HomeMy WebLinkAbout6.i. Change Order #1 Chippendale/CSAH 32 Improvements, City Project #344w
CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: September 16, 2003
Change Order #1, Chippendale /CSAH 42 Improvements, includes the addition of bituminous pathway along the
east side of Chippendale Avenue from Carrousel Way to 153r Street.
Two water and sanitary sewer services for the Uitdenbogerd property located at 14540 Dodd Boulevard are
included as part of Change Order #1. There services are being added in anticipation of 'a lot split and to avoid
patching Chippendale Avenue after construction is complete. The last item as part of Change Order #1 is a
price reduction resulting from changing the pavement marking arrows on CSAH 42 from poly preform to epoxy.
Staff requests Council approval of this item.
AGENDA ITEM: Change Order #1 - Chippendale /CSAH 42
AGENDA SECTION:
Improvements, City Project #344
Consent
PREPARED BY: Andrew J. Brotzler, P.E., City Engineer
•
AGEN JIM. 6 1
ATTACHMENTS: Change Order #1
APPROVED BY:
Change Order #1, Chippendale /CSAH 42 Improvements, includes the addition of bituminous pathway along the
east side of Chippendale Avenue from Carrousel Way to 153r Street.
Two water and sanitary sewer services for the Uitdenbogerd property located at 14540 Dodd Boulevard are
included as part of Change Order #1. There services are being added in anticipation of 'a lot split and to avoid
patching Chippendale Avenue after construction is complete. The last item as part of Change Order #1 is a
price reduction resulting from changing the pavement marking arrows on CSAH 42 from poly preform to epoxy.
Staff requests Council approval of this item.
CHIPPENDALE AVENUE AND CSAH 42 SEPTEMBER 10, 2003
STREET IMPROVEMENTS AND APPURTENANT WORK
CITY OF ROSEMOUNT PROJECT NO. 344
WSB PROJECT NO. 1399 -00
OWNER:
CONTRACTOR:
CITY OF ROSEMOUNT MCNAMARA CONTRACTING, INC.
2875 - 145TH STREET WEST 5001 160TH STREET WEST
ROSEMOUNT, MN 55068 ROSEMOUNT, MN 55068
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
$1,046,226.56
ORIGINAL CONTRACT TIME (SUBSTANTIAL):
10/31/2003
PREVIOUS CHANGE ORDERS: N/A
$0.00
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
NONE
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
$1,046,226.56
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
10/31/2003
NET INCREASE OF THIS CHANGE ORDER:
$23,137.85
NET INCREASE OF CHANGE ORDER:
NONE
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$1,069,364.41
CONTRACT TIME WITH APPROVED CHANGE ORDERS
10/3112003
RECOMMENDED BY:
l�
DAM E71-10TON, P.E., PROJECT MANAGER
APPROVED BY:
WSB & ASSOCIATES, INC. MCNAMARA CONTRACTING, INC.
ENGINEER CONTRACTOR
APPROVED BY:
CITY ENGINEER
CITY ADMINISTRATOR
DATE OF COUNCIL ACTION
Page 1 co ico -i
CHIPPENDALE AVENUE AND CSAH 42 September 10, 2003
STREET IMPROVEMENTS AND APPURTENANT WORK
CITY OF ROSEMOUNT PROJECT NO. 344
WSB PROJECT NO. 1399.00
DELETED ITEMS
Item No. Description
Qty Unit Price Extended Amount
Qty
Unit
PAVEMENT MESSAGE (LEFT ARROW) POLY
Extended Amount
69
PREFORMED
_2 EACH $365.00 ($730.00 )
PAVEMENT MESSAGE (RIGHT ARROW) POLY
70
PREFORMED
-4 EACH $365.00 ($1,460.00)
TOTAL DECREASE CHANGE ORDER NO. 1
($2,190.00)
ADDED ITEMS
Item No.
Description
Qty
Unit
Price
Extended Amount
71
PAVEMENT MESSAGE (LEFT ARROW) EPDXY
2
EACH
$265.00
$530.00
72
PAVEMENT MESSAGE (RIGHT ARROW) EPDXY
4
EACH
$265.00
$1,060.00
73
IRREGULAR WIDTH PAVING
128
SQ YD
$34.45
$4,409.60
74
BITUMINOUS BIKE PATH
350
LIN FT
$17.60
$6,160.00
75
ADD TWO WATER AND SEWER SERVICES
1
LUMP SUM
$13,168.25
$13,168.25
TOTAL INCREASE CHANGE ORDER NO. 1 $25,327.85
ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT $23,137.8,5
Page 1 CO 1 CO1 Detail