HomeMy WebLinkAbout6.m. Receive Feasibility Report/Approve Project/Order Plans & Spec's, Wensmann 12th Addition Street & Utility Improvements, City Project #287 CITY OF ROSEMOUNT j- EXECUTIVE SUMMARY FOR ACTION CITY COUNCIL MEETING DATE: February 2, 1999 AGENDA ITEM: Receive Feasibility Report/Approve AGENDA SECTION: Project/Order Plans & Spec's-Wensmann 12th Addition Consent Street & Utility Improvements, City Project #287 PREPARED BY: Bud Osmundson AGENDA �� � 6 AA City Engineer/Public Works Director ��� ATTACHMENTS: Resolution, Feasibility Report Executive APPROVED BY: Summary and Drawin s The City received a petition for public improvements from Wensmann Homes and Chippendale/42 Partnership on December 1 , 1998 and a Feasibility Report was ordered. Attached is a copy of the Executive Summary from the Feasibility Report and drawings of the project. The proposed improvements include all the streets and utilities for 151 st Street West between its terminus east of Shannon Parkway and its terminus at Claret Avenue. Claret Avenue south of 151 st Street is still scheduled to be constructed with the Wensmann 1 1 th Addition Improvements as soon as weather permits this Spring. It also includes all of the private streets and the utilities within the proposed townhome area. The total estimated project cost is $621 ,500 which includes all legal, engineering, administration and finance costs. There are some costs as described in the report for oversizing which will be paid for from the appropriate City Water and Storm Sewer Core Funds. Originally Staff was planning to combine this project with the McNamara - Phase 2 (City Project #304) project and construct as one. However, due to approvals required by the County and MNDOT (County) State Aid, we are recommending this project be completed separately so that home construction can begin early in the construction season. Staff recommends that the City Council take the action as described below. RECOMMENDED ACTION: MOTION TO ADOPT A RESOLUTION RECEIVING THE FEASIBILITY REPORT, APPROVING THE PROJECT AND ORDERING THE PLANS AND SPECIFICATIONS FOR THE WENSMANN 12TH ADDITION STREET AND UTILITY IMPROVEMENTS, CITY PROJECT #287. COUNCIL ACTION: 6 CITY OF ROSEMOUNT DAKOTA COUNTY, MINNESOTA RESOLUTION 1999 - A RESOLUTION RECEIVING THE FEASIBILITY REPORT, APPROVING THE PROJECT AND ORDERING PLANS AND SPECIFICATIONS FOR THE WENSMANN 12TH ADDITION STREET & UTILITY IMPROVEMENTS CITY PROJECT #287 � WHEREAS, pursuant to the resolutions of the Council adopted on December 1 , 1998, a report has been prepared by the City Engineer with reference to the improvement of Wensmann 12th Addition Street & Utility Improvements, City Project #287, and this report was received by the Council on February 2, 1999, and WHEREAS, the report provides information regarding whether the proposed project is necessary, cost-effective, and feasible. NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF ROSEMOUNT,MINNESOTA: 1 . The Council will consider the improvements in accordance with the report and the assessment of abutting property for all or a portion of the cost of the improvements pursuant to Minnesota Statutes, Chapter 429 at an estimated cost of the improvements of 5621 ,500. 2. Such improvements are hereby ordered as proposed pursuant to a petition by the affected property owner. 3. The City Engineer is hereby ordered to prepare plans and specifications for the making of such improvements. ADOPTED this 2nd day of February, 1999. Cathy Busho, Mayor ATTEST: Susan M. Walsh, City Clerk Motion by: Seconded by: Voted in favor: Voted against: 1. EXECUTIVE SUMMARY �� The Wensmann 12`h Addition Project includes the construction of streets and utility improvements for a proposed Townhome development located in the southeast corner of the intersection of Shannon Parkway and proposed 151 S` Street, as shown in Figures 1 &2. This development consists of 12 acres and is the final residential project contained within the 80-acre McNamara Addition. The developer is required to complete the remaining construction of 151 st Street between Shannon Parkway and Chippendale Avenue,which is also necessary to provide access to a portion of this development. 151 st Street will be constructed to a 40-foot wide urban street consisting of bituminous pavement, B618 concrete curb and gutter, and five-foot (5') concrete sidewalks on both sides of the street. Utility improvements include the construction of a 12-inch trunk watermain along 1515` Street. Lateral sanitary sewer and watermain will be constructed to provide individual services to each lot. Lateral storm sewer will be constructed to collect street drainage for the proposed street construction. A trunk storm sewer line will be constructed through the development from 1515t Street to O'Leary's Pond which will serve McNamara Addition Phase II and properties north of CSAH 42. The estimated total project cost is$621,500 which includes a 10% contingency and 30% indirect costs. Funding for the project is provided from special assessments to the benefitting properties,McNamara Addition Phase II,and the storm sewer and watermain core funds. The final lift of bituminous is proposed to be constructed in the yeaz 2000 with improvements intended to be assessed in the year 1999. This project is feasible,necessary,and cost-effective from an engineering standpoint and should be constructed as proposed herein. Feasibility Report for the City of Rosemount Wensmann 12`"'Addition-Street& Utility Construction and Appurtenant Work City Project No. 287 WSB Project No. 1067.50 Page 1 ; 'Y ; �}i',�'" — j[ '? '� ' '' �1r =-� - �!i�t, � t-� ��+.�{��{ +tt rc E-R5�l�I€b:T �'i Y(�' � j �tl t� j� � ^�; _l t ( .e � � r'� � ' ` � - i f"� �` ; ;���`� :� ; �t� > t :� � : �.}t` � - - .�� ��� ' j� � �;� i � E3 � � ? � :� , `� _ �;��`�'i�' _ _ - j :�. f" �•i_f . , �� � ,�-, �� � �' � l�j c,. : �:� E � ,� .: � _-_ ,`1� } i��'��'� � � �k fx ���: " �4-��� - - ' ��. ' " I�•• � �'. . r�t l ,��`, ` `�51$�' _, . � y -� S �� : -, : yy���, , r : � "��l C� . . � �/ _ ` }��lti_��� � � '��1 ' <�t � � -{I..� ''� ' t ir, __L ^'� F �{ � ��'�+ v // + / l t / � ` [/ tp . �: 7 ���e � �� , ' i. '��- � 1 � , . � � � �� _ � ;� : t f � v w �: �{y. �. � r i � � � �^+ �� � � �:"L �:----' � � �- �.,, ;� _ � .�--: �,.,�i,, .�, � � ; �, _ . ` � � �� � �� �; 1 �t �.., �, ����- t ���`_�,,: ��� - �. � � � J ��•f}�= � � �_.-------� ��, t - � _._,.,,.� � . , : �tL� ; � �--�� � `����� �1'-'-- ' 1 t { �s�,'�� i DRA�IAGE d� UTIUTY EASEMENT �� '\ - - ` , � �i:}_ '' � i \ ' �_ ' � :" '� ri � 4 i � ----- _ — _ - . . � 1 ->-. ,s ,_„ � r ``*: � Q .: f " ; - ; ; � � �_ ! ,_ N}��� }2 � � 0����a���i.L.7��r'"t�t;�./ ' l:; �y'�� � � {. � > tf t V . 1 ` ��j�NL'Nff[� � f ?t(: �+�� �{ � .: �r' �� `�� t ' f ��R, .� ���... i . � � . :._ � �; � ,��'-'���� � t � `t ��: i F :r"�`�,: -� ' - f ': ', �l1 �1!: �� ��. `�R�aS�� � r� f y � - �t �- I�f' t� r 4 ( �` � 1 � h : �7 j... i' �L� �,.! �4 .t /� _ y r�! f ��i '�� - , � '� ==:, -�-``�=-�����-------T-_� =� x ix� �: �� t� ,,!� -.,( ':� }[���1 _� #r �,�i�: fia} : � t"� f # ; i�-,��� ` :� i ; �:' ` � ' � �4: jt � � . � ....1 1 .L � { F t � { 1 � l �• c i J �k4 }t ! - �� ` � . � ������ �,# 1 I�� � � ��; #� � -� $ �^ F ,� .�_�_}_� � - " �' � . _-� '_ r # t.� � �_.--::-, _ ' -; , � #i,. �� , � , �� t �. ;� f . �-ii "�`1 , . ;:-, � �. :�s��i . .C i . -t- . 3. .� . t. ����#�� � Project Location � � �; cr 0 250 S00 v h � Wensmann 12th Addition ��� ��•� ����� � � '60e�.�e�o�.wa Strcets,Utilities,and Appnrtenant Work � �sB �`'�D°`'�� . . Figure Number E � ��*� Prn�ect Locahon �I sndms be FN(6t1-1700 '�� � �"' � � Rosemoun Minnesota. 2 ' , • • 1 Wensmar�n 12th Addition . . 1 �► - Stre et & Utlll � � 1 `= � A urtenant Work and pp 1 � Ci Pro'ect Number : 287 1 �Y J ' for the City of �'�"`�' . "�� ' ' � �r� � ' * � � � \`1 1 � � � � 1 � .. ♦ � 1 ' WSB Pro'.No. 1067.50 Fe 2 1999 J ��'Y � Submitted to: ' City of Rosemount ' 2875 145th Street � ; Rosemount, Minnesota. 55068 � , - �o w�wooa�on� „��� saa�wayzaa ao�erar�d /, M�neapolia,MN 56426 ! ' 6t2-S41�800 � , FAX 541-1700 INFRASTRUCTUf� - ENGINEERS - PLANNERS ' ' , FEASIBILITY REPORT 1 IWENSMANN 12TH ADDITION STREET AND UTILITY CONSTRUCTION ' AND APPURTENANT WORK CITY OF ROSEMOUNT CITY PROJECT NO. 287 � ' FEBRUARY 2, 1999 � t ' Prepared By: � WSB & Associates,Inc. 350 Westwood Lake Office Park ' 8441 Wayzata Boulevard Minneapolis, MN 55426 (612) 541-4800 ' (612) 541-1700 (Fax) 1 ' ' City ojRosemount- Wensmann 12`h Addition ' St�eet and Utility Construction ��+ Feasibility Report-City ProJect No.287 �i,7B WSB Project No. 1067,.SO ��„�!,,� ' ' - B.A.Mittelsteadt,P.E. 350 Westwood Lake Office Bret A.Weiss,r.E. II���� 8441 Wayzata Boulevard Peter R.Willenbring,P.E. ' Minneapolis, MN 55426 Donald W.Sterna,PE. Ronald B.Bray,P.E. 612-541-4800 ' &Associates, Inc. FAX 541-1700 ' February 2, 1999 , Honorable Mayor and City Council City of Rosemount 2875 West 145`h Street ' Rosemount, MN 55068 ' Re: Feasibility Report Wensmann 12th Addition Street & Utility Construction and Appurtenant Work ' City of Rosemount Project No. 287 WSB Project No. 1067.50 � Dear Mayor and Council Members: On October 6, 1998, the City Council authorized the preparation of a Feasibility Report for the , construction of streets and utilities to serve the Wensmann 12`'' Addition. In accordance with the Council's request, the report has been completed. ' We would be happy to discuss this report with you at your convenience. Please give us a call at 541- 4800 if you have any questions. ' Sincerely, WSB 8t Associates,In . ' 1 7 - ' Bret A. Weiss, P.E. Vice President , Enclosure , nm/sm , , M i n n e a p o l i s • S t . C l o u d , Infrastructure Engineers Plunners EQUAL OPPORTUNITY EMPLOYER ' CERTIFICATION ' ' � ' ' ' , I hereby certify that this plan,specification or report was prepared by , me or under my direct supervision and that I am a duly Registered Professional Engineer under the laws of the State of Minnesota. ' �i , Br et A. Weiss, P.E. , Date: February 2, 1999 Reg. No. 20753 ' ' , ' ' , City of Rosemoun�- Wensmann 12`"Addition : , Street and Utility Construction " IA,�O Feasibility Report-Clty ProJect No.287 ���� o WSB Project No. 106�SO ��� ' ' ' TABLE OF CONTENTS TITLE SHEET , LETTER OF TRANSMITTAL CERTIFICATION SHEET TABLE OF CONTENTS ' 1. EXECUTIVE SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 ' 2. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 2.1 Authorization 2 2.2 Scope 2 ' 2.3 Data Available 2 3. GENERAL BACKGROUND . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 ' 3.1 Project Location 3 3.2 Project Zoning 3 3.3 Existing Conditions 3 , 4. PROPOSED IMPROVEMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 4.1 Street(See Figure 3) 4 ' 4.2 Site Grading 4 4.3 Storm Sewer(See Figure 4) 4 , 4.4 Watermain 5 4.5 Sanitary Sewer 5 4.6 Sidewalks and Trails (See Figure 3) 5 ' 4.7 Private Utilities/ Street Lights 5 4.8 Permits/Approvals 5 4.9 Rights-of-Way/Easements 5 ' S. FINANCING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 5.1 Opinion of Cost 6 , 5.2 Funding 6 6. PROJECT SCHEDULE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 IFEASIBILITY AND RECOMMENDATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 ' APPENDIX A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Figures 10 ' APPENDIX B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 Opinion of Cost 16 ' ' City of Rosemount- Wensmann 12t°'Addition - Street and Utility Construction ��+� Feasibility Report-City ProJect No. 287 �■� , WSB Project No. I067.SO � ' 1. EXECUTIVE SUMMARY ' The Wensmann 12`� Addition Project includes the construction of streets and utility improvements for a proposed Townhome development located in the southeast corner of ' the intersection of Shannon Parkway and proposed 151 S` Street, as shown in Figures 1 &2. This development consists of 12 acres and is the final residential project contained within the 80-acre McNamaza Addition. ' The developer is required to complete the remaining construction of 151 st Street between Shannon Parkway and Chippendale Avenue,which is also necessary to provide access to , a portion of this development. 151 st Street will be constructed to a 40-foot wide urban street consisting of bituminous ' pavement, B618 concrete curb and gutter, and five-foot (5') concrete sidewalks on both sides of the street. ' Utility improvements include the construction of a 12-inch trunk watermain along 151 S` Street. Lateral sanitary sewer and watermain will be constructed to provide individual services to each lot. Lateral storm sewer will be constructed to collect street drainage for ' the proposed street construction. A trunk storm sewer line will be constructed through the development from 1515` Street to O'Leary's Pond which will serve McNamara Addition Phase II and properties north of CSAH 42. ' The estimated total project cost is$621,500 which includes a 10%contingency and 30% indirect costs. Funding for the project is provided from special assessments to the ' benefitting properties,McNamara Addition Phase II,and the storm sewer and watermain core funds. , The final lift of bituminous is proposed to be constructed in the year 2000 with improvements intended to be assessed in the year 1999. ' This project is feasible,necessary,and cost-effective from an engineering standpoint and should be constructed as proposed herein. , ' ' , ' � Feasibility Report for the City of Rosemount Wensmann 12`�Addition-Street& Utility Construction and Appurtenant Work ' City P�oject No. 287 WSB Project No. 1067.SO Page 1 , 2. INTRODUCTION ' 2.1 Authorization On December 1, 1998, the Rosemount City Council authorized the preparation of a , Feasibility Report to address development-related infrastructure costs attributed to the Wensmann 12�'Addition townhome development. This project has been designated as� , City Project No. 287. 2.2 Scope ' This project will complete the utility and street construction of 1515` Street, along with the construction of street and utility improvements for the Wensmann 12`h Addition ' townhome development,located in the southeast quadrant of Shannon Parkway and future 1515t Street, west of proposed Claret Avenue. This area is identified as Outlot E of the McNamara Addition. Wensmann 12`�Addition consists of 44 townhome lots. , The proposed improvements include the construction of streets,storm sewer,watermain, and sanitary sewer. A large diameter storm sewer that serves the McNamara Addition ' Phase II and property north of CSAH 42 is proposed to be extended through the center of this site to O'Leary's Pond. All site grading will be completed privately as a part of the grading activities directed by the developer. ' 2.3 Data Available ' Information and materials used in the preparation of this report include the following: • City of Rosemount Record Plans for adjoining properties , • City of Rosemount Topography Maps • City of Rosemount Water Supply and Distribution Plan , : City of Rosemount Storm Water Management Plan McNamaza Addition Phase I Plans and Specifications • Grading Plan by Ryan Engineering ' • Wensmann 11`�Addition- Plans & Specifications � ' ' ' ' Feasibility Report jor the Ctty ojRosemount Wensmann 12"'Addition-Street dc Utility Construction and Appurtenant Work ' City Project No. 287 WSB Project No. 1067.SO page 1 ' 3. GENERAL BACKGROUND ' 3.1 Project Location Wensmann 12`� Addition consists of a 12-acre parcel located in the SW '/4 of the ' McNamara Addition, bounded by Shannon Parkway on the west, future 151 S` Street on the north, future Claret Avenue on the east, and O'Leary's Hills 4th Addition and , O'Leary's Pond on the south. 3.2 Project Zoning , The project area was zoned agricultural until March 4, 1997 when the zoning for the McNamara Addition was changed to a mixed-use Planned Unit Development(PUD). The ' property was re-zoned to R-2 with the Wensmann 12`h preliminary plat. 3.3 Existing Conditions ' The project area is currently being graded by the developer. T'he terrain generally slopes and drains towazd the south into O'Leary's Pond (Pond WA -P600), located in the ' northwest corner of the O'Leary's Hills 4th Addition. The properiy is close to transportation services with Dakota CSAH 42 located to the north of the property, Shannon Parkway on the west, and Chippendale Avenue on the east. ' , ' ' ' ' ' . , ' ' Feaslbility Report for the Clty of Rosemount Wensmann 12`"Addition-Street& Utility Constructlon and Appurtenant Work ' City Project No.287 WSB Project No. 1067.50 Page 3 ' 4. PROPOSED IMPROVEMENTS , This report addresses the development of the street and utility improvements necessary to serve Wensmann 12�`Addition. There are additional street and utility improvements , sunounding this project that will be addressed within the McNamara Addition Phase II Feasibility Report or with the Wensmann 11`�'Addition Project. , 4.1 Street(See Figure 3) Proposed street improvements include the construction of 151 st Street between the ' existing street stubs constructed as part of McNamara lst Addition and Wensmann 1 lth Addition. 151 st Street will be constructed to a width of 40 feet, with a street section consisting of four-inches (4") of bituminous and eight-inches (8") of Class 5 aggregate ' base. The proposed private street system to serve the townhome units will be constructed. The private streets will be constructed to a width of twenty-eight feet(28')with concrete curb and gutter and a street section consisting of four-inch bituminous and six inches(6") , of Class 5 aggregate base. 4.2 Site Grading , The proposed site grading activities are currently underway and are funded privately by the developer. The grading will be verified for conformance to the approved grading plan ' during the design phase of the project. 4.3 Storm Sewer(See Figure 4) ' The storm sewer for this ro'ect consists of rovidin lateral service connections to P J P g accommodate site drainage. Ponding for the site will be completed as part of the grading ' operation including Ponds WA-P2439 and WA-P600. It is anticipated that the pond excavation will be completed prior to the start of street and utility improvements. ' Lateral storm sewer systems to serve the development area will be incorporated as part of this project. A portion of the lateral storm sewer system connects to an existing trunk ' 30-inch RCP line that was constructed as part of the McNamara Addition Phase I. The other lateral storm sewer system will discharge directly into O'Leary's Pond. , A proposed 33-inch trunk storm sewer line, which serves the McNamara Addition Phase II and property located north of CSAH 42, will also be constructed through Wensmann 12�'Addition and will discharge into O'Leary's Pond . , Ponding: Development of the ponds along the south side of the property has been coordinated with the developer to determine the best method for conforming with the ' development plans. The storm sewer system may be adjusted slightly to accommodate any modifications to the completed ponding construction. ' ' Feasibility Report jor the City of Rosemount Wensmann 12"'Addition-Street& Utility Construction and Appurtenant Work , City Project No. 287 WSB Project No. 1067.SO Page 4 ' 4.4 Watermain ' The watermain improvements include the construction of a 12-inch trunk watermain along 151�`Street,completing the connection between Shannon Parkway and Chippendale ' Avenue. Eight-mch watermain will be looped through Wensmann 12`� Addition from Claret � Avenue and will include two(2)connections to the watermain located within 151 S`Street West. ' 4.5 Sanitary Sewer The Wensmann 12"'Addition is proposed to be served by the extension of an eight-inch ' sanitary sewer system from the existing eight-inch sanitary sewer constructed through Outlot E during the McNamara Addition construction. An additional connection to the Claret Avenue sanitary sewer system will be necessary to accommodate a revised ' townhome layout which differs from the original design. This sanitary sewer system is connected to the Empire Wastewater Treatment Plant. (See Figure 3) ' 4.6 Sidewalks and Trails (See Figure 3) The proposed improvements include the construction of five-foot (5') wide concrete ' sidewalks on both sides of 151 S` Street. No sidewalks or trails are proposed to be constructed through the townhome development as part of this project. ' 4.7 Private Utilities/Street Lights ' The development will be provided electrical power by NSP, phone service by Frontier Communications, gas service by Peoples Natural Gas and cable television by Marcus Cable. Street lights for the improved streets will be provided by the developer as ' determined by the City and NSP. Standard residential street lights will be provided within the development, as necessary. , 4.8 Permits/Approvals Permits will be required for this proj ect from the Minnesota Department of Health for the � watermain extensions and the Minnesota Pollution Control Agency for the sanitary sewer extensions. In addition,the approval of the sanitary sewer plans is also required by the Metropolitan Council-Environmental Services Division. � 4.9 Rights-of-Way/Easements ' Proposed roadways are private, therefore no right-of-ways are required. Right-of-way dedication for 15151 Street and Claret Avenue is already in place with the McNamara Addition plat. All utilities will be located within provided easements. The final plat, ' which will be approved by the City Council prior to construction, includes all necessary easements. ' Feasibility Report for the City of Rosemount Wensmann 12`"'Addition-Street& Utility Construction and Appurlenant Work ' City Project No. 287 WSB Project No. 1067.SO Page S ' S. FINANCING ' S.1 Opinion of Cost A detailed opinion of cost can be found in Appendix B of this report. This opinion of cost , incorporates anticipated 1999 construction costs and includes a 10%continency factor and all related indirect costs. The indirect costs are estimated at 30% and include legal, engineering, administrative, and financing items. The summary of the total project cost ' is as follows: Total � Surface Improvements $233,200 Sanitary Sewer $110,300 Watermain $143,500 , Storm Sewer $134,500 Total $621,500 � The above costs do not include site grading. All site grading will be completed by the developer prior to the construction activities contained herein. , 5.2 Funding ' Funding for the project will be collected from special assessments to the benefitting properties,and the storm sewer and watermain core funds. There are also improvements to 151 S`Street and Outlot E of the McNamara Addition as part of the McNamara Addition ' Phase II project,that will be assessed to Wensmann 12`''Addition. The funding summary for costs associated with 151 S` Street and Outlot E is as follows: ' 151�STREET-STREET&UTILITIES OUTLOT E STORM SEWER CTTY PROJECT NO.287 WSB PROJECT N0.1067.50 , FUNDING SUMMARY MCNAMARAPHASEII WENSMANN 12TM , 151�STREET OUTLOT A OUTLOT B OUTLOT E STORM SEWER , CORE FfJNDS ' WpTERMAIN � COREFUNDS FRONTAGE FRONTAGE FRONTAGE FRONTAGE '� 151ST IS1ST 151ST 151ST ' 270.00' 415.00' 680.00' 00.00' STREET 516,378.02 525,171.48 E41,251.42 50.00 WA1'ERMAIN 54,849.42 57,453.11 512,214.27 E0.00 E1,809.50 ' ____ __ _ STORM SEWER 58,01495 512,318.23 520,18730 521,274.11 ', TOTAL E29,39339 545,093.82 573,803.99 521,425.11 ', 51,809.50 , OUTLOT E STORM SEWER STORM SEWER TOTAL 54,475.60 56,878.57 511,272.72 513,379.08 � GRAND TOTAL 533,868.99 S51,972.39 S85,076.71 S34,804.19 S1,809.50 , Feasibility Report for the Clty of Rosemount Wensmann 12`�Addition-Street& Uti[ity Construction and Appurtenant Work , Ciry Project No. 287 WSB Project No. 1067.SO Page 6 , Project costs associated with the streets, watermain, sanitary sewer and storm sewer construction to serve the development will be assessed 100%to the benefitting properties. ' The total cost of this item is $413,847. The developer is responsible for an eight-inch diameter watermain and eight-inch diameter sanitary sewer to serve the residential property south of 151 S` Street and west of Claret Avenue. The watermain construction � along 151 S`Street will be assessed to the adjoining property owners,with the City Water Core Fund paying for one-half of the oversizing for the south side of 151 S` Street. ' The project costs associated with the storm sewer improvements will be funded by the developer with the exception of the 33 inch system from 151 S`Street which will be funded by McNamara Addition Phase II and the City of Rosemount Storm Sewer Core Fund. ' The ro'ect costs associated with the 151�`Street constru i p ,1 ct on were agreed to be divided ' equally between McNamara Addition Phase II and the Wensmann 12`'' Addition and, therefore,will be 100%assessed to the development equally to the north and south sides of 151St Street. The project costs associated with Claret Avenue construction will be ' directed to Wensmann 12`� Addition and constructed as part of the Wensmann 11`n Addition. , Proposed assessments to the benefitting properties are as follows: A summary of the proposed costs per townhome unit is as follows: , $413,847 + 85,077= $498,924/441ots = $11,340 /unit ' This does not include assessments from McNamaza Phase I and Wensmann 11`n Additions. ' � ' ' ' ' ' ' Feasibt[ity Report for the City of Rosemount Wensmann 12"'Addition-Street& Utllity Const�uction and Appurtenant Work ' City Project No. 287 WSB Project No. 1067.SO page 7 I6. PROJECT SCHEDULE ' The proposed project schedule for this improvement is as follows: Order Feasibility Report, Plans and Specifications . . . . . . . . . . . . . . . October 6, 1998 ' Receive Feasibility Report/Order Public Hearing February 2, 1999 . . . . . . . . . . . . . . , Receive Plans and Specifications/Order Ad for Bid . . . . . . . . . . . . . . . March 2, 1999 ' Receive Bids . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . March30, 1999 Award Contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . April 6, 1999 ' Begin Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . May, 1999 ' Substantial Construction Completion . . . . . . . . . . . . . . . . . . . . . . . . . . . August, 1999 Assessment Hearing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . October, 1999 ' Final Lift of Bituminous . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . June, 2000 ' • This schedule is contingent on the developer completing site grading activities. Any delays associated with the site grading operation or other issues outside of the scope of ' this project will require the extension of the above-noted schedule. • This project was proposed to be completed in conjunction with the McNamara Addition ' Phase II project. However, due to design related issues with the McNamara Addition Phase II project , it is proposed that this project be bid separately from that project and constructed independently. ' ' ' ' , ' ' Feasibility Report for the City of Rosemount Wensmann 12`h Addition-Street& Uti[ity Construction and Appurtenant Work , City Project No. 287 WSB Project No. 1067.SO page g ' 7. FEASIBILITY AND RECOMMENDATION ' City Project No. 287 consists of the development of streets, utilities, and appurtenant work to accommodate the proposed Wensmann 12`''Addition. Included with the project improvements are sanitary sewer, watermain, storm sewer, and street improvements, in ' accordance with the City of Rosemount's comprehensive plans. ' It is the recommendation of WSB&Associates,Inc.that City Project No.287 is feasible, necessary and cost-effective from an engineering standpoint. We recommend construction of the proposed improvements as detailed in this report and phased according , to developer desires and City requirements. ' , ' ' , ' ' , , ' t ' ' Feasibility Report for the City of Rosemount Wensmann 12`"`Addition-Street& Utility Constructton and Appurtenant Work ' City Project No. 287 WSB Project No. 1067.50 Page 9 ' ' , ' ' � ' ' , APPENDIX A Figures ' , ' ' ' ' ' ' ' Feasibility Report for the City of Rosemount Wensmann 12`�'Addition-Street& Utility Construction and Appurtenant Work ' City Project No. 287 WSB Project No. 1067.SO Page 10 , n' n � 4 ' ' ' ' �� M� fl����w'��.�r � .r��'rw�nr��i���+�-� r-�� : NWiY�slbiC� ND '11CM1rA[ N9-.�12� � , � � T � ^` — — ( ` " } - �--���r.�s.a�-�! `^-�r,. .:�� ��:�...,« ": }*"�.^..,. ,� t..+�.�+c�� t � �� � 1� ��F ;�( � � ^��� � � � j � � �. , � �li .. . II} ►.► . ' ' t<li +� � � � ,� . q ou��.or� ��� orrrto�e }�1 i � +a�t�s'°t c �`� ��' { � �r � � i , ,. ����� . 1 � .F`-�i� �� 1 , �, i f FF � � �, �t� �� ` � � ri� �,. �_��_�_�. ! � j) . �r.� t E . : { a. F r���i.�'^^�,,,...�::..� } � .,_ . �� � , y� _�l� �.���.�.<�;,:.__ �� r �� �s�l ��,,.�'�`��" � � , ' �..:.:��--_-_�� _�--� _t�__ � t �.� .x : � . 1/�l- -"'_ ��.- _�--- -�,��,�►=�'-<�-�'� � i , � .�+aar'-� � �. ^�T,a,"' . . �r'"^' ,,,,.�. � '� �� � � ����� � �� �,# �'� OUiIOT E � ��� �` � � E ' ! � ��� ou'tt.ot f > � # ; ! f 1 _---, ���t � a , i�� •—���.�, ��� t�;�. t � ' i �J_ --------�=____—_��.�:.. __,�..�..�. __�.�,_�_J{ ��� } �!� ; � , � ►,�:t 1 � �`�'+��+��# �.�`��1�l� ' � � . _ . . _ r � � ���� Wcnsmann 12th Additioa wse�peawo. �art•so o�:�wn2,�s� � � e�.+wn�.ear�a Strects,UWitiee,aad Appurtena�t Work � wm�..�w.,�n+sarle � s,�.,-� Project Location Figure Number ��� F,���,� �'�"� � �°""�' - '� Rosemoun Min.nesota. ' � Y p t�:: - I�� � � , � .� � V '}�} ���� ,��t � � � � ���-. �1 tµ � � �� ��` 1 } � �_ '�.:� �,'�, �1 Y� �I � , ' '�'# f � i:� � � {`t d� i �_ �-��t-}�; � ' �. � : < < � # 1 � , � �j � c � a t , a�t t; i•�� i _. �1 F-� F_: � �4 {��'�j`_4 t��'3 - - ��� �r�; r�'' �� � � �t"-}1 � LT. I (1; j } � �� t � t �� �� ,Y� I '1f i � - - - � �"'�� ��� � �� �j�G.,1� '�^� r��; r '° `J�'' ' 1f � .,`_"~�.,.y'��'' f r � .` . +. ... ��4 k _�.�.'.� 1' .v-i-�Y'{ . Y;-�-�4--�� f-,�J�- � 1 � l�-i.'� ` � ' _ �r � �"` ,. -,�,_„�_`�-�.�j,,� _ ' 75y5,�, � ,� ; - .:�-�.r::.:�-� ' �,_- .,�'�� S i '; _ �. , � ..��'. ,�r E ,�� �-� �----�---� I � �``'--��--�; _ .. ,� ,r � ' � j � ' - ._ � .�"'�—__ ;r r�\: i c� � � r � I � � , `�.-,,.�" �^------� ' � , �- ,, ,�—'--=._� _ �._= j ,""," �: j 4 }t � / �i ,^`--.� `��, /�. � ! ,^ ^\ {' �. aJ ,� 1���/ i ��� �I �' �� --{-1 ; - ; /,''`1� {t �-- ,y �l3� # � y.:. ? �r,..a.�� / �1 1� , I r� �� � f�}/t.,� :.�� +t; � ' �- �� � ,/��wC � "11'�� y � � �- • ����.' �. �{ i r�F i \\.\ �l � '�- t'--.-.---.�'�'.�y`a.,�i ✓; `� � A �t �t, :� --� ,— A �, �, � � � ��� �`�"'� �. � �• �\ �- i � ti � . ' , `;l� i '� w. i_ 1 � a ���' �r--� ��� ' 1 t ` : � �� ;i �� 1� _r� ��—� � � � I �. � '���----� — � � , � � a �� , ---� . '1 � �.:� �� _�_---s '\;��, � � �j ,- � � . ', ' � ' :p; � �' ij �^ _\\ �� \1 g� ✓'' .' l\ ' � U \R j �� ! �;r�:� //L __—__,\\�` \�,'/ , \ , ''\ � ' �• \\`����\� �f � �� t� ��� ���— —������, � A • ����. � � � y �� , ' '` ' ! � � �_.:..�:.,N-. td �.�� �i—�' -..� ��,� ._._ ._�i'� _ � , ���`/� � �t �, (i i�� � DRAINAGE & UTIUTY EASEMENT `� � _/ s �,-i , ?, � z�r c�r� '" i�i�t j'Q. / �C --- ' ' � —=L- ,� � -�anra�Pnwc�w►��` � � -��_- -�-�-�- � -�. N ________ -_ _ '_ _�__ _.� __ -� ^�- � ��_ 11 •� � __��___________^ .��_ �_ ` _ �_ __��r � �_-----� , L��; ----�, ��y.,_ � ;;'--_---_ i 1 � �r �� '� � ,�; ' �_ — — _ - — � � � � (/ �`�,� '� �" i ' � ` �^ ''�\ �h I I I � I ( I j �� � � � � I �� ' r g\ ,'' � � _.._�—� I I I � �— yt � � I I ' I � \ �� � � �� . � ' i `� � � 1�.' �� � � i i �� ,i�j.,' '----..;, y � __ -- ' �-==�'- ' ; _ —�.—_�,._� � ; ) V��� "J, �� �`F C�$,VIEYI,AVENl1E I � / �� vf j-"� � / � 1 ! � � �, 1 � � � , , ; ',�.r ��/-Y�� �, � �y , L;I , � �� /--•. •�,/ ' i `�� ���� l:RE8f0lEAVBlIE ����—� � /`� ������ � — -----___—�-- -� -+ "_ -- �__;—_. �j � � / �- -� -—�-� - '�---��---'— �-'-�—�-. '!/`\ I / C� �^� , °°'a - �Q--y--- �--�--- , \\ ' ` __�-__*__.- _'L-_' /I�� \� \� \ � � \�� ��� I � � 7 //) ��\\ I � \�'�/� � �� bi -`i L �`� ' �`�' %; �,' �-i J�`� �e �-���` , �� ( I � I `` � ' '�� �' ��'� ! � � ' / � \ � � % ' r } ` � � �� �1 � ��i' J ; i � ,� •C'� S � � � , � � �, __ , � �,�., � ii „w_ -„� " � i � � �� i � �i � ��.,_—_..� `Z i� \� i �� fi� ,l \ � �ar� ' � � �� � � :, i i, .,,�-'r '.' /, eo�ww +'"----- \�� � �'• ' �� e�wwc ' ---�-__�_-___--,__`. �� j��` ` \\�/, �1 � '���-�--i----,; � ; , -�---� � � , - _--� , , ����� �� _ � � � 5 I{ .,✓ �:; _�_�, .,, �( � _ � i� �� =�' �� � 'I ----�-_. ,. , �,,� ,, , . � ��=—� «_=� _ �,- . ,� ��� �i `_'---_-+_`—�- _ _ -' �, ! ii ' �'I � lC ''� ' f� �Ii i{ _�, �i i � i! ------------� --+ ----T--�----� �j,�- a�-----�-----r;�----^-� --- i_ � � � 1 1 �—"'_._'- —_e`_ � ` ` _ +� —' �' � I �___ �"` ' ( I � 1� l � _ '�_._'-�_.=��.'Y-='_`_ '- � � �'. `.� _��.-�� T I 1i ��_",:.�Y= _.�-"_ ____ -� � ___-=; --- � I 4, � 1- .��"__�_--Av� �__� -- ' ; � ,��1. � - I 1 I I i'�t,..� ' i 'i ',�� "��� ,� � � � o ,00 zoo i Weasmann 12th Addition wse a�xt Ho. �asr•�o o.�r�ry z,�eeo � ��� s+� w,�eoW.r.�a Str�ets,Utilitiea,and Appurtenant Work � �rrw.pa.,�asris 01�"'�0° Street Conatruchon Figure Number �� F�c+,.,mo 3 �""�°� � � � ''`� Rosemoun Minnesota. � ' � ---_— ----- P�acuw i __ _, _ � , I �►wrn°" �-T �� � _� i � N I � _ - 11 jI'—� 1 ---------�^\- __� `; �� -. ..� ' r �� �1 L__(�I - _,__._� . /�Z, \ � ' ---- � j � / ����� �� ! �� � f- — _ _- � �—�J � �v� �� � I � 1 I i ( ;`� �' '� -` �1 i� I ' � i i 1 � � fig ��, i� ;� I ��' �- ,- � j ���! � � I , � ,� i--_--- ��� � i � ` � ', �- - . . � � ��-� �'< < � ; � — ' ' O'LEARY'S P�3ND \� ` �"� - ��� �, —� — , � I #WA-608� �` j ��� , � ����_ J , ; , �r , � � , 1 � i % ,� �,� , �� , � ' , ,e� 5,��. �- / �� ; � � `� ` L�� J 1 i l��` ^`�. ~�� \�J I ' � � � i ``. ` ' �{ � c�sro��va�uE , / �� j {� - ---- ------- -�-•_-� ``� \' � - `�.,_.�_ _`.�;� -I- ~«-__"__-_�-��-" //.\ i <� �. _ -Q-----------._...�---- 1 fi' . \� � � l`,� }..� , --�------------�--- � . \ � , � , . ., , { � �� , i�' ��' ` ' f/ `�� L.`-J !z �� « f'\` �� i��\ � � �: , 1 �e 1 ,�� �; � / t I � %''~1 '%'" � ' � ' I � , � I '� f` sr ,' � � i� ,� ,,,r� ' � C, � � � ' .��, � I� � ��-�� �_._ � ' , � � ! �•,\ � � �I � � " �� � '�., �i ,� .^� ! �� I I� �� ;���� � � ��. i �I . �'� �� � �� i I . \ JI_______ `.� 'I �C i 1 y� \ �I � f � \\�' r �---�--__, %/,� , - i� �;�, � ��-y-��� ; i �� i i ; y , `\;�j ;:��-:��.� '� i� , -1------L__ �� ✓ �i�"; ��" �� �� '! c�_ .�— ,.�;.� 'i ,�.. i �!'-��_ ——«-�� ,_,,,�� i�� �� i 1� 1 y----=-+�`"---- �1-_ � �' � � 1� I� I I i I{ ' `� -/I J� ' I� i�! i! ------------I-�-- --+ --- � �� � a�------------- �-� ---- --- � -i-----4 "�`, ` =f�rly��.�=-�' «.. � 1 � I � _ .+____�_ _ ' � �� k1 ��__ ---`___=--'--_-_� -�_ ---� � I � 1� 4.-- ��:_ �= _ _--. '# A-2 9 �; �1 1- `+�---���'_..�--� -- t1 � j ���-�_ - 1 -- � � � -� �;,r.�',, � � _ , � o ,oo zoo " W�nsmana 12t6 Addition v�e�►+0. �asr•so oa�:r�,nwr2,�eeo _ ��� e�. +n�we«,�a Streeta�,Utilitiea,nad Apgurtesant Work r M�rr�poU,1�IN 66{26 � „�,,�, Figure Number F �— F�xsr+-,�oo Storm Sewer "F""$""'� � � � '� Rosemoun Minnesota. 4 � ' � --=L- � �a�aww P�nKw��'- i� N �r -"T >_ > � 7 ` _------ -- �- ---- --=- -- �- •_, -- 11 i i ------ .._ _- `` .� _ �....__ ' ' '��) _"`____-� �`� ^�� �I� � \:'�-___._—`�=___ i' � �_J ; � �5^':•�� �, '1 � I f`- --_ ___ -- � i 1 / �� � P-��.,, i ' � �✓ �� I � � 1 I� 1 � � '� l v � "�� I ,i � j � � � i ��, , ' I_—o___J � 1 I ' � � �' . I � �, ��=� _ I � � ` �.�,.,/�• + "�W�L J Y � 1. ' ' ' ' �' r �E _ __�-�_�,�,_:�� 1 ' /�"/ ��� ��� �,,� � ' �' 1 ��� �.1!_�� � � y � //� � ����I� �r' ; i �' �"�� I �N�\� ;- trwA7ERYNN , � / , �� ti,� ; � ��. ,_ ,,f �, 1 � � � � � c�stonE�vewE \ a�vw�awx+ � ^' , {� - __-�._.�_�_.__�.T_-� , 2 ` /_�.� \ J a - �<` __" '.��-.__�,��_' � \ I / /I�`\ �/ .~ ��ai ��� � � --�--�L___�___�—�_ ��-._.�' � \ ` 1 i /// \\ // \\� � __l_'_�__._'__�__—_�—__ //� \ \ �\ � / \� �� '� 1 ��/1� ��.� \� /! �\�V �_ ' a �,/, � � '�\ I� �/li �✓ � R i����'� !� ! � �� � 1 � ' l 1 � / � yI • �� � ,� 1 � \�, l i 1 i i' ��� ,,.r�, ` ' � , ' /\ \`� i �! / � ,�� `Z > r i ��� i I� "\ '' i i �� � �� 'I ! �` i �� �. y� 'a� \ �' � �� ��'� y �I__-_--„\___� �� \ '�,/-'/ �- ' i� I `%�� �,.,�\� /----�. � - � 8' ARY \ �,_ \�-' i"�►-----+� � 1 I � � I� `���,.;- ::;;-.;.�� �I -�_ i� � :�- ► '! � ��,{� ; _ -L-._ <�;'P�I�c`'" �� I�:. I �.��_�� �- i �� +:'-�."�-.F -",-__ �- i'� 11 'j 1� �--�--+--_-_.+__ - - . � � ' *-` I� � � �f I\I .D---'� .'� ' �� �,� 1{ -------------� --+ --- � i , . ---- __ � � ( ��------- - _«`-� —�--------�� I , ��r===��_;�-- t r�' ��' �r _�-_- _.._�-�—> «. ' � 1 �����`�r��'�-- '�..�- ��—�-�`__� �` �� �1'�`+�.-�---___��v� � I t��'��'1 -- ' I ' ,� "�,. ,} __, ' -- I � � i „t �1 � � �; � � ,�� 2�� v Weesmsun 12t6 Additioa ���. +�.� o�:�.r�,+9ae � ��� ea wh,�+eo�rswa Streeb,Utilities,nnd Appnrtenant Work � IAYrwpols,MN b6�Z6 ��� ��,� Ssnitsry S�wer/Waterm�ia F�9ure Number �""s'"`�"� � °'�" " `� Rosemount Minnesota. 5 � ' ' , ' ' ' � ' , APPENDIX B Opinion of Cost ' , , ' , ' , , ' Feasibiliry Report for the Ctty of Rosemount Wensmann 12`"'Addition-Street& Utility Construction and Appurtenant Work ' City Project No. 287 WSB Project No. 1067.50 Page 16 ' � � Sp Bp S � � Sp � � S �p � S S S S�p � � V�i Op O O S O 1� O � Sp pS � � N Y V � ti 8 ��$` O OtV „ �n O N N � b Y N< Q N � N Q v�i P Q�$ � O V�l P O 8 N r n b � = 1 �� 'H N N N N �H ��} N �(� ry�(N� ��p N N ���.j� � N � N N � N O O N O Y O e� e� �0 O l •h F�i� � N N H H N N N L l M H M � N ~ � H N � � .l�-i � � CS fj 'V N N H Yf n ' O S O O O O O O � O O O O O O O � r O O O O O t� O O O O O O O O ` S 1� .� `G 00 O t�f ^ Np N p N t� P O �+f o�p N .-. N Y N O O O O Nf O ��.� I� N v� fV � O� O� < Y N N � N �D N O M I � ' g OSB � f�,l � � o .y.� � a a =F O H N y H H N , V O I I � i o �_,+ W � I I a�t � stl , � ' o� I Ili i f � 8.1 sssss ss ss s8 � s. s s � � o ^ � N I I M N 00 W < � � I a�0 � N � Q � � N Q p V I�I b I�� QI fVI .-: H � ' r HH HMNHN � H � HIHH ' Tq(�U N H N N H .�. M � N t� O O O S O O O O O O O O O O o �d s o o v� r $ „ — o 0 o i � n v o ' �� � �il � � ^ � N � N ^ I I N o � I � I u �---I � ; '' w ;` s 8 s s s 8 8 s s 8 8 s 8. s s 8 s � 8 s 8 8 s s s s 8 � � � � a +1 p� p p 0 pP p 0� p o p p �c N p c p o p p pp o �o n v� ' �O 'I P I O O O � O q O `O V �O 8 �O � O = 8 f� Q O PQ O 8 O �D V � NI V O �I��� � N H H H H 9 H N '-e+� N b y �y y N Q y H H H H N H N O 0 Vl N M H � H `^ � e o" ^ ear� e Y� y I M H H M � H N Q� u H H H � F-- i 2 '� e g $ g 8 g g g a g g g 8 g = n g g g g � g g g g g g � j I ' � ��e o � ._ _ �d .- o0 0 �c o 0 o 8 a v a; R .-. oe r; p o p r; c ',,,. \ !g �¢ N N T v�i � Q N N ry� � b 1� O� I N I O E� a � � i �, �, � , � r� 3 , � �—�-� '' v �, � i � ,! i i , ' � �j� g8gggg88�pg888888g888 � �.p � Q}g{ 88 ,.'�0!8�8�8 �. 8 i i 2 I y � H N H H H H N H N H H H � H H H H N H H N H M H H N N N �N �I I O � I �i ' � y V � f � � � I � N � � � � U � � 6 � ZZZ �" z � � � � � � � � � � � � � �C � C � I `� � � � < � � � � � o � 000a� a� b < b � o�� a< � b � < � � c 4 ! .] .d W .d V C .d F E+ F m C7 (n .] .d W .] ..1 vi ..1 u� W .] ..1 .] ul .7 6 m 4 ' C � Y � 4 � Y Q °° � � � t-� O ,� q � � ��a U � y �.� p ' 1 L ` �6 O � U �j p � C��7C7 � � i � �oi y q..7 � < 5ae � � W � � � � U` i c ��'U" °< � X u1 �" � O pZ N � Q � �+ � ... O � C � V c' C d s X w � � � � iy�� C7 � X � � (n [ � � y p �t�i� � � �� � � W � � 6 < � � � � F-� � � O � � 3 �` � , � cy 000 `� � � ��qy � < � � �g �<S � � � e�qc � o o � w � � i y � � W o o �q °w p, o. � � W 3 y G G U � 3 � � � � � .��.t � �I I '� �° °� F� < � � � ww d `� m � � m a � � � � �{y' �{y' g�f�] o � � � a � � cWi � v � o d � O O O O j � � � 5 � W W � Q U U C�+ F� F� _ U h `� � � � U � � � �� t� p � � g p u �, � z `� 5c U � s ,� ,� pq 5 t� �j F � � � oG v�i y o�. C7 v�i y � � � k5 � c � � < U �V a � w w e `v `v R1 vdi F � d � O � y � � Z ` ' � � � h � � < < < < < < < < < < < < < < < < < < < < < < < < < a < < < < < < `1� � o , �^� ` i _' : . _ — °~' Z � �' c �2z e 4 -_ __ t � O 422'�.� � Z ,� � � � � �ro N _ H � �v _ _ _I _ IWI �U� v �, 'Z �`� '$ .� „c,jo $ $IHN � �S�, �.�, r ��., � �S', � $ �.�, � �.`�, � � � $ `^ $ $ $ $ �.�, �.�, h � '�, � a r `u v 2Wr� � Y � w = � S $ 8 � $ o . . p . < �p �p �p y < �} a :Z, 1 1 ��Z U N � � � MO <n O v^i p O O O rl M N `O �D �O �O V `O 1� N 1� n I _� � �` ^ ' �4� q {��, N N N N N N N N N N N N N N N O N N N N N N N N O O O O N N N N F � F � � �. .r W � y F V F � < � �S' � ryt� C1 � 07 � F U� `i '"' N rf < v1 �O 1� a0 T � O .�. .-lV. M ^ � N �O ^ 00 T N N N N N N N N N N N (A .�i (A f��l F t, 3 � 3` �I ' , ' � � � � a. ' ' y � � S S � O O P O T T N � � !� b y � � � ro V O� .-� t� � .iaj �0 (� � N CI 00 Cl V N� � h t� �� �Q� H M y H y H H y Vf yj � [� �+ N , v Z, $p g g gp $ M�gO = gp �� S O P N O � � O � O c a — � a , wa � �� �� ' � o�� � , ya N F� �� � ' 1 � p p p ppp pI � O O O O O � O N O a � b �p V �Cn[ � � g g o 0 0� N � � � � � y��� � y N a0 H � N H H r � ♦p e q ' + � � H H M N N VI „�„� 0 � N o' 88888 °' 8 � 8 o � g a � g � = g � g z �_ - � _ - _ Z �`�. ' y 3 0 h ` w •�u $ g g 8 g 8 8 g N � ' � �� a� N n g n Q $ H U y N H H N N y � � � � � O � z a � zU � � � � � � � � � � o � � � � � � aa a ' � 4 j � C � � O � � y � � ' �„ O � p .s� � N � � 5 � r � � z � M �, � r V � oo � �" o � , o < a� NN � � °� � � U � � f+�t � � � y ��y � y w y Vl V1 Q < .� Q y � �l f 0 V � O d ,y V °' °' ��cilFo' � s �' M ' m v q � � o�. a � � xo `Ci, U � oi ' � U a ao V U `oo co F y„ o h ♦ ': � e � p b �^^ � 2 W OC i0 LO Cl P� C! a0 00 �� � � ' �ry g Z q � p � N O �Op � � O aZ'� Z Z `2F�{,`, F`CgO y N N .-. ... N .. N z � U[.. '� `+U a � i. $ $ v n $ n $ $ O Uk] .� �i" OVi "0�� ZO, �2 r ^ e e � e e e e N < � < e5 �v C �p L ' �� � � � N tV N N N N N � F � F ,Q � L � 4 V y ��a � � ° � � e'�� " a' � � 1� N N n e��f � M N e�n f]/1 � f�/1 MI l" LL � v � , ' , a � o, tl ' 4 ' 8 8 8 8 8 8 8 8 8 8 8 8 8, 8 8 S � � � ; 8 8 8 p�p N 8 8 v�i v�i p�p 8 e� O vi r�l M b t� f V N 1^ �N O H M P �O W O� � � � O `�1 .�i $�� H M M H N H M � H M � � H � � � fi� H N H ' � S S �a � S S S S �p �p � S S S �� � n ^ M O ^ � � V O N N � � d ' � i ��-�o � ���.) ' � � �� � O�� I I I � O O O O O O O O O O w�i w�i ly 2 � g � � � w a � :�b n o�p�r , I�U N I H N ~ Nly Hi{^IN M i I jj�;;j Z, g 8 8 8 8 8 g T f-��-- �y�'a � N � � �O � I �I tl , = � p � � S � � S � � � � � � � olM n o M s p p p p p p ii �p8 p W �i} O� O O � O O v�i H T `O vri P oa{ P ip op O N � i���� M ~ ~ N H N y H y N V I H 00 N N y � ' H f9 I i IH � i� g 8 g 8 g g g g g g g g 8 I __��__ p � `c — ._ � �c v - - � g o r g I � i �e��$ r n = � '��f� a ' I '; ' . Z 3 o � � � � �� g 8g 8 8 8 8 � 8 8 8 g 8 8 8 g ,� � p O O ^ � CI , V � ^ H N � H H H N H N H H H ~ � H H .1� Z � � cxicSiE�iucxic�iu � c�icxi � � � � � � x � < � < < < a � < < � � � � � $ � � m m m w w m w � � � � j j I � ' � 4 4 C � o 1 ! N � 0 � N h y ° z UU �' r o z � � 3 xxozN w � g � c"7 � U z � °' � � °° o � o � � � � z � � � N � xa �i � � �k � � , � �, �, v, w m � Q Q p E� y j {[�� � � � � � j � p � � � � � � `'`��� J > > �O 6� y �( � Py {t7 � d ' E. `� � � � � � � � � � � � 333 � �j � � � e � � > > - e � = o � � o � � � o h � ^ �^� : u � u � � � vuuuuuu � u �°� � o ' ^ � q��g Z _ � �n o e o d �2Z e z v, v7vZZ � �� N N N N N N N N N�N p W � ~ 2�k�j �Z � $ $ $ $ $ $ $ $ $ $ $ $ $ $ � .7 � .7 � .'��' G' C7 �'1 �O� �� �e �o u �o �o �o �o �o �o �o �o �o �o �o �o < � < f�. � tl �p � ' y 4 4 N N N N N N N N N N tV tV N N r F 0 F �� � ,� �. 4 � Z[�y?�w � � ° ° < h � a' 41 3 U� 3 n M n v e v a � e � e e e v�i v� y o � � � O�i 01 ;�� � � V � , , ' o N o, � ' a 8 O O O O O O O O O O O O O O O $ ti � Y1 �O N �� t, $ � 8 g $a 8 $ � m e� g � 8 v�i a 'e � e^n � � 1� � O� 00 M e O 'f O ♦ ��� H H H N M y N y H H H H N H N q H O f�l � N.p H H � N N � O O S � � S � � � N P O Q O O. O ��� � 1� O P lV �G � �O O O T vi O � O � N� v� � � M � .� N � � r�t O ���� I 8 O O O O S 0 O� P O a ....._.�rV I g a � p I � I g V N a ^ V O�,hp ' O b � O r � rf O� H ^ V1 �� N N I H � � y' N 1� 0�0 b VM H � H y � H (y O O .�-. O O O O�� � n �o c� ' i�a ;gsgs j Is�is ; ', sgs � = � � � � y � �I I ry, wL V`"1 N I r P ' I^{�U H H H M H H H H N MO � ra I a' �p O I1 I I I III yl �Nly'y H yyy���,,, 8 g g 8 g g g v g �y•� 00 O P C N v� v1 O < � � q N v� 00 e� � ���`� � � � N OI � 1 F• ^ . i '� �I p � g g g g g g'g g $ $ o � a � o e�0o � y a�p °�° h g $ g ^ � $ � � y � � e � e � ��F�,) N y ~ H H H N I ~ � N N K b � ' o I3 , ��I � H� w "� � o°' o °° '° 8 � 8 II II � 8 8 8 8 � � }I-{f I� N � � � �INI i � �IN I I Z i •C I '�, 'i °z` ,�'� ' ' ' i i ' � 3 0 � � � �° g $ 8 8 8 8 8 8 8QQ 8 8 8 8 8 g $ j o � �� �H N M N H y �,j H H H H H H � � � , � � o � x �'i � � � � x Sx � � � � x � � � 3 .� Z � � < b � b � b � < a � � � � � a r q � ., u� .a .a ..� .� .� m m .� � .� a v v, ' � F � � � � � 3 � � z o 0 0 0 � w �W � Y � Y 4 r ? , � y q f� < � v°'i v � � r � ' G U U Up U � � `n v) v, rn �U � � � � E � a �j v' O G G G q L j e c7z zC7t7ac�i � � � � � � � w�` `o 0 � � O O G A p p � � � � � � � � F � ,L',r� au� o j U o � � � � > >� � � � � � � � � � � � �� g � � j °C � 6dP� " " � a � o o� ,e °lmawm .� .�� Gc�mraaccc� � ' � a a o"e a a F FN �' �`-' � � � � � �''`j `� M � Q M � �� O o� o 0 0 0 �a � °w V — r+ n U U.�.U U V V U C7 0� � y � � � E I i •� n R�1." y� O G O A O G L1 G f] O A 0 G G O f] � �� � 0 ' ory� Z I� � e ry � 22' � W i�� O o�i 7� Z Z '~`�i��Q w � � 5 � � � � � � � � � � � � � � � < � � u o"i a o �0 a �•�Z � o � o 0 0 0 o g � g g o � _ = e � � � F � C p t , k N N N N N N N N N N N N N N N N Fp Q pF ��'y 3� F `r F � < z ;O � � � ��S Li v�i `�' vQi V' v�i vei �' v`�i v�i v00i vPi $ $ �o e "7 0 � o O � y Y ,�..'� '� rn ., n n F C9 fi, � V � ' ' ' ' ' ' ' ' WENSMANN 12TH ADDI'C[ON STREET&UTILITY CONSTRUCTION AND AppUR7'ENANT WORK C[TY PROIECT NO.287 WSB PROJECT NO.1067.50 ' ------ _. --- -----__..-.._---._- - - WATERMAIN TRUNK COST WORKSHEET ON I51 ST STREET ONLY --i- ---�-- ---�--------- -- � COSTS � � ITEM j I UNIT I QUANTITY -�-� DIFFERENCE I MULTIPLIER•" _ TOTAL 12" 6" � ' � I 12"WATERMAIN LF 635 S22 S19 S3 ' 0.5 S952S0 _ .- � ----- ----�-- � I --�- .__.-.._ .._..: _. .. . 2 ! 12"GATE VALVE EA 1 SI,000 5550 5450 I QS �� 5225.00 I � -- --.--�._.__...__ _ ' 3 CONNECT TO EXISTMG WATERMAIN EA 2 5300 5200 5100 0.5 __SI00.00 _ 4 � FITTMGS LG 735" SI 0.5 5367.50 ' SUBTOT , $1,645.00 _ +10°/CONTINGENCIES 5164 50 TOTAL COS'I'TRUNK OVERSIZIN S 1,809 50 ' NO OVERSIZING FOR PROPERTY NORTH OF I51'T STREET OVERSIZiNG FOR TI-IE PROPERTY SOUTH OF 1 S 1"STREET WO.L BE PAID BY Tf�CITY ' WEIGH'f DffFERENCE BETWEEN 12"AND B"FI7"fINGS , " A MULTIPLIER OF 0.5 IS USED BECAUSE THE PROPERTY NORTH OF I51'T STREET IS COMN4ERCIAL AND REQUIRES 12"WATERMAIN,T[-IERgpORE,NO OVERSIZING REQUIItED. T[�PROPERTY SOUTH OF I51'�STREET ONLY REQUIRES AN 8"WATERMAIN. 77�CITY WI1,L PAY FOR OVERSIZING ON Tk�SOUTH HALF OF ISISTREET. 1 ' � , ' ' Feasibility Report for the City of Rosemount Wensmann 12`"`Addition-Street& Utility Construction and Appu�tenant Work City Project No. 287 ' WSB Project No. 1067.SO Page 21