HomeMy WebLinkAbout6.i. Payment #2 and Change Order #1, Conley Avenue Street & Utility Improvements, City Project #303 , CITY OF ROSEMOUNT ' EXECUTIVE SUMMARY FOR ACTION CITY COUNCIL MEETING DATE: November 2, 1999 AGENDA ITEM: Payment #2 and Change Order #1, Conley AGENDA SECTION: Avenue Street & Utility Improvements, City Projec #303 Consent . PREPARED BY: Bud Osmundson AGENDA � � City Engineer/Public Works Director � � ' � ATTACHMENTS: Payment Voucher #2 APPROVED BY• I � This item requests the second payment to Richard Knutson, Inc., in the amount of 5363,190.27 for City Project #303, the Conley Avenue Street & Utility Improvements. Work completed and represented in this payment as of October 15, 1999 is 50% of contracted work. The work has been inspected and is in compliance with the Contract Documents. This payment covers utility work and some street grading work. The payment also includes Change Order #1 . The Change Order is for the construction of cable concrete over a Koch pipeline that the storm sewer outlet swale intersects with at Highway 52. The Contractor expects to start curb & gutter construction this week. Attached is a copy of the Construction Pay Voucher #2 and Change Order #1 for your information. Staff and WSB & Associates recommend approval of this second payment and Change Order #1 . RECOMMENDED ACTION: MOTION TO APPROVE PAYMENT #2 AND CHANGE ORDER #1 TO RICHARD KNUTSON, INC., IN THE AMOUNT OF 5363,190.27 FOR THE CONLEY AVENUE STREET & UTILITY IMPROVEMENTS, CITY PROJECT #303. COUNCIL ACTION: 5 , r ' BA hlittelsteadt,P.E. - 350 Westwood Lake Office Bret A.Weiss,PE. II���� 8441 Wayzata Boulevard Pecer R\Y/'illenbring,P.E. Minneapolis, MN 55426 Donald W.Sterna,P.E. Ronald B.Bray,P.E. _ 612-541-4800 &Associates, Inc. FAX 541-1700 October 22, 1999 Honorable Mayor and City Council City of Rosemount 2875 145`h Street West Rosemount, MN 55068 Re: Construction Pay Voucher No. 2 / Change Order No. 1 Conley Avenue Street & Utility Construction and Appurtenant Work City Project No. 303 WSB Project No. 1148.21 Dear Mayor and Council Members: Please find enclosed Construction Pay Voucher No. 2, together with Change Order No. 1, for the referenced project. Change Order No. 1 reflects an increase to the contract amount of$11,520.00,resulting in a new contract total of$1,341,127.35. The amount of the change order is included for payment with this voucher. Would you please approve the enclosed documents and process payment for the voucher and change order in the amount of$363,190.27. Please forward to Richard Knutson,Inc.at your earliest convenience. Thank you. Sincerely, WSB &Associates, Inc. < 6���� Bret A. Weiss, P.E. Vice President Enclosures c: Bud Osmundson/Doug Litterer, City of Rosemount Richard Knutson, Inc. nrri F:IWPWIMll fd.?llw-?-co-1 dtr.wpd M i n n e a p o l i s • S t . C l o u d Infrastructure Engineers Planners EQUAL OPPORTUNITY EMPLOYER � Construction Pay Voucher Voucher No: 2 Date: 22-Oct-99 ' Project: Conley Avenue Street&Utility Constrution and Appurtenant Work Project No: CP 303 Period Ending: 15-Oct-99 S.P. 1906-44 WSB Project No. 1148.21 Contractor: ic ar nutson, nc. 12585 Rhode Island Avenue South Savage, MN 55378 Contract Date: 4-Aug-99 Work Started: Completion Date: Work Completed: Original Contract Amount $1,329,607.35 Total Additions $11,520.00 Total Deductions Total Funds Encumbered $1,341,127.35 Total Work Certified to Date $675,635.37 Less Retained Percentage 5.00% $33,781.77 Less Previous Payments $278,663.33 Total Payments Incl.This Voucher $641,853.60 Balance Carried Forward $665,491.98 Approved for Payment This Voucher $363,190.27 Approvals WSB 8 Associates, Inc. In accordance with field observation, as performed in accordance with industry standards, and based on our professional opinion, the materials installed are satisfactory and the work properly performed in accordance with the plans and specifications. The total work estimated to be completed as of October 15, 1999 is as indicated herein and we hereby 50% recommend payment of this voucher. � Signed: Signed: Construction Observer Project Manager/Engineer Richard Knutson, Inc. , This is to certify that to the best of my knowledge, information, and belief, the quantities and values of work certified herein is a fair approximate estimate for the period covered by this voucher. Contractor: Signed: Date: Title: City of Rosemount Approved for Checked by: Payment: Authorized Representative Date: Date: �� '����1 M:\1148.20\Exce�vo-2xls , , - CHANGE ORDER NO. 1 CONLEY AVENUE STREET 8 UTILITY CONSTRUCTION&APPURTENANT WORK CITY OF ROSEMOUNT PROJECT NO.303 S.P.'1906-44 WSB PROJECT NO.1148.21 Owner: Ciry of Rosemount Date of Issuance: October 22, 1999 Contractor: Richard Knutson, Inc. Engineer: WSB&Associates, Inc. You are directed to make the following changes in the Contract Document description: Add cable concrete in the Trunk Highway 52 ditch to protect the Koch pipeline,as indicated in attached schedule. CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME Original Contract Price: $1,329,607.35 Original Contract Time: August 4, 1999 Previous Change Orders: No.— to— $0.00 Net Change from Previous Change Orders: None Contract Price Prior to This Change Order: $1,329,607.35 Contract Time Prior to This Change Order: August 4, 1999 Net Increase of This Change Order: $11,520.00 Net Increase of Change Order: None Contract Price With All Approved Change $1,341,127.35 Contract Time With Approved Change August 4, 1999 Orders: Orders: Recommended By: Approved By: JL�� � Bret A.Weiss,P.E. WSB&Associates Inc. Richard Knutson Inc. Engineer Contractor Approved By: Approved By: Date of Council Action: . " City Engineer City Administrator