� � EXECUTIVE SUMMARY FOR ACTION
CITY COUNCit MEETING DATE: November 21, 1995
AGENDA ITEM: STAC Charge Change AGENDA SECTtON:
NEW BUSINESS
PREPARED BY: Bud Osmundson AGENDA �tQ�s � � � �
City Engineer/Public Works Director � � �V�
ATTACHMENTS: Summary Sheets APPROVED BY:
The Storm Sewer Access Charges (STAC) that the City presently collects with Building Permits
are shown in the attached literature. They range from S 1,071 per Single Family house to
57,130 per acre for Industrial property. As the attached, comparison with 4 adjacent cities
shows Rosemount is the only City that collects its Storm Water Trunk Costs at the Building
Permit stage. AU of the area cities have an Area Charge which is collected from the developer
through the final plat process. By collecting all of our costs with the Building Permit it makes
the permit costs seem high in relation to other area cities. However, in the area cities that
portion is collected from the developer prior to the builder taking out a permit.
For 1996 we have numerous options available as outlined. Staff is recommending that we
modify our present system to include Trunk Area Charges similar to adjacent communities and
to lower the Commercial and Industrial Zoned Property Trunk Fees. Staff is also recommending
that we raise the Single Family fee to match the average of the other communities in the area.
What this would do is actually lower the Building Permit cost by approximately 5500 for a
Single Family Building Permit. It also lowers considerably the Building Permit charges for the
Commercial and Industrial zoning districts. However, the amount collected will be
approximately the same due to the fact that we are collecting it from the developer at final plat.
One major advantage to collecting the fees up-front from the developer is that the City will
have in-hand, front end funding for the trunk costs for Storm Water Facilities in a project area.
When the Surface Water Management Plan is complete, these Trunk Area Charges may be
requested to be modified. However, that may take up to six months prior to approvaf by all
involved agencies.
RECOMMENDED ACTION: Discussion item only with direction to Staff.
COUNCIL ACTION:
4
� SUMMARY OF AREA CITIES
1995 STORM WATER TRUNK COSTS
COLLECTED FROM DEVELOPERS AND BUILDERS
AS OF 10-25-95
ITEM APPLE BURNSVILLE EAGAN LAKEVILLE ROSEMOUNT
VALLEY
Truck Area Charge
Collected from Developer
(Prices are per acre>:
• Single Family 2,350 5,227.20 3,310.56 4,704.48 0
• Muitiple Family 2,940 6,969.60 4,181 .76 5,227.20 0
• Public/Institutional 3,530 6,969.60 5,052.96 4,704.48 0
• Commercial 3,530 7,405.20 5,052.96 6,577.56 0
� tndustrial 3,530 7,405.20 5,052.96 6,577.56 0
Connection/Access
Charges �STAC)
Collected with Building
Permit
(Prices are per acre):
� Single Fami(y 0 0 0 0 3,213 *
� Multiple Family 0 0 0 0 5,110
� Public/Institutional 0 0 0 0 5,110
• Commercial 0 0 0 0 6,640
� Industrial 0 0 0 0 7,130
* S 1,071 per unit
The average Trunk Area Charges are as follows:
Single Family S3,898 per acre
Multiple Family $4,830 " "
Public/Institutional $5,064 " "
Commercial $5,641 " "
Industrial $5,641 " "
, ,
` PROPOSED
1996 STORM SEWER ACCESS CHARGES
Options Available:
1. Leave present system as is (coilect with Buiiding Permit) and leave fees as is
2. Same system as is but lower fees (i.e., Commercial and Industrial)
3. Modify system to include Trunk Area Charges and Lower fees to average of
area communities
4. Raise fees
5. Wait until SWMP is complete and enact changes then
Staff recommends No. 3
;
� .,�w____- . , . _;.: __ - - _ _---___
.
PROPOSED
1996 STORM WATER TRUNK COSTS COLLECTED
FROM DfVELOPERS AND BUILDERS
A. Trunk Area Charges Collected from Developers
Single Family 52,000 per acre (50.046/sf)*
Multiple Family
S2,530 " " °
Public/lnstitutionai
52,550 " " u
Commercial
�2��2� u n u
Industrial
52,820 " " "
* Gross acres of developable property minus acreage of ponding (at high water level) plus
wetlands at delineation line.
B. Connection Charges (STAC) Collected with the Building Permit
Single Family S 650 per lot
Multiple Family S 430 per housing unit (4plex=4units)
Public/Institutional 52,550 per acre of impervious acreage
'� Commercial
$2,820 u �. ,� �, «
' $2,820 � �, �� „ ,�
� Industrial
;
' These new rates shall be charged to all property other than those currently platted and also in the
planning stages incfuding Shannon Pond East, Shannon Meadows, Wensmann 7, 8 and 9,
Eastbridge PUD Single Family and Multiple Family. These fees shall not be charged to all areas on
which the property owner provides treatment of surface water through an MPCA approved
treatment plan or plant and which an NPDES Permit is in place.
'�';