HomeMy WebLinkAbout6.h. Change Order #1, Wensmann Pond Bank Stabilization, City Project #334CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE July 2, 2002
AGENDA ITEM: Change Order #1, Wensmann Pond Bank
AGENDA SECTION:
Stabilization, City Project #334
Consent
PREPARED BY: Andrew J Brotzler P E, City Engineer
AGEN f 6 r F
LL�IYY�I r �7
ATTACHMENTS: Change Order #1
APPROVED BY-
Included is Change Order No 1 for the Wensmann Pond Bank Stabilization Project The additional costs
encompasses the work and material needed to install a water level control device and stabilize all the erosion
sensitive areas of Wensmann Pond
Wensmann Pond is a regional stormwater pond where the water levels can fluctuate drastically Staff needs the
ability to control the water elevations during large storm events Plans were developed and awarded to Lloyd's
Construction Services to construct the telemetry system as part of the Pond Bank Stabilization project The
structure has been installed and the electrical float is ready to be wired into the system In addition, trees were
added around the newly installed structures to provide an enhanced look to the area.
Staff is asking that the Council approve the attached Change Order 41 for the Wensmann Pond Bank
Stabilization, City Project 4334
RECOMMENDED ACTION: MOTION TO APPROVE CHANGE ORDER 41 FOR THE
WENSMANN POND BANK STABILIZATION, CITY PROJECT 4334 AND AUTHORIZE THE
NECESSARY SIGNATURES
COUNCIL ACTION:
CHANGE ORDER NO 1
E
Wensman Pond Bank Stabilization June 26, 2002
City of Rosemount Protect No 334
WSB Protect No 1005 -29
OWNER
City of Rosemount
2875 145th Street West
Rosemount, MN 55068
CONTRACTOR
Lloyd's Construction Services, Inc
7207 West 128th Street
Savage MN 55378
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION
SEE ATTACHED DETAIL FOR ADDITIONAL QUANTITIES AND COSTS
IN CONTRACT PRICE
ORIGINAL CONTRACT PRICE
PREVIOUS CHANGE ORDERS NO_TO_
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER
NET INCREASE /DECREASE OF THIS CHANGE ORDER
CHANGE IN CONTRACT TIME
$98,09000
ORIGINAL CONTRACT TIME
7112002
$000
NET CHANGE FROM PREVIOUS CHANGE ORDERS
NONE
$98,09000
CONTRACT TIME PRIOR TO THIS CHANGE ORDER
7112002
$12,31600
NET INCREASE OF CHANGE ORDER
NONE
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERE $110,406 00 CONTRACT TIME WITH APPROVED CHANGE ORDERS 7/1/2002
RECOMMENDED BY
.���14"
Mark A Ertchson, P E
WSB 8 ASSOCIATES, INC
ENGINEER
APPROVED BY
CITY ENGINEER
DATE
APPROVED BY
x n T
Ltey .1 ms,1.^A-
LLOYD'S CONSTRUCTION SERVICES, INC
CONTRACTOR
F IWPW1M1005- 291ExceR1005 -29 VoucheACO -1
Change Order No 1 Detail
Wensman Pond Bank Stabilization
City of Rosemount Project No 334
WSB Project No 1005 -29
ADDITIONAL ITEMS
Total Additional Items $12,316.00
F IWPWlM1005- MExceA1005 -29 VoucheAC01 Detail
Extended
Item No
Description
Qty
Unit
Price
Amount
NEW
MANHOLE STRUCTURE
1
EA
$5,30000
$5,30000
NEW
SAND IMPORT
632
CY
$7 50
$4,74000
NEW
MANHOLE RE- CONSTRUCT
1
LS
$1,40000
$1,40000
NEW
TREES
4
EA
$21900
$876 00
Total Additional Items $12,316.00