EXECUTIVE SUMMARY FOR ACTION
COMMITTEE OF THE WHOLE DATE: July 10, 2000
Staff seeks council direction on the proposed remodeling of City Hall. There are three possible scenarios for
remodeling that will be presented at the work session. A cost estimate is included and a memo from Jeff May is
included on financing the remodeling.
If the City Council gives the direction to move forward the 2001 budget will be modified to reflect the change
and upon council approval formal plans will be prepared for the remodeling for work to begin in the spring of
2001.
AGENDA ITEM: City Hall Remodeling
AGENDA SECTION:
DISCUSSION
PREPARED BY: Thomas D. Burt, City Administrator
AGENDff 2
ATTACHMENTS: Proposed Plans, Financing Memo &
APPROVED BY:
Cost estimate
MEMORANDUM
DATE: July 6, 2000
TO: Thomas D. Burt, City Administrator
FROM: Jeff May, Finance Director
- SUBJECT: City Hall Remodeling
In looking at the funding for the City Hall remodeling, there are a few factors that should be
considered before proceeding:
1) There are.-3 years of debt currently left to pay on the original City Hall bonds
Year 2000- $ 5,833 (8/1 Interest Payment)
Year 2001 - $138,870 (2/1 P &I Payment & 8/1 Interest Payment)
Year 2002 - $138,038 (2/1 Final P &I Payment — Taxes Collected in 2001)
2) There is current and future funding built into the Building CIP Fund that could be used
for the remodeling:
Year 2000 - $ 64,400 for City Hall Improvements
Year 2001 - $110,000 for Lease - Purchase Payments on City Hall Improvements
Years 2002 & On - $110,000 for City Hall Lease - Purchase Payments
3) We are looking at issuing Lease Revenue(L/R) Bonds or doing a Lease- Purchase(L/P) to
fund the remodeling. At the end of 1999, 10 -Year L/R Bonds were estimated to be issued
at 5.5% and 15 -Year L/R Bonds were estimated to be issued at 5.75 %. 10 -Year or 15-
Year L/P's were estimated at 6.0% to 7.0 %.
4) The total cost of the remodeling is estimated at $2,000,000.
5) Annual payments on 10 -Year or 15 -Year financing would range from a low of $200,000
to a high of $266,000 if the whole $2,000,000 was financed. Those payments could be
lowered if a portion of the total cost was bought down. This has been discussed by using
water and sewer utility funds to contribute towards the cost of the remodeling. Another
possibility would be to use General Fund reserves to buy down the total.
y_
V
City Hall Remodeling Page 2
At this point there are different options that are available in proceeding with this project. In
giving these options, I am making the assumption that we are going to do our best at minimizing
the impact on the taxpayers. In making these assumptions I am also going to assume that the
Water Utility Fund and the Sewer Utility Fund would each contribute $100,000 and the General
Fund would contribute $300,000 to the cost of the remodeling reducing the total financing
needed to $1,500,000. Following are some of the options that have been looked at:
1) Proceed forward in 2000 and complete the project issuing L/R Bonds or doing a L/P.
First payment would not be until 2001 and we would use 2000 & 2001 General Fund
and Building CIP Fund monies encumbered/budgeted during those 2 years, to make the
2001 payments (adding necessary funding to the 2001 CIP to make up any difference in
final payment). The years 2002 and beyond payments would be made as part of the
Build CIP Fund budget and would increase the taxes for only the difference between
the lease - purchase payments and the $138,000 that we levied in 2000 for the final 2001
collection (2/1/2002 payment) for the original City Hall bonds. This is because the
original bond issue for the City Hall would be paid off and replaced by the levy for the
remodeling. This option would have as minimal an increase in taxes that I can see. Also,
we would look at the Water Utility Fund and Sewer Utility Fund each contributing a
yearly amount if they do not contribute a lump sump payment up front(much like the
Public Works building expansion project).
2) Get an estimate of each cost of the phasing that the architects have come up with and
incorporate those costs into future CIF's and pay for the project as we go. This would
be difficult to do because of the vaned phasing costs and could take many years to
complete. City Hall could look like it was under constant construction for 5 to 10 years.
At this point in time, it would appear to me that Option #1 above would be our best choice. We
would finance $1,500,000 to complete the work, issuing the debt sometime in the fall of 2000
and the first payment coming sometime in 2001 using funds budgeted/encumbered from 2000 &
2001. Years 2002 and beyond payments would be from Building CIP levies that will be made
that replace the original City Hall bond issue. The taxes should increase minimally for the
citizens because of the remodeling project.
F
Rosemount City Hall
Expansion and Remodeling
Budget Cost Review
7/7/00
Tom Burt, City Administrator
Robert Vanney, Architect
Todd Christopherson, Amcon
Costs are budgetary and are based upon preliminary drawings by Vanney Associates for Phases
I through Ili. Drawings Dated 5/8/2000.
Notes:
1. Remodeling costs for Phase I include sprinkler system for entire existing building.
Assumes adequate flow and pressure available in right of way near building.
2. Costs based upon similar materials, finishes, and systems.
3. Electrical upgrade in Phase I is sized for Phases 11 and 111.
4. All estimates are based upon 2000 costs plus 3% for inflation allowance for year
2001.
5. No winter conditions or soil corrections are assumed.
6. Estimates for Phases 11 and Iii assume they are done simultaneously with Phase I. If
done later, increase for inflation and for additional mobilizations and smaller projects.
7. Existing mechanical systems are assumed functional and are not replaced or
upgraded in these budgets. New systems are assumed to be similar type.
8. ' There does not appear to be any asbestos issue associated with this project,
however, an independent expert should evaluate this if necessary.
7n100 Rosemount City Hall
Expansion and Remodeling
AMCON
TJC
1 of 1
Jum 00 Cast Estimates - summary
t-
Area (SF)
Est. Cost
Subtotals
Phase 1
Lower Level
Garage
1,802
81,068
Existing Council Chambers
1,889
103,903
Remodeling
3,935
149,525
Upper Level
Offices over garages
3,245
415,411
New Council Chambers
1,540
184,800
,Remodeling
6,338
221,830
Site Improvements
120,000
Upgrade Electrical for all 3 Phases
35,000
Sub -total Construction Cost
1,311,537
Project bevelopment Cost
236,000
FFE
Contingency =
92,000
Total Project Costs - Phase 1
1,639,537
1,639,537
Phase II
Lower Level
Garage Addition
3,585
154,155
Upper Level
Storage Addition
3,585
283,215
Sub -total Construction Cost
437,370
Project Development Cost
79,000
FFE
Contingency
31,000
Total Project Costs - Phase H
547,370
547,370
Phase III
Lower Level
New stair to upper level
12,000
Upper Level
Finish Offices over garage
3,585
96,795
Sub -total Construction Cost
108,795
Project Development Cost
20,000
FFE
Contingency
8,000
Total Project Costs -
Phase N
136,795
136,795
f Total ftlect Costs
- Phases
&M
$2,323,702
AMCON
TJC
1 of 1
Jum 00 Cast Estimates - summary