HomeMy WebLinkAbout6.g. Payment #1, Wellhouse No. 9, City Project #273BCITY OF ROSEMOUNT
EXECUTIVE SUMMARY FOR ACTION
CITY COUNCIL MEETING DATE: December 17, 1996
AGENDA ITEM: Payment #1, Wellhouse #9
AGENDA SECTION:
City Project #273B
Consent
PREPARED BY: Bud Osmundson
City Engineer/Public Works Director
AGEND-%
TTW #6 G
ATTACHMENTS: Payment #1
APPROVED BY
This is a request for Council consideration for Payment #1 for City Project #273B,
Pumphouse #9 construction. The amount requested is $51,860.97 to Municipal
Builders, Inc. Staff recommends payment as requested.
The Construction Status Report is attached F.Y.I. The Contractor has completed the
installation of structural fill, the completion of the footings and partial completion of
underground plumbing, plus the well casing has been brought up to grade. The project
will probably sit pending weather conditions until February or March when further block
work can be completed. This project is on schedule and we should have Well #9 on line
prior to June or July of 1997.
RECOMMENDED ACTION: MOTION TO APPROVE PAYMENT #1 IN THE AMOUNT OF
$51,860.97 TO MUNICIPAL BUILDERS, INC. FOR CITY PROJECT #273B. I
COUNCIL ACTION:
IF
'r
CONSTRUCTION STATUS REPORT
REPORT NO. I
DATE: DEcEmzER 3,1996
PUM(P HOUSE NO. 9
FILE NO. 42408
CONSTRUCTION FOR THE WEEK OF NOVEMBER 25, 1996:
Bonestroo
Rosene
Anderilk
Assodates
are & Architects
St Paul - Milwaukee
1 . Backfilled foundation area with granular fill on Monday, November 25a.
2. Backfilled remaining area to bottom of foundation with granular fffl on Tuesday, November
26'. General Contractor installed riser pipe and stubbed out water main past footing
approximately 8 linear feet. Densities were taken on both Monday and Tuesday backfilling.
3. Silt fencing was installed on Tuesday, November 26'.
4. The footing was formed and poured on Wednesday, November 27h.
5. The block wall footing was placed on Friday, November 29'.
6. Backfilled interior of footing walls with granular fill and the exterior of the footing walls with
common fill on Monday, December 2d.
7. Completed backfilling interior of footing walls with granular fill and the exterior of the footing
walls with common fill on Tuesday, December 3rd.
CONSTRUCTION FOR REMAINING WINTER SEASON:
1 . The Mason's may lay the block walls during February if a warm week is available.
2. No more work scheduled until Spring.
Copy: Mr. Bud Osmundson, City of Rosemount
Dick Foster, Bonestroo
L\424\42408\csr02.rpt
FAX TRANSMISSION
Date: December 5,1996
Our File No.: 42408
From: Thn Grinstead
Pages To Follow: 4
Original Will Follow In Mail; Yes No K,
To: Doug Litterer Fax Number: 423-5203
Organization: City of Rosemount
Subject: Rosemount Pumphouse No. 9
Remarks:
Doug,
Following is a copy of Request for Payment No. I for the Well No. 9 Pumping
Facility in the amount of $51,860.97. Please include the pay request to the
agenda for the second council meeting in December. The 3 copies are
currently in the mail to MB1 and we will send you the signed copies by the
end of next week. Please give me a call at 604-4881 if you sbould need any
further information.
Copy to: RWF
Signed;
Note To Addressee: if you did not receive all of the pages in good condition, please advise sender at your
earliest convenience. Thank You.
I -----------------------------
For Office Use Only
Faxthenniall: Yes— No --2L— Urgent fax immediately: Yes— No—
Cjdl to conpirm fax was received: Yes— No Fax and return original to sender. Yc,-.__._ No_...
Makecoplesfer: File_0thers
Fax Copies to (tuore then one),
other!—.—
+7AC:oN 'Cn/l.n: El 0;1:()[. 1, I.0 I.occ) 7 I.C) -0- qqlWTlnqqW nNW AnMIC'4NnQ
Bonestroo
IM ftW e Uftmkn
Rosene
2=W9dHVMy38
NIM
Anderlik &
Associates
SIL Pati. MN 55113
61249*4=1
Engineers & AnhitectS
FOX 612-OW1311
Date: December 5,1996
Our File No.: 42408
From: Thn Grinstead
Pages To Follow: 4
Original Will Follow In Mail; Yes No K,
To: Doug Litterer Fax Number: 423-5203
Organization: City of Rosemount
Subject: Rosemount Pumphouse No. 9
Remarks:
Doug,
Following is a copy of Request for Payment No. I for the Well No. 9 Pumping
Facility in the amount of $51,860.97. Please include the pay request to the
agenda for the second council meeting in December. The 3 copies are
currently in the mail to MB1 and we will send you the signed copies by the
end of next week. Please give me a call at 604-4881 if you sbould need any
further information.
Copy to: RWF
Signed;
Note To Addressee: if you did not receive all of the pages in good condition, please advise sender at your
earliest convenience. Thank You.
I -----------------------------
For Office Use Only
Faxthenniall: Yes— No --2L— Urgent fax immediately: Yes— No—
Cjdl to conpirm fax was received: Yes— No Fax and return original to sender. Yc,-.__._ No_...
Makecoplesfer: File_0thers
Fax Copies to (tuore then one),
other!—.—
+7AC:oN 'Cn/l.n: El 0;1:()[. 1, I.0 I.occ) 7 I.C) -0- qqlWTlnqqW nNW AnMIC'4NnQ
0 w n c r: City of Ro.semount, P.O. Box 5 10. Rosemount, MN 55068-05 1 U
"Andwlk For Period: Start to December 3,1996 -
6
Unw.=- Controctor: Municipal Builders, Inc., 17125 Roanoke St, NW, Anoka. MN 55304
REQUEST FOR PAYMENT
WELL NO. 9
PUMPING FACILITY
File No. 42408
SUMMARY
Date:
Nf-
1996
I
Original Contract Amount
2
Change Order - Addition
3
Change Order - Deduction $
4
Revised Contract Amount
305,M)AX)
I
Value Completed to Date
$
514,192-50
6
Material on Hand
$
2,39SM)
7
Amount Earned
S
54,590.50
K
Less Retainage 59c,
$
2,729.52
9
Subtotal
$
91,800.97
to
Lcss Amount Paid Previously
$
0.00
i i
AMOUNT DUR THIS RFQUEST FOR PAYMFNT NO.
$
51,86().y7
Recommended for Approval by:
BONESTROOt ROSENE, ANDERLIK & ASSOCIATES, INC.
Approved by Contractor.'
MUNICIPAL BUILDERS, INC.
Specified Contract Completion Date:
1-�41AIA-PAMSF01 IFST.W82
4�zr,ew M eN-i-e%i I 1 0- 1
Approwd by Owncr:
C ITij0FjjtO%SKM0UNT
Date;
Part 2 - Pumphouse
27 Construct pumping facility for Well No. 9
including masonry structure, interior piping,
cheinical feed equipment, electrical controls,
mechanical equipment and correlated
appurtenances LS
28 Well pump, Section It 170 J.S
MAPAN04MINFIFOUEST.W02
47A'�:ON Olqn: rO 97:91. QA/(:0/7L
1 226,509.00
1 21,000,N)
LL5'L9q9 71.9 -10- S91VTIOqqV (INV OoMlq:IN()g
Contract
volt
Quantity
Amount
No.
Item
Unit
Quantity
Price
to Date
to Date
1
10" DIP, 8'deep in place
LF
98
100.00
8
MOO
2
6" DIP, B'deep, in place
LF
10
150.00
3
4" PVC drain pipe
LF
16
10.00
4
6" hydrant
HA
1
2.5m.00
5
6" pie valve and box
EA
1
11500,00
6
10" wet tap with g,v. and box
EA
I
2,50U.UU
7
C. 1. fittingi
EA
485
3M)
8
Drain manhole with casting
L'i
1
31(XX)I(X)
9
Remove curb and gutter
LF
10.(X)
10
Remove bituminous walk
SP
464
21M)
11
Saw cut bituminous walk
LF
16
5.(X)
12
Concrete drive entrance w/aggrepto base
SF
310
5AX)
13
Concrete curb & gutter Des, B-6 12
LY
160
12.00
14
Concrete sidewalk
SIF
270
MO
15
Bituminous sidewalk
SF
270
5,00
16
Stockpile and respread topsoil
i's
I
8M.00
0.5
4(X).(X)
17
Common fill
CY
21115
4.00
748
2,992.(X)
Is
Granular rill
CY
11500
7.50
1,539
11,542.50
19
Sand rill
CY
46
6.00
2o
Class V aggregate base
IN
42
16.00
21
Bituminous base
TN
17
75.00
22
Bituminous wear
TN
20
75.00
23
Site sodding
SY
365
3.00
24
Seeding
AC
0.5
1,5M.00
25
Erosion control (Sill Fence)
LS
1
5(X).()O
1
5M.M
26
Rock construction entrance
TN
IOU
MIX)
Total Part I - Site Work
16,234,10
Part 2 - Pumphouse
27 Construct pumping facility for Well No. 9
including masonry structure, interior piping,
cheinical feed equipment, electrical controls,
mechanical equipment and correlated
appurtenances LS
28 Well pump, Section It 170 J.S
MAPAN04MINFIFOUEST.W02
47A'�:ON Olqn: rO 97:91. QA/(:0/7L
1 226,509.00
1 21,000,N)
LL5'L9q9 71.9 -10- S91VTIOqqV (INV OoMlq:IN()g
Break Down of Part 2
'I'otal Part I - Site Work 16,234.50
'rotal Part 2 - Purnphouse 35,958,00
Total Work Completed to Date $52,192.54)
Stored Materials
Water Meter EA I 2,398.(.K.) 2,399-00
j:\424N42408\RF-QUE5T.W82
46ze -^ki e^ 14�^ - J7 e -j -j - ni ^Z leA Ill i i e-inee% -vie% E3 &,9 1
Contract
Unit
Quantity
Amount
Item
Vnit
Quantity
Price"'
to Date
to Date
Performance tx)nd and insurance
EA
1
81500.00
1
8.5(X).(X)
Mobilization
F.A
1
5,5(X).(X)
0.6
3,300.00
Sub -cut site
EA
4,300.(X)
1
4.3000)
Placesand from well
EA
2.100.00
1
2. 1 (X).(X)
Backfill labor
EA
l,guu.()O
I
I't)()().(X)
Concrete und masonry
EA
1
77,019-00
0.18
13,863,00
Precast roof
EA
I
3,300R)
().(K)
Unicis
EA
W).(X)
().(X)
Wood rix)f framing
EA
10,000SX)
().(X)
Foundatiun insulation
EA
950.(X)
0.8
760.(R)
Shingics, insulation and skylight
SA
2,2(X).00
0.00
Aluminum suffits and facia
EA
2,700.00
0.00
Caulking
FA
600.00
().(K)
H. M. doom, rratnes and hat'dware
EA
5,200.00
0.00
Overhead door
HA
950.(.X)
U.00
Painting
EA
6,430.00
().(X)
Building letter
EA
26().(X)
().(X)
Well pump
HA
1
21,000,00
0.00
Chemical feed equipment
EA
12,8()0.00
0.00
interior DTP, rittings and valves
EA
6,5w,o()
0119
1,235.W
Water meter
EA
2,5(X).(X)
0.00
Floor drains & piping
EA
4(X).00
0.00
Sprinkler systern
EA
9(K).(X)
0.00
Ventilation work
EA
4.3000)
0.( X)
Fan coil unit and pump
EA
I
3.2W,00
01(m)
Gas heatcr, piping and vent
EA
1,
3,400.(X)
()-(X)
Electrical work
FA
1
60,(M.00
(100
Total - Breakdown for Part 2
.35,958.(X)
'I'otal Part I - Site Work 16,234.50
'rotal Part 2 - Purnphouse 35,958,00
Total Work Completed to Date $52,192.54)
Stored Materials
Water Meter EA I 2,398.(.K.) 2,399-00
j:\424N42408\RF-QUE5T.W82
46ze -^ki e^ 14�^ - J7 e -j -j - ni ^Z leA Ill i i e-inee% -vie% E3 &,9 1
PROJECT PAYMENTSTATUS
Owner CITY OF ROSFMOUNT
Project No.
File No.
Contractor MUNICIPAL BUILDERS. INC.
CHANGE ORDERS
PAYMENT SUMMARY
I'li),
- -- -- uVrou
. m
. -., -
-- - - . . -
2,729.52
I
Start
12-04-96
51900.97
2,729.52
54.590-50
3
4
5
6
7
to
Material on Hand
$2,398-00
Total Payment to Date
$51,860.97
Original Contract
$305,700SX)
Retainage, Paymetit No.
2,729.52
Change Orders
,Total Amount Earned
1 $54,590.30.
Ruviscd Contract
$305,700.(X)
i-lAimemnmFir-ni 1W WAP
474 C . AKI fn i en * 07*01 04 / en / 71 1 1 C I oco 71 in 19 C=1WT1A0tW AK1W ^^MIL�71kl^ln