HomeMy WebLinkAbout6.e. Payment #5 & Final - Marcotte Pond Lift Station, City Project #338r CITY OF ROSEMOUNT EXECUTIVE SUMMARY FOR ACTION CITY COUNCIL MEETING DATE: February 20, 2003 AGENDA ITEM: Payment #5 & Final — Marcotte Pond Lift Station, AGENDA SECTION: City Project #338 Consent PREPARED BY: Andrew J. Brotzler, P.E., City Engineer AGEN - )E #6 - ATTACHMENTS: Payment Voucher #5 & Final APPROVED BY: This item is on the agenda to request Payment #5 and final to Landwehr Construction in the amount of $13,402.43 for the Marcotte Pond Lift Station, City Project #338. Staff recommends that Council approve Payment #5 and final for the project and accept the project for perpetual maintenance. RECOMMENDED ACTION: MOTION TO APPROVE PAYMENT #5 AND FINAL FOR MARCOTTE POND LIFT STATION, CITY PROJECT #338 AND ACCEPT FOR PERPETUAL MAINTENANCE.. COUNCIL ACTION: 3 B Honorable Mayor and City Council City of Rosemount 2875 — 145 Street West Rosemount, MN 55068 Attn: Cindy Dorniden, City of Rosemount Re: Construction Pay Voucher No. 5 (Final) and Final Documentation Marcotte Pond Lift Station and Appurtenant Work City of Rosemount Project No. 338 WSB Project No. 1323 -00 Dear Mayor and Council Members: Please find enclosed the final Construction Pay Voucher for the above - referenced project in the amount of $13,402.43. Also enclosed are the following documents required for processing final payment: 1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes 290.92 requiring withholding state income tax and; 2. Consent of Surety to Final Payment certification from the contractor's surety. February 3, 2003 3. Two -year maintenance bond. We recommend that you make final payment in the amount of $13,402.43 for Landwehr Construction, Inc. at your earliest convenience. Sincerely, WSB & Associates, Inc. Mark A. Erichson, P.E. Project Manager Enclosures cc: Mike Lohrman, Landwehr Construction, Inc. Andy Brotzler, City of Rosemount sb Minneapolis • St. Cloud • Equal Opportunity Employer FAWPwtnv3zs- ornositNsd It, cti.doc Voucher No. 5 (Final) Date: December 19, 2002 Period Ending: September 30, 2002 Project: Marcotte Pond Lift Station and Appurtenant Work City of Rosemount, MN City Project No. 338 WSB Project No. 1323 -00 Contractor: Landwehr Construction Contract Date: 11/20/2001 Completion Date: Work Started: Work Completed: Original Contract Amount $282,136.00 Total Additions $1,111.00 Total Deductions ($18,420.00) Total Funds Encumbered $264,827.00 Total Work Certified to Date $281,823.50 Less Retained Percentage 0.00% $0.00 Less Previous Payments $268,421.08 Total Payments Incl. This Voucher $281,823.50 Balance Carried Forward ($16,996.50) Approved for Payment This Voucher $13,402.43 Approvals WSB & Associates, Inc. In accordance with field observation, as performed in accordance with industry standards, and based on our professional opinion, the The total work estimated to be completed as of September 30, 2002 is as indicated herein and we hereby recommend payment of this voucher. 100% Signed: Signed: 4 d, Cons ruction Observer Project Manager /Engineer Landwehr Construction This is to certify that to the best of my knowledge, information, and belief, the quantities and values of work certified herein is a fair Contractor. L,g,�pyyr�l�rsr- Date: IL�z��o Signed: /-' Title: w.1z City of Rosemount Checked by: Approved for Payment: Date: Date: F.•IWPWIM 1323- 001ExceAvouchers1 V05 -Cover