City of Rosemount received the feasibility report on March
20, 2003 and ordered a Public Hearing; and
WHEREAS, the City Council of the City of Rosemount has held a Public Hearing on the
Chippendale Avenue /CSAH 42 Street and Utility Improvements, City Project #344.
NOW THEREFORE BE IT RESOLVED, that the City Council of the City of Rosemount
hereby orders the improvements of the Chippendale Avenue /CSAH 42 Street and Utility
Improvements, City Project #344.
NOW THEREFORE BE IT FURTHER RESOLVED, by the City Council of the City of
Rosemount hereby orders the preparation of plans and specifications for the Chippendale
Avenue /CSAH 42 Street and Utility Improvements, City Project #344.
ADOPTED this 17` day of April, 2003.
William H. Droste, Mayor
ATTEST:
Linda Jentink, City Clerk
Motion by:
Voted in favor:
Seconded by:
Voted against:
MEMORANDUM
TO: Honorable Mayor and City Council Members
Jamie Verbrugge, City Administrator
FROM: Andrew J. Brotzler, P.E., City Engineer
DATE: April 15, 2003
RE: Supplemental Information for Regular Council Meeting, April 17, 2003
Chippendale Avenue /CSAH 42 Street & Utility Improvements, C.P. # 344
Agenda Item 8
Please find attached a preliminary assessment roll and exhibit for the Chippendale
Avenue /CSAH 42 Street & Utility Improvements project. The proposed assessments for the
properties located along Chippendale Avenue south of CSAH 42 are based on Option 1 as shown
in the feasibility report. The proposed assessments for the residential properties located along
Chippendale Avenue north of CSAH 42 are based on the current street assessment rate shown in
the Schedule of Rates and Fees for 2003.
Also attached is a memorandum with attachments summarizing the public informational meeting
conducted on April 9, 2003.
Should you have questions, please do not hesitate to contact me.
G:\ENGPROJ\344\councilmemo2.041503.doc
Preliminary Assessments
WSB Project: Chippendale Avenue
Project Location: Rosemount, Minnesota
WSB Project No: 1399 -003 Assessment / Lot $2,295.00
Assessment / Foot $118.48
Parcel
Fee Owner
Fee Owner Address
PID
Frontage (ft)
Assessment
1
Edwin & Kathleen R. Tousignant
14530 Chippendale Ave.
34- 62853- 090 -01
na
$2,295.00
Rosemount, MN 55068
2
Fred Uitdenboged
14540 Dodd Blvd
34- 03010 - 030 -95
na
$2,295.00
Rosemount, MN 55068
3
Glen & Ione Uitdenbogerd
14625 Chippendale RR 4
34- 03010- 010 -95
na
$2,295.00
Rosemount, MN 55068
4
Eric A & Jennifer K Heim
14645 Chippendale Ave.
34- 03010- 020 -95
na
$2,295.00
Rosemount, MN 55068
5
Rosemount National Bank
15055 Chippendale Ave.
34- 47501- 020 -01
365
$43,245.20
Rosemount, MN 55068
6
Lyndale Terminal
P.O. Box 1224
34- 71150- 012 -01
208
$24,643.84
Holiday Convenience Store
Minneapolis, MN 55440
7
Lucy B Carlson
3500 W 80th St. STE 200
34- 64630 - 040 -01
208
$24,643.84
Chippendale Center
Bloomington, MN 55431
-
% United Properties
--
- Total 781
i
i
N A
�1
' I
I I
I (I
O
O
LO (D
0
O
N
O)
U!
a
DOLL- 1K- Cg17Mj
'au� •a'a q+
OO8YL65
ZQQcQf�Q01NleawlW
�V/ r /
3
CD
O
OOE aging
ABM451H IeILOWOVI U 090
W
p
i
i
N A
�1
' I
I I
I (I
O
O
LO (D
0
O
N
O)
U!
a
i
Chippendale Avenue
151 Avenue to 145 Street
Public Hearing Presentation Materials
April 17, 2003
{i
I
Project History
I. Segment 1 Upper 149 Street to 151 Street
• Feasibility Report completed — 2002
• Public Hearing — June, 2002
• Plans /Specs ordered
II. Segment 2 145 Street to Upper 149 Street
• Feasibility Report completed — March 2003
• Neighborhood Meeting held — April 10, 2003
• Public Hearing - April 17, 2003
0
Traffic Study
I.
II.
Chippendale south of CR 42
2003 Traffic
2023 Projected Traffic
— 8 1 500 ADT
15,000 ADT
Chippendale north of CR 42
2003 Traffic l
2023 Projected Traffic
5,800 ADT
— 9,900 ADT
0
III. Roadway Maximum Capacities
2 lane .............................8 — 10 ADT
3 lane or .........................10 — 1800 ADT
4 lane undivided
4 lane divided ................15,000 — 261000
Iv. Recommendations
• Add center median from Lower 149 to 151
• 4 -way stop at 151 Street
• Three -lane design from Lower 149 to 145
Street
Proposed Improvements
1. Chippendale Ave. south of CR 42
• Mill /overlay pavement
• Replace cracked curb
• Add center median
• Add permanent curb south of 151 St
• Add sidewalk on east side south of 151 St
2. 42 /Chippendale intersection
• New signal
• New right turn lanes onto Chippendale for both
directions
• Adjust medians for left turn tapers
• Adjust turning radii on curbs
3. 42 /Canada
• Add right turn lane onto Canada
0
40 Chippendale - north of CR 42
A. CR 42 to Upper 149
• Add center median
• Add right /left turn lanes
• Relocate existing trail
• Taper to city street
S
B. North of Upper 149
• Replace existing pavement
• Widen from two -lane (36'wide) to three -lane
(44'wide)
• Replace curb
• Replace existing trail west side
• Add new sidewalk east side
Summary of Costs
SEGMENT DESCRIPTION
TOTAL
1.
All improvements on Chippendale Ave. south of CSAH 42
$167,430
2.
All improvements on Chippendale Ave. north of CSAH 42
$1
3.
All improvements on CSAH 42 west of Chippendale Ave.,
excluding the Right Turn Lane
$63,600
4.
All improvements for the right turn lane on CSAH 42 to
southbound Chippendale Ave.
$96,940
5.
All improvements on CSAH 42 east of Chippendale Ave.
$163,480
6.
All improvements for the right turn lane on CSAH 42 to
southbound Canada Ave.
$112,610
7.
New signal at Chippendale Ave. and CSAH 42 intersection
$243
TOTAL
$198929480
I
Special Assessments
I. Commercial Rate — South of CR 42
35 % of mill /overlay costs - $118.48 per front foot
II. Residential Rate
Per City assessment policy — 2003 rates — 2,295 / lot
Funding Summary
1 Based on $118.48 per front foot
2 Based on $2,295 per foot
3 County participation is 55% of the construction cost (50% for signals) plus 18% for engineering
Storm
Sewer
Sanitary
Special
Municipal
Dakota
Core
Sewer
Watermain
Segment
Assess.
State Aid
County
Fund
Street CIP
Core Fund
Core Fund
TOTAL
Chippendale South
$58,600'
$108,830
$167,430
Chippendale North
$9,180
$48,830
$975,800
$8,010
$3,500
$1,045,320
CSAH 42 West
$31,210
$31,750
$640
$63,600
CSAH 42 Right Turn
Lane onto
$33,930
$12,810
$48,400
$1,800
$96,940
Chippendale
CSAH 42 East
$75,200
$81,620
$6,660
$163,480
CSAH 42 Right turn
lane onto Canada
$54,720
$56,220
$1,670
$112,610
Signal System
$132,770
$110,330
$243,100
TOTAL
$101,710
$415,540
$328,320
$59,600
$975,800
$8,010
$3,500
$1,892,480
1 Based on $118.48 per front foot
2 Based on $2,295 per foot
3 County participation is 55% of the construction cost (50% for signals) plus 18% for engineering
a
Project Schedule
Receive Feasibility Report ............... ............................... .........March 20, 2003
Public Informational Meeting ..............April 9, 2003
Public Hearing to Order Improvements ................ ....................April 17, 2003
Design......................................... ............................... April 18 — May 23, 2003,
State Aid Approval /County Approval /Agreement ....... May 19 — June 6, 2003
Bidding.................................................... ............................... June 6 -27, 2003
BidAward ...................................................... ....................... .I....... July 1, 2003
Construction ...............July 14 - Nov. 30, 2003
.......... .............. .....................
Assessment Hearing ..` .............................. ............................... November 2003