HomeMy WebLinkAbout6.g. Receive Feasibility Report/Set Public Hearing for Hawkings Pond Addition Street & Utilitity Improvements, City Project #275 l
f ` CITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: February 18, 1997
AGENDA ITEM: Receive Feasibility ReportlSet Public AGENDA SECTION:
Hearing-Hawkins Pond Addition Street & Utilities CONSENT '
Improvements, City Project #275 '�,
PREPARED BY: Bud Osmundson AGENDA���. J� (� �
City Engineer/Public Works Director -"�►' �� �1
ATTACHMENTS: Executive Summary-Feasibility Report APPROVED BY:
Resolution
The City received a petition for public improvements from the owners of the Hawkins
Pond area on May 7, 1996. The City received a petition for improvements for the
easterly portion of the Baptist Church property on September 3, 1996, and Feasibility
Reports for both projects were ordered. Since that time one developer has acquired
control over the entire property and the two feasibility reports were melded into one
covering the entire property. The resulting Feasibility Report addresses the public
improvements necessary for the entire 29 acres which will result in approximately 69
single family homes.
The total estimated project cost is approximately 1.28 million dollars. The developer has
requested that the City complete the grading for the project which is also included in the
project cost. There are three existing single famify homes in the southwest corner of the
site which will be provided sanitary sewer service with this project. There will be
proposed assessments against these three parcels and a minor amount of funding from
the Sanitary Sewer, Watermain and Storm Sewer Core Funds for pipe oversizing, but the
majority of the cost will be assessed against the developing property. The funding
details are shown on the attached summary as is the proposed project schedule.
We have been in contact with the three property owners that will be affected by the
property and have provided them copies of the Feasibility Report. Staff recommends
that the Gouncil receive the Feasibility Report and set a public hearing for March 4, 1996
to consider the proposed improvements.
RECOMMENDED ACTION: MOTION TO ADOPT A RESOLUTION RECEIVING THE
FEASIBILITY REPORT AND SETTING A PUBLIC HEARING FOR HAWKINS POND ADDITION
STREET & UTILITIES IMPROVEMENT, CITY PROJECT #275.
COUNCIL ACTION:
3
�
CITY OF ROSEMOUNT
DAKOTA COUNTY, MINNESOTA
RESOIUTION 1997 -
A RESOLUTION RECEIVING THE FEASIBILITY REPORT/SET PUBLIC HEARING
HAWKINS POND ADDITION STREET & UTILITY IMPROVEMENTS
CITY PROJECT #275
WHEREAS, pursuant to the resolutions of the Councii adopted on May 7, 1996 and
September 3, 1996, a report has been prepared by the City Engineer with reference to the
improvement of Hawkins Pond Addition Street & Utility Improvements, City Project #275,
and this report was received by the Council on February 18, 1997, and
WHEREAS, the report provides information regarding whether the proposed project is
necessary, cost-effective, and feasible.
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF ROSEMOUNT, MINNESOTA:
1. The Council will consider the improvements in accordance with the repart and the
assessment of abutting property for all or a portion of the cost of the improvements
pursuant to Minnesota Statutes, Chapter 429 at an estimated total cost of the
improvements of 51,278,000.
2. A public hearing shall be held on such proposed improvements on the 4th day of
March, 1997, in the Council Chambers of the City Hall at 8:00 p.m. and the clerk
shall give mailed and published notice of such hearing and improvements as required
by law.
ADOPTED this 18th day of February, 1997.
Cathy Busho, Mayor
ATTEST:
Susan M. Walsh, City Clerk ',
Motion by: Seconded by:
Voted in favor:
Voted against:
4
3
i
� February 18, 1997
Preliminary Report
. Hawkins Pond
Street and Utility improvements
Rosemou�t, Minnesota
Executive Summary
City Project No. 275 provides for the construction of sanitary sewer.
water main, storm drain, street and site grading improvements in the
proposed Hawkins Pond development. This development consists of 69
single-family residential lots,68 of which are assessable in terms of street
and utility improvements. The project has been split into two phases.
Phase A contains 441ots, and Phase B contains 251ots.
Tlus improve�ment is necessary to provide the subject property with
municipal utilities and street access. In addition, the improvement is
cost-effective and feasible from an engineering standpoint. The
improvement would best be constructed as an individual project rather
than as a part of another project.
This improvement is located in the north half of Section 30,
Township 115N, Range 19W. The proposed lots are located in the '��
viciniry of Hawkins Pond which is north of 145th Street West and west
of Shannon Parkway. The project includes approximately 3300 lineaz
feet of sanitary sewer,44001inear feet of water main, 30001ineaz feet of
storm drain, and 38001inear feet of street construction.
The total estimated project cost is $1,278,000. Of this total,
approximately $1,229,150 is assessable to the Hawkins Pond
development, approximately $10,850 is assessable to the three (3)
properties along 145th Street West for sanitary sewer construction, and
approximately$38,000 will be recovered through City core funds.
A-ROSEM9604.02
Page 1
i
4
Spreading the $1,229,I50 over the 68 assessable lots in Hawkins Pond ',
yields an aQproximaie assessment rate of$18.076 per lot. Due to the '
different sewer configurations necessary to serve the three (3) lots along '
145th Street West, the estimated assessments for these lots are not all
equal. The assessments for lots 010-36 and 010-45 are approximately '�,
$3,�0 each. The assessment for lot 010-43 is approximately �4,350. !
Project construction is scheduled to begin in May of 1997. Substantial I
completion is scheduled for the fall of 1997. Final completion(including �,
the bituminous weaz course) is scheduled for the spring of 1998.
i
1
_4
k
�
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604A2
Rosemount,Minnesota Page 2 �
J
Table 3
Assessment Area
Hawkins Pond Preliminary Piat No.of
Block Lots Assessable �ots
� 1 1
2 1 - 10 10
3 1 -23 23
4 1 - 15 15
5 1 - 19 19
Subtotal 68
Parcels Along 145th Street West
No.of
Owner(s) Street P�.N Assessable Lots
Address
Fioyd Berg� 4335 34-03010- 1
010-43
David&Judith 42�5 34-03010- �
Bezenek a10-45
Greg&Teresa 4255 34-43010- 1
Goettsch 010-36
Subtotal 3
TOTAL NO. OF ASSESSABLE LOTS 71
Table 4
C�ty Core Costs and Assessabie Costs
City Water City Storm Totai City Remai�ing
Phase Total Cost Main Core Drain Core Assessable
Costs Costs Core Costs �as�
A $944,000 $7,000 $19,000 $26,000 $918,000
B $334,000 $12,000 $0 $12,000 $322.000
A+B $1,278,000 $19,000 $19,000 $38.000 $1.240,000
Table 5
Breakdown of Assessable Costs '
Hawkins No.of ,
Sanitary Sanitary Sanitary Assessable Assessment
Assessable Pond
Phase Costs Sewer to Sewer to Sewer to p���minary Lots in per Lot in
Lot 010-36 Lot 010-45 Lot 010-43 P�at Hawkins Hawkins Pond
Pond ,
A $918,000 $3,250 $3,250 $0 $911,500 43 $21,198
B $322,000 $0 $0 $4,350 $317,650 25 $12,706 ,
A+B $1,240,000 $3,250 $3,250 $4,350 $1.229.150 68 $18,076
�
�
5.0 Project Schedule
The proposed schedule for this improvement is listed below. This
schedule is based on the provisions of Chapter 429 of the Minnesota State
Statues. The schedule assumes that all elements of the improvement,
including developer obligations and easement acquisitions, are completed
in a timely manner.
• Receive Feasibility Report,
Set Public Hearin Februa 18 1997
9 rY �
• Conduct Public Hearing, Order Pians and
Specifications March 4, 1997
• Receive Plans and Specifications,
Order Add for Bid March 18, 1997
• Open Bids April 11, 1997
• Receive Bids/Award Contract April 15, 1997 II,
• Begin Construciion May, 1997 '
• Substantial Completion Fall, 1997 ',
• Bituminous Wear Course and Final Completion Spring, 1998 '
• Hold Assessment Hearing Fall, 1998
• First Payment Due w/Taxes Spring, 1999
�
� . �
Hawkins Pond ����� -�
� Street and Utility Improvements (�- �
1" � �,'
�
��� � � �
��+� �O ' �
� �
� Preliminary Report
�
�
� Ci of-Rosemount
tY
Minnesota
� '
� Ci Pro'ect No. 275
tY 1
SEH No. A-ROSEM9604.02
'
February 18, 1997
�
�
�
�
SHORT ELLIOT'T HENDRICKSON INC .
� �
=SEN
� MULTIDISCIPLINED.
SINGLE SOURCE.
�
i
�
��
Hawkins Pond
� Street and Utility Improvements
Preliminary Report
�
City of Rosemount
Minnesota
�
, City Project No. 275
� SEH No. A-ROSEM9604.02
February 18, 1997
� -
�`
�
� •
I hereby certify that this preliminary report was prepared by me or
�1 under my direct upervision, and that I am a duly Registered
Professional E i r under the 1 ws of State of Minnesota.
. ,
� �
Date: February 18, 1997 Reg.No.: 19699
�
Reviewed By: 02/18/97
�
Date
i�
�
Short Elliott Hendrickson Inc.
�� 3535 Vadnais Center Drive II
200 SEH Center ',
St. Paul, Minnesota 55110
�; (612) 490-2000
�r
�
�
-
� 3535 VADNAIS CENTER DRIVE,200 SEH CENTER,ST.PAUL,MN 55110 612 490-2000 800 325-2055
- ARCHITECTURE • ENGINEERING • ENVIRONMENTAL • TRANSPORTATION
�
�
� February 18, 1997 RE: Rosemount, Minnesota
Hawkins Pond
Street and Utility Improvements
,� City Project No. 275
SEH No. A-ROSEM9604.02
� City of Rosemount
2875 145th Street West
�; Rosemount, MN 55068
ATTN: Mr. Bud Osmundson, City Engineer/Public Works Director
:� Gentlemen:
In accordance with your authorization, we have prepared the attached preliminary report for street
� and utility improvements in the Hawkins Pond development: This report discusses sanitary sewer,
water main, storm drainage, street improvements and site grading, and provides cost estimates far
� each.
We find this improvement to be feasible and recommend that it be constructed in general compliance
� with the provisions of this report.
We would be pleased to review this report with you in detaiL
# Sinc rel ,
Y
• .
�
.
David F. Simons, .E.
�
nn
F:�DOC�PROJECTSUtOSEM\9604.02�REPORTS�HAW KIlVS.218
�
�
��
SHORT ELLIOTT
HENDRICKSON INC. MINNEAPOLIS,MN ST.CLOUq MN CHIPPEWA FALLS,WI MADISON,WI LAKE COUNTY,IN
EQUAL OPPORTUNITY EMPLOYER
�
1
� i
� Table of Contents
� Certification Page
Letter of Transmittal
�, Table of Contents
' Page
� Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.0 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.1 Authorization 3
,�� 1.2 Sco e 3
P
1,3 Data Available 3
� 2.0 General Back round . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
. 9
2.1 Loca#ion 3
�� 2.2 Adjacent Property 3
2.3 Site Conditions 4
� 3.0 Proposed Improvements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
_ 3.1 Sanitary Sewer 4
3.2 Water Main 5
� 3.3 Storm Drainage . 5
3.4 Street Construction 6
,, 3.5 Site Grading 7
�; 3.6 Easements 8
3.7 Permits g
� 4A Financing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
4.1 Cost Estimates 9
4.2 Assessment Area 9
� 4.3 Cost Recovery 10
5.0 Project Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
,�
�
�
�
f
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
r
Rosemount, Minnesota Page i
^
�
� S readin the $1 229 150 over the 68 assessable lots in Hawkins Pond
� P g , ,
yields an approximate assessment rate of$18,076 per lot. Due to the
� different sewer configurations necessary to serve the three (3) lots along
145th Street West, the estimated assessments for these lots are not all
� equal. The assessments for lots 010-36 and 010-45 are approximately
� $3,250 each. The assessment for lot 010-43 is approximately $4,350.
Project construction is scheduled to begin in May of 1997. Substantial
,� completion is scheduled for the fall of 1997. Final completion(including
the bituminous wear course) is scheduled for the spring of 1998.
.-.
,� ,
�'
� ',
�
�4
.,
��
�
�,
�
�
�
�'
�
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota Page 2
�
�`
� 1
Hawkms Pond
CG��� �
� Street and Utility Improvements -��
� �
q� 7 - �
��� � � �
t .1-^-
� Preliminary Report
�
�
� Ci of Rosemount
tY
Minnesota
� •
� Ci Pro'ect No. 275
tY 1
SEH No. A-ROSEM9604.02
�
February 18, 1997
�
�
�
�
SHORT ELLIOT'T HENDRICKSON INC .
� �
=5E�1
� M ULTIDfSCIPiINED.
SINGLE SOURCE.
� ,
�
�
Hawkins Pond
� Street and Utility Improvements
Preliminary Report
;��
City of Rosemount
� Minnesota
, City Project No. 275
,� SEH No. A-ROSEM9604.02 -
February 18, 1997
�5 - .
.k�� � - . . � � � . � . �
� . - . �. � . � . � � . ,
,� . . . ' . � . . � ... .
I hereby certify that this preliminary report was prepared by me or
�i under my direct upervision, and that I am a duly Registered
Professional E i r under the I ws of �tate of Minnesota.
�
. ,
.
�
Date: February 18, 1997 Reg. No.: 19699
�
Reviewed By: 02/18/97
�
Date
`� i
�''
Short Elliott Hendrickson Inc.
�� 3535 Vadnais Center Drive
200 SEH Center
St. Paul, Minnesota 55110
� (612) 490-2000
�
�
-
� - 3535 VADNAIS CENTER DRIVE,200 SEH CENTER,ST.PAUL,MN 55170 612 490-2000 800 325-2055
- ARCHITECTURE • ENGINEERING • ENVIRONMENTAL • TRANSPORTATION
�f
�
� February 18, 1997 RE: Rosemount, Minnesota
�. Hawkins Pond
Street and Utility Improvements
� City Project No. 275
SEH No. A-ROSEM9604.02
� City of Rosemount
2875 145th Street West
�. Rosemount, MN 55068
ATTN: Mr. Bud Osmundson, City Engineer/Public Works Directar
� Gentlemen:
In accordance with your authorization, we have prepared the attached preliminary report for street
�
and utility improvements in the Hawkins Pond developrnent. This report discusses sanitary sewer,
water main, storm drainage, street improvements and site grading, and provides cost estimates for
� each.
We find this improvement to be feasible and recommend that it be constructed in general compliance
� with the provisions of this report.
We would be pleased to review this report with you in detaiL
� Sinc rely,
. �
�
.
David F. Simons, .E.
�
nn
F:�DOC\PROJECTSV20SEWn9604.02�REPORTS�HA W KINS.218
�
�
� SHORT ELLIOTT
HENDRICKSON INC. MINNEAPOUS,MN ST.CLOUD,MN CHIPPEW,4 FALLS, WI MADISON, WI LAKE COUNTY,IN
:� EQUAL OPPORTUNITYEMPLOYER
�
� Table of Contents
,� Certification Page .
�' Letter of Transmittal
Table of Contents
� Page
� Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.0 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.1 Authorization 3
`� 1.2 Sco e 3
_, P
1.3 Data Available 3
� 2.0 General Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.1 Loca#ion 3
� 2.2 Adjacent Property 3
2.3 Site Conditions 4
� 3A Proposed Improvements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.1 Sanitary Sewer 4
3.2 Water Main 5
�' 3.3 Storm Drainage 5
3.4 Street Construction 6
3.5 Site Grading 7
3.6 Easements 8
3.7 Permits 8
� 4A Financing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 �
4.1 Cost Estimates 9 II�
4.2 Assessment Area 9 'i
� 4.3 Cost Recovery 10 �,
5.0 Project Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 '
� ,
,�
�
f
�
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota Page i
�'
� List of Tabies
Page
�
Table 1
� Permitting Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Table 2
,� Summary of Cost Estimates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Table 3
�; AssessmentArea . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Table 4
� City Core Costs and Assessable Costs . . . . . . . . . . . . . . . . . . . . . . . 11
Table 5
� Breakdown of Assessable Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
:�
. ,
� List of Appendices
�
Appendix A
Detailed Cost Estimates
:�
Appendix B
Drawings
�
�
�
� I
�
y..,
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota Page ii
�
� Februar 18 1 7
.. Y � 99
�
� Preliminary Report
Hawkins Pond
� Stree� and Utilit Im rovements
Y P
� !,
�
Rosemount, Minnesota I
� Executive mm '
Su ary
City Project No. 275 provides for the construction of sanitary sewer,
�, water main, storm drain, street and site grading improvements in the
proposed Hawkins Pond development. This development consists of 69 ',
single-family residential lots,68 of which are assessable in terms of street
� and utility improvements. The project has been split into two phases.
Phase A contains 44 lots, and Phase B contains 25 lots.
� This improvement is necessary to provide the subject property with
� municipal utilities and street access. In addition, the improvement is
cost-effective and feasible from an engineering standpoint. The
� improvement would best be constructed as an individual project rather
than as a part of another project.
This improvement is located in the narth half of Section 30,
� Townshi 115N, Ran e 19W. The ro osed lots are located in the
P g P P
vicinity of Hawkins Pond which is north of 145th Street West and west
of Shannon Parkway. The project includes approximately 33001inear
feet of sanitary sewer,4400 linear feet of water main, 30001inear feet of
storm drain, and 3800 linear feet of street construction.
'� The total estimated project cost is $1,278,000. Of this total,
approximately $1,229,150 is assessable to the Hawkins Pond
� development, approximately $10,850 is assessable to the three (3)
properties along 145th Street West for sanitary sewer construction, and
approximately$38,000 will be recovered through Ciry core funds.
�
�
�y
A-ROSEM9604.02
� Page 1
�
� Spreading the $1,229,150 over the 68 assessable lots in Hawkins Pond
yields an approximate assessment rate of$18,076 per lot. Due to the
� different sewer configurations necessary to serve the three (3) lots along
145th Street West, the estimated assessments for these lots are not all
s equal. The assessments for lots 010-36 and 010-45 are approximately
� $3,250 each. The assessment for lot 010-43 is approximately$4,350.
Project construction is scheduled to begin in May of 1997. Substantial
;�' completion is scheduled for the fall of 1997. Final completion (including
the bituminous wear course) is scheduled for the spring of 1998.
�
�'
�
�
�',
i
�� � � � �
�
�
�
�
�
�
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02 il
� Rosemount, Minnesota Page 2
�J . � . . � . . � � . � . �
�� .. � . . ... � .. � .
1.0 Introduction
�, �' 1.1 Authorization
On May 7, 1996, the City Council of the City of Rosemount, upon
petition by the developer, authorized the preparation of a preliminary
report for site grading and construction of streets and utilities in the
�$ Hawkins Pond develo ment. This im rovement has been desi nated as
P P g
City Project No. 275.
�� 1.2 Scope
The purpose of this report is to determine the engineering feasibility of
the project based on a review of the data available, and to make
�" recommendations and provide cost estimates for the construction of
sanitary sewer,water main, storm drain, street facilities, and site grading
improvements.
1.3 Data Available
Information and materials used in the preparation of xhis report include:
�` �
• Preliminary Plat for Hawkins Pond(January, 1997)
• Preliminary Grading and Development Plan for Hawkins Pond
�� (East Side - October, 1996; West Side - December, 1996)
• City of Rosemount Construction Record Drawings
� • Comprehensive Sewer Plan Update (June, 1991)
v • City of Rosemount Drainage Plan for the West Drainage Area
� (May, 1989)
• City of Rosemount Comprehensive Water System Plan (October,
1988) �
'� • City of Rosemount Assessment/Improvement Policy (March, 1992)
• Improvement Policy for Public Infrastructure (July, 1996)
�
- 2.0 Generai Background
� 2.1 Location
The project location is shown in Drawing No. 1. The project area is
located in the north half of Section 30, Township 115N, Range 19W.
�, The project is in the vicinity of Hawkins Pond which is located north of
145th Street West and west of Shannon Parkway.
2.2 Adjacent Property �
�
Ad�acent land uses are mostly residential. The John Hawkms residence
is located in the northeast corner of the development and will become part
� of the Plat (Lot 11, Block 2). The Country Hills First Addition
development is located to the north of the project area. The Shannon
Meadows development is located immediately to the east. Several
� existing homes and 145th Street West lie to the south of the project area.
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
'� Rosemount, Minnesota Page 3
�` .
� The First Ba tist Church of Rosemount owns the property to the west of
P
the project area. Currently, some of the Church property is undeveloped.
� The Church facility itself is located in the northeast corner of Diamond
_ Path and 145th Street West. This report was prepared in close contact
- with a representative of the Church, and it utilized a Concept Plan drawn
��; under the Church's direction.
�.3 Site Conditions
;� The project area formally consisted of three larger lots owned by Mr.
John Hawkins,together with a portion of the Church's property. In the
- 1980's the City of Rosemount acquired easements across a portion of
�, � these properties for the purpose of creating a storm water storage pond
(Hawkins Fond), and for the purpose of constructing trunk sanitary ,
sewers and sanitary Lift Station No. 4.
�' Hawkins Pond drains approximately 271 acres and has an existing
normal water level(NWL)of 912 with a high water level (HWL)of 929.
� Using a 2-foot freeboard, the City has established a low floor building
elevation of 931 in the vicinity of Hawkins Pond.
Originally, the pond was designed as an infiltration pond. Therefore,it
�` holds very litde water except for periods immediately following a rainfall
or snowmelt event. In the past,some of the project area has been used for
agricultural purposes. There are several mature oak and pine trees on the
�l site. �
�, 3.0 Proposed Improvements
3.1 Sanitary Sewer
Proposed sanitary sewer facilities are shown on Drawing No. 2. These
facilities include the installation of 8-inch sanitary sewers on all streets
within the development except for a portion of Dekalb Avenue. This
� section of Dekalb Avenue already has a 10-inch trunk sanitary sewer
inplace. In fihis area, sanitary sewer services will be cut into the existing
trunk sewer as needed.
� Currently, the three (3) existing lots located between the proposed
development and 145th Street West do not have sanitary sewer service.
The street addresses of these lots are 4255 - 145th Street West, 42'75 - �
�. 14
Sth Street West and 4355 - 145th Street West. As a art of this
, p
project, 8-inch sewer mains will be extended south on Davenport Avenue
�, and southwest from 144th Street West to serve these lots. '
The sewer main running sauthwest from the west end of 144th Street will
be continued westerly to the Church property. This could be used to
�' serve future development in the southeast corner of the Church property.
1n addition,the existing sanitary sewer service to the Church building off
�
Hawkins Pond Street and Utility improvements A-ROSEM9604.02
�' Rosemount, Minnesota Page 4
�
�� �,�,'
of Dekalb Avenue will need to be relocated to comcide ith the proposed
lot con�guration. ;
��� Lots 12 through 15 of Block 3 will be served by the existing 8-inch
sanitary sewer which runs through the center of these lots to Lift Station ,
�� No.4. Three (3)existing sanitaty sewer wyes will be utilized for Lots 12
though 14. An additional sanitary sewer wye will be cut into this main
for Lot 15. '
'� The proposed facilities also include the extension of 4-inch sanitary sewer ,
services 15 feet into each lot from the xight-of-way line. Due to the large
size of Lot 5,Block 1,there is potential for a future lot division into four ,
�; lots. Accordingly, four sewer services will be stubbed into this lat.
. 3.2 Water Main
I �`' Proposed water main facilities are shown on Drawing Na 3. A 12-inch
hunk main will be mstalled along Dekalb Avenue, 144th Street West and j
Davenport Avenue south of 144th Street West. This will provide a '
�, 12-inch connection between 145th Street West and Country Hills First
Addition. A portion of the cost for the 12-inch trunk main will be
recovered from City core funds. An 8-inch main will be installed on
�\ 143rd Street West and on Davenport Avenue.
Lots 12 through 15 of Block 3 will be served from an extension of the ,
� existing 6-inc�i stub off of 145th Street West. A 6-inch water main will
- be connected to the stub and extended easterly and westerly to serve these
four lots. '
� The three(3)existing lots located between the proposed development and
145th Street West are currently served with water from 145th Street
� West. Accordingly, it is not necessary to provide additional water
services to these lots.
� The proposed facilities also include hydrants for�re protection and the
extension of one-inch services 15 feet into each lot from the right-of-way
line. Due to the large size of Lot 5,Block 1,there is potential for a future I,
� lot division into four lots. Accordingly, four water services will be �,
stubbed into this lot. �,
3.3 Storm Drainage ,
�` Proposed drainage facilities are shown on Drawing No: 4. The facilities ''
include storm drain connections from the proposed streets to Hawkins
:� Pond. The storm drain piping varies in size from 12-inch to 42-inch '
� diameter pipe.
Catch basins will be installed to collect storm runoff from the street. The
�' catch basins will be installed with sumps to collect sediment from the
street prior to discharging the storm water into Hawkins Pond.
{�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
Rosemount, Minnesota Page 5 '�
�
�
� Storm drain facilities will be extended to the westerl bound of the
Y �'Y
development to pick up runoff from the west. Most of the drainage from
� the Church property flows east, through the proposed development, to
_ Hawkins Pond.
� Lots 12 through 15 of Block 3 will not require the installation of storm
, drain facilities. These lots will be graded such that storm water runoff
will flow north over the ground surface to the pond. The front yard area
may drain south to 145th Street West.
��
A 12-inch diameter storm drain forcemain will also be installed along the
• east side of Davenport Avenue between the southwest corner of Hawkins
� Pond and 145th Street West. This will be used in the future when the
storm water pumping station is installed near the existing sanitary Lift
Station No.4. The storm water pumping station will be used in the future
� to limit the high water level (HWL) of the pond during large runoff
events.
� 3.4 Street Construction
The pro�ect mcludes the construction of standard city streets as shown on
�� Drawing Nos. S and 6. As shown on the drawings, the streets xo be
constructed include 143rd Street West, Dekalb Avenue, 144th Street
West,and Davenport Avenue. A 5-foot wide concrete sidewalk will be
installed on the south side of 143rd Street West and on the west side of
� Davenport Avenue. A concrete valley gutter will be constructed at the
� intersection of 145th Street West and Davenport Avenue to facilitate
� street drainage. Barrieades will need to be installed at the west end of
143rd Street West. In addition,traffic signs and/or street name signs will
be installed as required.
�' The proposed street section consists of a 2-inch bituminous wearing
course, a 2-inch bituminous base course,a 6-inch aggregate base course,
�' and a modified"S"design(surmountable)concrete curb and gutter. This
pavement section utilizes a granular subgrade which will be constructed
in conjunction with the site grading. The required street grading includes
� core excavation of a11 plastic or nonsuitable rnaterials within the roadway
area and replacement with granular ar suitable materials. Fine grading,
topsoiling,and sodding of the boulevard areas will also be included in the
�; City's contract.
Street improvements for Lots 12 through 15 of Block 3 will be minimal
due to the fact that street access is already provided by 145th Street West.
�` As a part of this project,the long driveway connecting the John Hawkins
residence with 145th Street West will be eliminated and a new driveway
aecess off of 143rd Street West wili be provided to the residence. The
i� existing curb drop and pavement on 145th Street West at the Hawkins
driveway will be removed and replaced with concrete curb and gutter I
� II
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02 '
� Rosemount,Minnesota Page 6
�
� (design B618). This will be done when the removal of the existing
driveway is accomplished.
� All street lighting facilities will be constructed, owned, and maintained
- by Dakota Electric Association(DEA). The street lights will be provided
� as part of the extension of electrical service to the project area.
Therefore,construction of street lighting facilities will not be included in
the City's construction contract. Provisions for electrical service and
� associated restoration will be paid for and coordinated by the developer.
Installation of the lighting system will not occur until the City's street
construction project is completed.
� In accordance with City requirements,a shoebox type lighting fixture will
be needed at the intersection of 145th Street West and Davenport Avenue.
Lantern type lighting units will be installed in other areas.
� The develo er will also coordinate and a for the installation and
P PY
restaration associated with natural gas,telephone, and cable TV service.
� 3.5 Site Grading
_ Preliminary or"rough"site grading will be included in the City's contract
'� for this project. The site will be graded in general conformance with the
Grading Plan. This grading will include topsoil stripping/stockpiling,and
excavation and removal of all unsuitable soils from building pad and
� street right-of-way areas. Where possible, mature existing trees will be
preserved during the site grading. After the excavations are complete,
embankments ar"fills"will be constructed with suitable material so that
� structure footings and roadway imnrovements can be constructed on a
stable subgrade. Salvaged topsoil from the initial stripping operation will
then be respread into back yard and boulevard areas.
� This project also inciudes the installation of a clay liner in the bottom of
the Hawkins Pond basin. The clay material used to line the pond will be
� obtained from onsite, provided that suitable clay material can be found
during the grading operation. The clay liner will be 18 inches in depth
and will be installed to pravide approximately 3 feet of standing water.
� This will be done for aesthetic purposes.
The addition of 18 inches of liner material to the pond and the creation
� of 3 feet of standing water will raise the narmal water level (NWL) of the
pond by 4.5 feet to elevation 916.5. This will reduce the effective storage I
volume of the pond. Narmally,this would also raise the high water level
�. (HWL). Hawev�r,the HWL will remain at elevation 929 due to a future
storm water pump which will be constructed at the pand to control the
HWL.
,�' If additional excavation material is needed to complete embankment
areas and balance the earthwork, 18 inches of material could be removed
from the pond bottom prior to placing the clay liner in the pond.
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota Page 7
�
� 3.6 E
asements
Thirty-foot wide easements for sanitary sewer construction wili be needed
� around the perimeter of Lot 11,Block 4. These easements are shown on
Drawing No. 2. This will facilitate the construction of a sewer extension
and the relocation of the existing forcemain in this area. In addition,
� � easements 10 to 20 feet in width will be needed along both sides of the
common lot lme between I,ots 6 and 7,Block 4. These will be needed to
�'' relocate the Church's sewer ser�ice.
Easemerrts, 10 to 20 feet in width, will be needed along both sides of
common lot lines where storm drain piping is proposed. These easements
�; are shown on Drawing No.4.
There may be a need to obtain temporary construction easements for
� grading,roadway, and utility construction along the edges of the existing
lots located along 145th Street West. The need for these easements will
be determined during final design.
�, Most of the remaining improvements will be installed in existing
p easements or in future street rights-of-way whieh will be dedicated to the
City as stipulated in the Developer's Agreement with the City.
/� . 3.7 Permits
Construction permits will be required from several agencies for this
�; project. The'following table summarizes the pernuts which may be
required:
� Table 1 �
Permitting Requirements ,
� Permitting Permit Responsibility Permit I'
Agency Nam� Fee '
City Developer
� Minnesota Sanitary Sewer ✓ $240.00
Pollution Control Extension Permit
Agency(MPCA)
�'' Minnesota Water Main ✓ $�50.00
Department of Extension Permit
�� Health (MDH)
Minnesota General National ✓ $240.00
� Pollution Control Pollutant
� Agency(MPCA) Discharge
Elimination
System (NPDES)
Construction
� Storm Water
Permit
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota Page 8
�
,� 4.0 Financing
4.y Cost Estimates
� Detailed cost estimates for all proposed improvements are included in
Appendix A of this report, The estimates are broken down by phase, as
� shown on Drawing No. 7. The estimates do not include any costs for
., easements which may be required. In addition, street lighting,electrical,
gas, telephone, and cable TV costs are not included in the estimates.
� The cost estimates are based on bid prices obtained from similar type
projects during 1996. The estimates include allowances for contingencies
' (10 percent) and anticipated legal, administrative,engineering, and fiscal
� costs (30 percent).
A summary of these costs is presented inTable 2. All of the site grading
� costs were included inPhase A because the site grading far the entire site
should be done as a part of Phase A. It would be difficult to obtain an
earthwork balance and accomplish the pond lining if the site grading were
�, done separately for each phase.
f� Table 2
Summary of Cost Estimates
�, Phase Sanit�ry Water Storm Streets Site Total
Sewer Main Drain Grading
A $143,000 $157,000 $176,000 $260,000 $208,000 $944,000
� � B $110,000 $76,000 $50,000 $98,000 $0 $334,000
A+B $253,000 $233,000 $226,000 $358,000 $208,000 $1,278,000
�
4.2 Assessment Area
� All lots within the Hawkins Pond preliminary plat,except for Lot l 1 of
Block 2, are subject to assessments to recover the project costs. Lot 11
of Block 2 was previously assessed for City utility and roadway
� improvements under other projects.
Under normal circumstances, the sanitary sewer and storm sewer
� improvements which are part of this project and which provide benefit to
the Church would be assessed to the Church. These improvements
include the sewer extension to the southeast corner of the Church
� property and the storm sewer extension to the westerly plat boundary.
However, one of the conditions of the sale of property by the Church to
the developer was that the developer would pay the costs of any
� assessments to the Church. Accordingly, the Church is not considered
part of the assessment area.
� i
Hawkins Pond Street and Utility tmprovements A-ROSEM9604.02 �
� Rosemount, Minnesota Page 9
�
� The three 3 existin lots alon 145th Street which will receive sanita
( ) g g n'
sewer service are also considered part of the assessment area.
� A summary of the parcels included in the assessment area is presented in
Table 3.
� Table 3
Assessment Area
� Hawkins Pond Preliminary Plat No. of
Block Lots Assessabie Lots
1 1 1
� 2 1 - 10 10
3 1 -23 23
� 4 1 - 15 15
5 1 - 19 19
� Subtotai 68
� Parceis Along 145th Street West
No. of
Owner(s) Street P.�.N. Assessabie Lots
Address ,
� Floyd Berg 4335 34-03010- 1 '
010-43
David&Judith 34-03010-
� Bezenek 4275 010-45 1
Greg&Teresa 34-03010-
Goettsch 4255 010-36 �
� Subtotal 3
� TOTAL NO.OF ASSESSABLE LOTS 71
� 4.3 Cost Recovery
The cost for this project will be recovered from City core funds and
� special assessments.
:� Because the proposed 12-incfl water main in Dekalb Avenue is a trunk
facility, the difference in cost between this 12-inch main and an 8-inch
� main is considered a City core cost. Accordingly, this cost is proposed
to be recovered from the City's Water Main Core Facility Fund. For
Phase A + B, this amount is estimated to be $19,000. Likewise, the
� 12-inch storm drain forcemain along Davenport Avenue is also
` considered a trunk facility, and the cost is pro�osed to be recovered from
the City's Storm Drain Core Facility Fund. For Phase A+B,this arnount
�; is estimated to be $19,000.
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota page 10
�� . . . . .. . . � � ��I
� After the water main and storm drain core costs are subtracted from the II
total, the remaining assessable costs are estimated to be $1,240,000 for
� Phase A +B. A summary of the City core costs and assessable costs is '
presented in Table 4.
� . Table 4
C�ty Core Costs and Assessable Costs
� City Water City Storm Total City Remaining
Phase 7otal Cost Main Core Drain Core Assessable
Costs Costs Core Costs Costs
� A $944,000 $7,000 $19,000 $26,000 $918,000
B $334,000 $12,000 $0 $12,000 $322,000
A+B $1,278,000 $19,000 $18,000 $38,000 $1,240,000
�
The extension of sanitary sewer facilities to serve the three{3) existing
� lots along 145th Street is a benefit which is assessable to these lots.
For the two lots on each side of Davenport Avenue (Lots 010-36 and
� 010-45),the estimated additional cost that is necessary to provide sewer
service to the lots is$6,500,or$3,250 per lot. This is the cost to extend
the sewer main further to the south along Davenport Avenue to serve the
� two lots. •
For lot 010-43, the estimated cost to run sewer south from 144th Street
� West to lot 010-43 is$8,700. However,this extension also serves Lot 11,
Block 4. Therefore, only one-half of the cost, or$4,350, is assessable to
lot 010-43.
� After these assessments for lots 010-36, 010-45, and 010-43 are
subtracted from the total assessable cost, the remaining amount is
� assessable to the Hawkins Pond development. A breakdown of the
assessable costs is presented in Table 5.
�� Table 5
Breakdown of Assessable Costs
,N
� Hawkins No.of
Sanitary Sanitary Sanitary Assessable Assessment
Assessable Pond
Phase Sewer to Sewer to Sewer to Lots in per Lot in
Costs Preliminary
Lot 010-36 Lot 010-45 Lot 010-43 P�at Hawkins Hawkins Pond
� ' Pond
A $918,000 $3,250 $3,250 $0 $911,500 43 $21,198
B $322,000 $0 $0 $4,350 $317,650 25 $12,7d6
�; A+B $1,240,000 $3,250 $3,250 $4,350 $1,229,150 68 $18,076
.
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota Page 11
�
� The assessment er lot for Phase A is hi her than for Phase A + B
P g
because Phase B has fewer costs associated with it. For example, much
� of the sanitary sewer for Phase B is already inplace. Also, Phase B does
not include any site grading or pond lining costs.
� Since Phase B cannot be completed by itself, the lowest assessment per
lot results from constructing both phases of the project together at one
time. Phase B has fewer infrastructure needs,and this helps to reduce the
� assessment per lot for Phase A+B.
1
5.0 Project Schedule
� The proposed schedule for this improvement is listed below. This
schedule is based on the provisions of Chapter 429 of the Minnesota State
� Statues. The schedule assumes that all elements of the improvement,
including developer obligations and easement acquisitions,are completed
in a timely manner.
� . R
ece�ve Feasibility Report,
Set Public Hearing February 18, 1997
� • Conduct Public Hearing, Order Plans and
Specifications March 4, 1997
� • Receive Plans and Specifications,
Order Add for Bid March 18, 1997
� • Open Bids April 11, 1997
• Receive Bids/Award Contract April 15, 1997
� • Begin Construction May, 1997
• Substantial Completion Fall, 1997
� • Bituminous Wear Course and Final Completion Spring, 1998
• HoldAssessment Hearing Fall, 1998
� • First Payment Due wlTaxes Spring, 1999
�
�
�' ��
�
Hawkins Pond Street and Utility Improvements A-ROSEM9604.02
� Rosemount, Minnesota Page 12
�
�
Appendix A
I�'' � Detailed Cost Estimates
�
� .
�
�
�
�
� •
�
�
� �i
� �
�
�
�
�
� .
�
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility improvements
City Project No. 275
, � SEH No. A-ROSEM9604.02
Sanitary Sewer Construction
, �; Phase A
� ! Description Unit Quantity Unit Price Amount
� 8" PVC Sanitary Sewer Pipe (10' - 15') L.F. 1,315 $15.00 $19,725.00
8° PVC Sanitary Sewer Pipe (15' - 20') L.F. 540 $20.00 $10,800.00
8" PVC Sanitary Sewer Pipe (20' - 25') L.F. 500 $31".00 $15,500.00
� 4" PVC Service Pipe L.F. 2,220 $8.00 $17,760.00
8"x 4° PVC Service Wye Each 47 $75.00 $3,525.00
4" PVC Service Riser L.F. 160 $14.00 $2,240.00
� STD Manhole 10' Deep w/Casting Each 11 $1,400.00 $15,400.00
Excess Manhole Depth L.F. 62 $100.00 $6,200.00
Outside Manhole Drop Section L.F. 20 $10Q.00 $2,000.00
� Connect to Existing Sanitary Sewer •Each 2 $500.00 $1,000.00
Cut in 8" x 4" Wye Each 1 $1,000.00 $1,000.00
Crushed Rock Pipe Foundation Ton 300 $12.00 $3,600.00
� Replacement Backfill Ton 300 $5.b0 $1,500.00
Subtotal Sanitary Sewer Construction $100,250.00
� Plus 10% Contingencies $9,750.00
Estimated Construction Cost $1 i 0,000.00
� Plus 30% Administrative, Legal, Fiscal and Engineering $33,000.00
Total Estimated Cost $�143,000.00
�
� I
� �
�
�
�
�
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH Na A-ROSEM9604.02
Water Main Construction
�+ Phase A
� __ Description Unit Quantity Unit Price Amount
� 6" DIP Water Main, Class 52 L.F. 390 $16.00 $6,240.00
8" DIP Water Main, Class 52 L.F. 2,210 $18.00 $39,780.00
12° DIP Water Main, Class 51 L.F. 550 $24.00 $13,200.00 *
� 6" Gate Valve & Box Each 7 $500.00 $3,500.00
8" Gate Valve & Box Each 4 $600.00 $2,400.00
12" Gate Valve & Box Each 1 $1,000.00 $1,Q00.00 *
� Remove Existing Hydrant Each 1 $500.00 $500.00
Hydrant Each 7 $1,250.00 $8,750.00
DIP Water Main Fittings Lb. 1,000 $2.00 ,_ $2,000.00 *
� Connect to Existing Water Main •Each 3 $600.00 _' $1,800.00
1° Corporation Each 48 $50.00 $2,400.00
1" Copper Service L.F. 2,400 $8.00 $19,200.00
� 1" Curb Stop Each 48 $100.00 $4,800.00
Crushed Rock Pipe Foundation Ton 150 $12.00 $f,800.00
� Replacement Backfill Ton 150 $5.00 $750.00
12° x 12" Wet Tap Each 1 $2,200.00 $2,200.00 *
� Subtotal Water Main Construction $110,320.Q0 *
Plus 10% Contingencies $10,680.00
Estimated Construction Cost $121,000.00
� Plus 30% Administrative, Legal, Fiscal and Engineering $3fi,400.00
Total Estimated Cost $157,000.00 *
� *
Includes City Water Main Core Cost of . . . . . . . . . . . . . . . . $7,000.00
�
�
� ',
�
�
,
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements ,
City Project No. 275
� SEH No. A-ROSEM9604.02
Storm Drain Construction
�' Phase A :
,� _ Description Unit Quantity Unit Price Amount
� 12" RCP Storm Drain Pipe L.F. 320 $20.00 $6,400.00
15" RCP Storm Drain Pipe L.F. 800 $23.00 $18,400.00
18" RCP Storm Drain Pipe L.F. 800 $25.00 $20,000.00
� 24" RCP Storm Drain Pipe L.F. 70 $35.00 $2,450.00
27" RCP Storm Drain Pipe L.F. 170 $38.00 $6,460.00
36" RCP Storm Drain Pipe L.F. t70 $52.00 $8,840.00
� 42" RCP Storm Drain Pipe L.F. 65 $70.00 $4,550.00
12" DIP Storm Forcemain L.F. 550 $24.00 $13,200.00 *
� Manhole, Type B L.F. 80 $150.00 $12,000.00
Catch Basin, 7ype X ' L.F. 55 $150.00 $8,250.00
Catch Basin, Type Y L.F. 20 $150.00 $3,000.00
� R-1733 Manhole Casting Each 11 $300.00 $3,300.00
R3067V Catch Basin Casting Each 15 $300.00 $4,500.00
24° RCP Apron with Trash Guard Each 1 $1,200.00 $1,200.00 ,
� 42" RCP Apron with Trash Guard Each i $1,800.00 $1,800.00
Crushed Rock Pipe Foundation Ton 250 $12.00 $3,000.00
Grouted Riprap C.Y. 25 $80.00 $2,000.00
� Granular Filter Blanket C.Y. 50 $10.00 $500.00 - '
Silt Fence L.F. 1,400 $2.00 $2,800A0
Straw Bales Each 150 $6.00 $900.00
� �
Subtotal Storm Drain Construction $123,550.00
Plus 10% Contingencies $12,450.00
� Estimated Construction Cost $136,000.00
Plus 30% Administrative, Legal, Fiscal and Engineering $40,000.00
� Total Estimated Cost $176,000.00 *
� * Includes City Storm Drain Core Cost of . . . . . . . . . . . . . . . . . . . . $19,000.00
�
�
�
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH No. A-ROSEM9604.02
Street Construction
� Phase A
� Descri tion Unit Quantit Unit Price Amount
Y
I � Mobilization L.S. 1 $8,000.00 $8,000.00
Common Excavation C.Y. 1,800 $2.00 $3,600.00
Granular Borrow C.Y. 1,800 $4.00 $7,200.00
� Subgrade Preparation R.S. 26 $100.00 : $2,600.00
Test Rolling R.S. 26 $20.00 $520.00
� Aggregate Base Placed, Class 5 C.Y. 2,000 $12.50 $25,000.00
Base Course Mixture, Type 31 Ton 1,200 $22.00 $26,400.00
Bituminous Material for Tack Coat Gallon 450 $1.00 $450.00
� Wearing Course Mixture, Type 41 Ton 1,200 $24.00 $28,800.00
Adjust Gate Valve Box Each 5 $150.00 $750.00
Adjust Frame and Ring Casting Each 20 $200.00 $4,000.00
� 4" Concrete Walk S.F. 12,000 $1.80 $21,600.00
Remove Concrete Curb and Gutter L.F. 200 . $5.00 $1,000.00
Concrete Curb and Gutter, Modified L.F. 5,200 $6.00 $31,200.00
� Concrete Curb and Gutter, B618 L.F. 550 $12.00 $6,600.00
Salvaged Permanent Barricades L.F. 25 $6.00 $150.00
� Salvaged Topsoil C.Y. 8Q0 $6.00 $4,800.00
Seeding Acre 3 $500.00 $1,500.00
Mulch with Disk Anchoring Acre 3 $500.00 $1,500.00
� Sodding S.Y. 3,600 $2.00 $7;200.00
Subtotal Street Construction $182,870.00
� Plus 10% Contingencies $17,130.00 �
Estimated Construction Cost $200,000.00
Plus 30% Administrative, Legal, Fiscal and Engineering $60,000.00 ,
� Total Es#�mated Cost $260,000.00
� ,
'�
�
�
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH Na A-ROSEM9604.02
Site Grading
� Phase A
I� � Description Unit Quantity Unit Price Amount
� Common Excavation C.Y. 37,400 $1.30 $48,620.00
Unclassified Excavation C.Y. 8,000 $4.00 $32,000.00
Pond Liner Excavation C.Y. 11,900 $2.25 $26,775.00
'� Salvage Topsoil C.Y. 12,900 $3.00 $38,700.00
Subtotal Site Grading Construction $146,095.00
� Plus 10% Contingencies $13,905.00
Estimated Construction Cost $160,000.00
� Plus 30% Administrative, Legal, Fiscal and Engineering $48,000.00
Tota1 Estimated Cost $208,000.00
�
�
�
� I�I
� I
�
�
�
�
�
�
ESTIMATE OF COST
, � Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH No.A-ROSEM9604.02
Sanitary Sewer Construction
'�, � Phase B
� Description Unit Quantity Unit Price Amount
� 8" PVC Sanitary Sewer Pipe (10' - 15') L.F. 455 $15.00 $6,825.00
8" PVC Sanitary Sewer Pipe (15' - 20') L.F. 440 $20.00 $8,800.00
8" PVC Sanitary Sewer Pipe (20' - 25') L.F. 110 $31.00 $3,410.00
� 4" PVC Service Pipe L.F. 1,215 $8.00 $9,720.00
8" x 4° PVC Service Wye Each 14 $75.00 $1,050.00
4" PVC Service Riser L.F. 110 $14.00 $1,540.00
� Reconstruct Manhole L.F. 32 $150.00 $4,800.00
Remove and Replace Forcemain L.F. 330 $30.00 $9,900.00
� STD Manhole 10' Deep w/Casting Each 5 $1,400.00 $7,000.00
Excess Manhole Depth " L.F. 45 $100.00 $4,50a.00
Outside Manhole Drop Section L.F. 8 $100.00 $800.00
� Connect to Existing Sanitary Sewer Each 2 $500.00 $1,000.00
Cut in 8" x 4" Wye Each 13 $1,000.00 $13,000.00
Crushed Rock Pipe Foundation Ton 200 $12.00 $2,400.00
� Replacernent Backfill Ton 200 $5A0 $1,000.00
Abandon Existing Sewer Serviee L.S. 1 $2,000.00 $2,000.00 �
Subtotal Sanitary Sewer Construction $77,745.00 I
� Plus 10% Contin encies 7 2
g $ , 55.00
- fstimated Construction Cost $85,000.00
� Plus 30% Administrative, Legal, Fiscal and Engineering $25,000.00
Total Estimated Cost $110,000.00
�
�
�
�
�
�
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH No. A-ROSEM9604.02
Water Main Construction
� Phase B
� Description Unit Quantity Unit Price Amount
� 6" DIP Water Main, Class 52 L.F. 25 $16.00 $400.00
12° DIP Water Main, Class 51 L.F. 1,230 $24.00 $29,520.00 *
6" Gate Valve & Box Each 2 $500.00 $1,000.00
� 12" Gate Valve & Box Each` 3 $1,000.00 $3,000.00 *
Hydrant Each 2 $�,250.00 $2,500.00
DIP Water Main Fittings Lb. 600 $2.00 $1,200.00 *
� Connect to Existing Water Main Each 2 $600.00 $1,200.00
1" Corporation Each 25 $50.00 $1,250.00
1" Copper Service L.F. 1,250 $8,00 $10,000.00
� 1" Curb Stop • Each 25 $t00.00 $2,500.00
Crushed Rock Pipe Foundation Ton 100 $12.00 $1,200.00
Replacement Backfill Ton 100 $5.00 $500.00
� *
Subtotal Water Main Construction $54,270.00
Plus 10% Contingencies $4,730.00
� Estimated Construction Cost $59,000.00
Plus 30% Administrative, Legal, Fiscal and Engineering $17,000.00
� Total fstimated Cost $76,000.00 *
� * Includes City Water Main Core Cost of . . . . . . . . . . . . . . . . . . $12,000.00
�
�
�
�
i
�
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH No. A-ROSEM9604,02
Storm Drain Construction
� Phase B
� Description Unit Quantity Unit Price Amount
� 12" RCP Storm Drain Pipe � L.F. 60 $20.00 $1,200.00
15" RCP Storm Drain Pipe L.F. 120 $23.00 $2,760.00
18" RCP Storm Drain Pipe L.F. 50 � $25.00 $1,250.00
� 27" RCP Storm Drain Pipe L.F. 450 $38.00 $17,100.00
Manhole, Type B L.F. 35 $150.00 $5,250.00
Catch Basin, Type X L.F. 15 $150.00 $2,250.00
;� Catch Basin, Type Y L.F. 5 $150.00 $750.00
R-1733 Manhole Casting Each 5 $300.00 $1,500.00
� R3067V Catch Basin Casting Each 4 $300.00 $1,200.00
Crushed Rock Pipe Foundation ' Ton 100 $12.00 $1,200.00
Silt Fence L.F. , 700 $2.00 $1,400.00
� Straw Bales Each 50 $6.00 $300.00
Subtotal Storm Drain Construction $36,160.00
� Plus 10% Contingencies $2,840.00
Estimated Construction Cost $39,000.00
Plus 30% Administrative, Legal, Fiscal and Engineering $11,000.00
� Total Estimated Cost $50,000.00
�
�
�
� '�
� .
�
�
�
ESTIMATE QF COST
� Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH No. A-ROSEM9604.02
Street Construction
� Phase B
� Description Unit Quantity Unit Price Amount
� Mobilization L.S. 1 $3,000.00 $3,000.00
Common Excavation C.Y. 800 $2.00 $1,600.00
Granular Borrow C.Y. 800 $4.00 $3,200.00
� Subgrade Preparation R.S. 12 $100.00 $1,200.00
Test Rolling R.S. 12 $20.D0 $240.00
Aggregate Base Placed, Class 5 C.Y. 900 $12.50 $11,250.00
� Base Course Mixture, Type 31 Ton 550 $22.00 $12,100.04
Bituminous Material for Tack Coat Galion 200 $1.00 $200.00
Wearing Course Mixture, Type 41 Ton 550 $24.00 $13,200.00
� Adjust Gate Valve Box ' Each 4 $150.00 $600.00
Adjust Frame and Ring Casting Each 9 $200.00 $1,800.00 �,
� 4" Concrete Walk S.F. 0 $1.80 $0.00 !
Remove Concrete Curb and Gutter L.F. 0 $5.00 $0.00 ,
Concrete Curb and Gutter, Modified L.F. 2,400 $6.00 $14,400.00
� Concrete Curb and Gutter, B618 L.F. 0 $12.00 $0.00 '
Salvaged Permanent Barricades L.F. 0 $6.00 $0.00
Salvaged Topsoil C.Y. 400 $6.00 $2,400.00
� Seeding Acre i.5 $500.00 $750.00
- Mulch with Disk Anchoring Acre 1.5 $500.00 $750.00
Sodding S.Y. 1,600 $2.00 $3,200.00
�
Subtotal Street Construction $69,890.00
� Plus 10% Contingencies $6,110.00
Estimated Construction Cost $76,000:00
� Plus 30% Administrative, Legal, Fiscal and Engineering � $22,000.00
Total Estimated Cost $98,000.00
�
■
�
�
�
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements
City Project No. 275
� SEH No. A-ROSEM9604.02
Sanitary Sewer Construction
� Additional Cost to Serve Lots 010-45 and 010-36
� Description Unit Quantity Unit Price Amount
� 8" PVC Sanitary Sewer Pipe (10' - 15') L.F. 150 $15.00 $2,250.00
4" PVC Service Pipe L.F. 200 $8.00 $1,600.00
8" x 4" PVC Service Wye Each 4 $75.00 $300.00
� Crushed Rock Pipe Foundation Ton 20 $12.00 $240.00
Replacement Backfill Ton 30 $5.00 $150.00
� Subtotal Sanitary Sewer Construction $4,540.00
Plus 10% Contingencies $460.00
Estimated Construction Cost $5,000.00
# Plus 30% Administrative, Legal, Fiscal and Engineering $1,500.00
Total Estimated Cost to Serve 010-45 and 010-36 $6,500:00
�
$6,500 - 2 lots = $3,250f1ot
� �'
� �
�
�
�
�
�
�
�
. � �� . . . .. . � . �
ESTIMATE OF COST
� Hawkins Pond Addition
Street and Utility Improvements
� City Project No. 275
', � SEH No. A-ROSEM9604.02
Sanitary Sewer Construction
� Additional Cost to Serve Lot 010-43
� Description Unit Quantity Unit Price Amount
� 8" PVC Sanitary Sewer Pipe (15' - 20') L.F. 110 $20.00 $2,200.00
4" PVC Service Pipe L.F. 90 $8.00 $720.00
8" x 4" PVC Service Wye Each 2 $75.00 $150.00
� 4" PVC Service Riser L.F. 20 $14.00 $280.00
STD Manhole 10' Deep w/Casting Each 1 $1,400.00 $1,400.00
Excess Manhale Depth L.F. 13 $100.00 $1,300.00
� Crushed Rock Pipe Foundation Ton 10 . $12.00 $120.00
Subtotal Sanitary Sewer Construction $6,170.00
� Plus 10% Contingencies $530.00
Estimated Construction Cost $6,700.00
Plus 30% Administrative, Legal, Fiscal and Engineering $2,000.00
� Total Estimated Cnst $8,700.00
� Minus 50% Developer Cost ($4,350.00)
� Total Estimated Cost to Serve 010-43 $4,350.00
�
� �
�
�
�
�
�
I_
�
,l
. �.�
— ,
, a. �, � �
� , ��,,w���a��; ol.. 0�14
����� o�i �3�0
�•���„�� �' ✓
•-_ ---- -__
s !���p��„4!�`°�,.B�O
�� ��/�c. "�""� �����
-'= 3��► p �
1 v. � ���o�� ��%� O
� �M '.���� v����� . . .
� � ��� o���o����0��, • . • ' •
���� � �1,,��,��r''�V� .
;_� ;�.� �s�,,�e ey11� ��
� �..��: ��o�����o���a�/
- � ����������
� �����3a����z�r��e
� ��� ��� ���
,� :sa%r-�+�'`'��i�.,�'�,'����� Q ■�� ❑E3��0�"JQ
�, `6e��'4s'� a��; v�S,..cv, � � +� �
� ��� �,,s������� 3 � ,'�It� �y os�:�a��e
�. �avy�ll;�w' � n1�!�'
�� ��F�E p ■0 ����aa...�r.
�����s�,t.a:����'��i �■G�1/��G�o ��.�1�0�0�'
�, 'u'.�'>:< <:.rfF3f�.�,� W'-x � r�,w��` "'��
�������I'���t9� �d��� ��Q����1
� c+�*�aE'��v�� �► � r� a�oaoa ����
��� �e �� ��� ��: � �
'�' ►.y�:� a:
�e �� o �q� ��o o � Q �� a o���� s��
�� �' �����'`� �� • i C � � ! ���3j �� L���a� 11�1
Q ' !o v � ��, '�� . � a '''' 3�3� ►'�� ��'.�.:, F!M"�
�'� ' � '� � � �3:� t�� � � v � � R !�`�0�p�R'�0 Q �E����.
!-�� �� � - Y`C�q .>� . � �l����*�3t,��'�I1E�C'�
�C
,�.�g :��� ��t�a� a� • �o' ;; � c��������
� � Q�o�� �,;. �n.� A�� �;�e �lT.a�I1C1Gl�a��Q �
� Q �, ' 0►'FJ � ��� <1i �i ��Q�y��� 't.3 t�..:"`�'i',
M-f . � � d� O'a� �� �� .c � R�'„s7m!'�11
� >a - '� �, ��o f,,�j 1�,�e. -r� .v rso �QGQ •t�ifi�7aa� �
� o a � A 4' s.: �� �n o� �o ���"��3'�'���' �? �
.. .,� � .�o �i ._ �.- �.� �.� — � � �'^�l��ol� �1
� � ■� n� r-�r; �►, c:s
r'- ��r �A t�:7�: ►�� �`� `� � C�
�� �t�, tri�� -� ❑: �r �r; �R; � a o.'� �f,'+�� r �a� d � ,
� ' F� - t � �� : �[- ��c� �. � �� ,� ■ r� o♦`,--,, � � �
� 'f'' , ��s� ��1 � ��; �e: �t,� =� ,..�+iCii�i�rt� � '� � _: �k
� �cy: • a �c; �►,-; �r.
� � �+� �•�Q '�y n c• i o�r o =h�~`�' ..�i ►.c ►�
/ �;��-� . L
.
�r�����Q�G�G�?CCta �.'�t:�ii ' . � d�:���►� � ���
� y
� �
-
� � � r � � � � ' o ' � �
-..� ..,
J ' • i � . . . � � � �
�
�
' ' � NOT REQUIRED FOR THIS PROJECT
Q � BITUMINOUS WALK 'K CONCRETE WALK � A
1 0 � � � � �
; �
. o
� , , 60� , �
� SLOPE�/�" PER FC�pT 32' SL PE�/�'� PER� FOQTj �
� ��
-�r�— 8' �-�-3y=-� CONCRETE CURB � 4 GROWN �6yZ � 1 5� --I r�-'
' AND GUTTER � T •
. ,
� , �9' —� , . s'-� ,
I � I
, �
. : �
I 1
� 2" BITUMINOUS WALK ,.
MN DOT 2331TYPE 41 4 CONGRETE
�' WALK
:.t:
� 6" CLASS 5 AGGREGATE
BASE COURSE
(100% CRIJSHED QUARRY ROCK)
� COMPACTED SUB-GRADE -
4" MN DOT 3149.2 B
SELECT GRANU�Aft BORROW
�
2" BITUMINOUS WEAR COURSE
� - MN DOT •2331 TYPE 41
MN DOT •2357 BITUMINOUS TACK COAT
2" BITUMINOUS BASE COURSE
MN 00T •2331TYPE 31
� 6" CLASS 5 AGGREGATE
BASE COURSE
(100% CRUSHED QURRRY ROCK)
� 6" MIN. SCARIFY lW0 COMPACT
SUB-GRADE
' NOTES�
� 6" CONCRETE SIDEWALK IN ORIVEWAYS.
� CONTRACTION JOINTS AT 5'INTERVALS.
, � EXPANSION JOINTS AT 60'GdTERVALS (MAX.).
� PED RAMP PER CURRENT MNOOT SPEGFICATION :
AND STANDARD P�ATE WITH EXPOSED AGGREGATE '
SURFACE TREATMENT AND RAMP OIMENSIONS OF
� 5'� 5'• 5'- 15'AT CURBS. NO SGALE
Drowing Title Dote �
' �• u� STANDARD RESIDENTIAL 1/25/95
� � CROSS SECTION P�ate no.
I ST-�
_ � No.
HAWKINS POND TYPICAL SECTION Ros�s6o4 6
:� DAlE
�
� ROSEMOUNT, MINNESOTA CITY PROJECT N0. 275 2_,�97 7
� N
,
' 200 0 200
••,:
.. .. .. . . . . . . . .......... . . .. . . . . .... ..f: . . . . .
, � B OCK 2 �
pC, SCALE IN FEET
0� � 1 2 3 4 5 6 7 8 9 10 11
� •
_
� > ; � 2 3 2 i 143 D STREET W. .
� N . Q . � . � . . .
N
� . . � . . � � . .
N 2 �
� Q 19 4 3
�
3 � 5 23 22 21 20 19 18 17 16
18 � � •�'
� � • 4
d. 4
6
v 17�'? � �..._ 5
� •;:;:�'5 ••Y o B OCK 3 �I
r � � . ,s v � a 6 �,
n 6 O � ••t: ',
rn Q �
o v t5 8 p � II
' � �
o � 14 9
8 8
'
9 13 12 11 10 g
144 H TRE T W.
� 10 12 13 14 15
10
�� 12 13 14 15
, 11
� N
d
�
, �
O
c0
�
�'
�
O
� � 145TH STREET W.
�
w
�
' o
�
� �
a
�
0
� �
a
Q FILE N0.
U
� ROSEMOUNT HAWKINS POND PROPOSED PHASES Ro�s6o4 7
��� MINNESOTA CITY PROJECT N0. 275 �ArE
� 2-,a-s� 7
� N
�
� � 200 0 200
v
� 100
SCALE IN FEET
v
�
N CUT IN WYE $„ V�
� ON EXISTING " 143RD STREET W. _
o SEWER MAIN w o , �
� (TYP.) `t �� �
� m � � � �
� � � -
� Q v "; �
� Y .•'•
�� �
W ••• U i i .,
j • W . � � . „
� .,... :.� Q — — — — — — — — Z .
� i••.: o � 925 � �( .
q , '
o _'� � g2� 915 � �' .
O Q .
� � � I �
Z I
CLEAN � � � I . .
�. - OUT ) � . � � � .
� � `Z � I
o \ � H W K I N S
i �s� �� I
o `��� �
RELOCATE EXISTING _ J 0 N D �
� SEWER SERVICE TO F —' F— 'F — I
FIRST BAPTIST �� � (
CHURCH OF ROSEMOUNT 144 H TRE T W. �
, — — 915 920
/ — —
/'I , � SEWER � s2s» � < �
�/, �I� � � $,. PVC �� — — '
� �� �_J , N0. 4 � �
010-40 020-40 � CUT IN WYE
� RELOCATE — ON EXISTING
N EXISTING � � 010-43 010 45 010-36 � SEWER MAIN
a FORCE MAIN (4I
� o� � -- �
� o � -- � --- ---
� � I
� --- --- --- --- --- --- --- --- - --- - - -- --- -- -- --- ---
� � � � � � � � � � �
�r « < « < «
0
� � 145TH STREET W.
�
W
N
� O
�
�
a
�
0
� �
a
a FILE N0.
� � R(JSEMOUNT HAWKINS POND SANITARY SEWER Ros�seo4 2
v��E� MINNESOTA CITY PROJECT N0. 275 IMPROVEMENTS aATE
� 2-,8-9� 7
� N
�
� i 200
-
-
v CONNECT TO ' ' " """"'�'
. . .. . . . . . . . .......... . . .. . . . . ...�:.. . . . .
■ 1�
SCALE IN FEET
v
� CONNECT TO
= 8" DIP EXISTING W.M.
w
`� � 143RD STREET W.
� �' W �P
3 Q ���
, � m . . � . . .
�� 12" I P .. • � � . "
o Q � ".: �
� Y :.,•: � � � .
W •• � U � � .,
• � . � � ..
� E •.;:. Q — — — — — — — — -� o '
� 925 �I
2� 9�5 ( Q
� .
o . p (�� 9 ' �
� M Z I �
� CLEAN � � � I . � I � � �
r � � OUT o----� � Q . ( � � �
°' o � H WKI NS
� � ''
N I
� � 0 N D �
� � � � . � � , F > F �.J � I � � . .
r4 � I
I 144 H TRE T W. � 9�5
� — — — 925 920
<— ,
�I� ��— �
I 12' DIP 12" DIP — — — �
� � � �
010-40 020-40 �
� I
a I�I 010-43 010-45 010-36 � 6" DIP .
o � � �
� � --- --- --- --- --- �--- --- --- - --- - ---�---- --- -- - -- --- --- ---
� � � � � � � � � � ,
d. « < « « «
0
� � 145TH STREET W.
w OPEN CUT STREET, REMOVE HYDRANT
o WET TAP ONTO AND CONNECT TO
� � EXISTING W.M. EXISTING HYDRANT
Q LEAD
�
0
� �
Q
Q FILE N0.
� ROSEMOUNT HAWKINS POND WATER MAIN RosEMssoa
�E�I MINNESOTA CITY PROJECT N0. 275 IMPROVEMENTS pA� 3
� 2-78-97 �
� N
�
�
:•,:••.: ::.............: . ... . :.. .......,
, ;........ . ... ........... .
200 0 200
� . .. . . . . . .......... . . . . . . ....:.. . . . . . .
� �
SCALE IN FEET
v
i
_
,.
W
�' � 143RD STREET W. '
� � l.�' ---
3 Q ���
a) � ,�$r. i j
. . ' ~ v � . . . .
� ` ' _ � .
� Q � ••,:. � � 20' DRAI AGE & �
W .. � � � i UTI TY ASE ENT �-� � .. ..
i ' '
■ . ... Q _ - - -� - - - - � z :';'•.. �
� r••.. ' �— O(
o �„_, 925 I t/�
co � . . . . .. . °��� gt5• � �' ' �
N . � .. . . . . . . . . Q
� � Z .' '.'. ....:..: .:.:.:. ,.:..:..� ....... . .... .�. � .
'
� EXISTING
. ^ � CLEAN �Z� `��� > ....... ..�.�.�. .�.�.�. .... . . . ..... .'...... .... I .
°�T�---> �-r� STORM POND
o '��, ��, —27��—`� 36� I .:.:� :.:.:.: :�.H. . W.��K . .I. N. .S :�::: : :
� i � '�,',` ------ ---- .. .. . . . . . . . . .. . . . ... . . . .. . ( �INE LOWER
� � � .. ..:... . :�..O N D . I TOREL�EVA�ION 9N 6.5
� - - - -� -J .:...:.....:.......:.:. ...:.:.:.:.:.:...� �.�.�.�. .�.�.... :.:._
F —' F ?F I WITH 18" CLAY
. . . . . .. . .
� 1 �. . . .. . . . . . . . . . .. . . .. .� �.�.�.�.�.�. .�.�.�. .�.� . . . .� � LINER TO CREATE
144 H TRE T W. � . . . . . . . . . ._.�.�.�.�.�.�.�. ��������� . . .�. .� � 3' OF STANDING
' �_' —— — ��s�� WATER.
. . .. . . .
� 925 920
�
; �
. �� — — �
�
�I� 1� — — — I
� �
I I � 010-40 020-40 � �'
' t I
a I i I 010-43 010-45 � 010-36 I
o II ; 8' �
� � �--- ' �
--- --- --- --- --- --- --- � --- - - -- --- -- -- --- --- --- ---
� � � � � � � � � ,
� < < < «
a
� � 145TH STREET W.
w 8" DIP FORCE MAIN
o FOR FUTURE (STORM)
� � LIFT STATtON
�
a
�
0
0
�' a
a FILE N0.
U
� ROSEMOUNT NAWKINS POND STORM DRAINAGE Ros�sso4 4
� MINNESOTA CITY PROJECT N0. 275 IMPROVEMENTS oAr�
�` 2-16-97 �
� N
�
, i 200 0 200
" . . .. . . . . . . . . .... . .. . . . . ..�_:. . . . . .
� 100
SCALE IN FEET
PERMANENT
' BARRICADES�� STREETUMINOUS
_
w
� `� 143RD STREET W. ---
� �.i I
3 �C '�` ,'
� . m 60' R/W
� _ . . • f— v � . . •
'� •.�. �' �
o •: • �
� Y ,:,°: �.�� • 5' CON W LK .
:' p � �
W •• � C.� i i ..
• � . � � ..
� :'•:� �T — — — — — — — — � Z •• �
� :'•r••..��'� � O I I
o � 925 � .
� � 92� 915 I � '
N . Q Q ,
, � z I �
� CLEAN � ] � � I . I
I
, 0 o�T,�--_> o � H W K I N S
i REMOVE EXIST.
o I O N D i DRIVEWAY
, . . . F - ' F , F J I � . . � .
_ _ � � I
144 H TRE T W. � s�5 �
� — — — 925 920
— <—
I lj `�— — — `— �
� I``� �
010-40 020-40 � REMOVE EX. DROP CURB
� AT HAWKINS' DRIVEWAY,
I I � AND INSTALL B618
N 010-43 010-45 010-36 I
� I�-I I CONCRETE CURB & GUTTER. �
o � � I
� � -- --- --- �---
--- --- - --- --- --- - - -- --- -- -- - -
� � � � � � � � � � �
� « « < « «
� o
� 145TH STREET W.
� REMOVE EX. DROP CURB
N AT UFT STATION DRIVEWAY,
, � AND INSTALL 661$
Q CONCRETE CURB & GUTTER.
�
0
� �
Q
U
Q
_ FILE N0.
� ROSEMOUNT HAWKINS POND RosEMseoa 5
�� MINNESOTA CITY PROJECT N0. 275 STREET IMPROVEMENTS oarE
� 2-78-97 �